Fontaine Avenue Streetscape Improvements
PLACE Meeting #2
July 18, 2019
In Conjunction With
![Page 2: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/2.jpg)
Agenda
▪ Project Overview
▪ Meeting Updates
▪ Speed Data
▪ Public Workshop #2 Recap
▪ Preliminary Concepts and Design Development
▪ Next Steps
▪ Adjourn
2
![Page 3: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/3.jpg)
Project Overview
![Page 4: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/4.jpg)
▪ Project Area as defined by the project SMARTSCALE application
Project Area
![Page 5: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/5.jpg)
Project Budget
▪ PE (Survey, Environmental, Design)= $1,200,000
▪ RW (Right of Way and Easement
Acquisition, Utility Relocation = $3,700,000
▪ CN (Construction, Oversight,
Inspection, Contingencies) = $6,800,000
▪ TOTAL PROPOSED PROJECT FUNDING = $11,700,000
▪ Project Is Fully Funded Through Smartscale (HB2)
![Page 6: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/6.jpg)
Initial Project Schedule
•Data Collection
•Traffic Analysis
•Alternative Concepts
CONCEPTUAL DEVELOPMENT
•Refine Concepts
•Prepare 30% Plans
•Agency Review
PRELIMINARY DESIGN
•Prepare 60% Plans
•Incorporate Feedback
DESIGN DEVELOPMENT
•Request Right of Way Authorization
•Utility Relocations
•Easements
RIGHT OF WAY AND UTILITIES
•Prepare 100% Plans
•Coordinate Bid Package
•Final Agency Review
•Request Authorization for Construction
FINAL DESIGN
•Advertise for Contractor
•Complete Bidding Process
•Prepare Contract
•Award Contract
ADVERTISEMENT AND BIDDING
CONSTRUCTION PHASE
Fall 2018 –Spring 2019
Spring 2019 - Fall 2019
Fall 2019 –Winter 2020
Winter 2019 – Winter
2020
Winter 2020 – Fall 2021
Fall 2021
Winter 2021
![Page 7: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/7.jpg)
Meeting Updates
![Page 8: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/8.jpg)
Meeting Updates (Since PLACE Meeting #1)
▪ 3/14/19 - PLACE Task Force Meeting #1
▪ 3/25/19 - Steering Committee Meeting #3
▪ 4/18/19 - Public Open House #2
▪ 6/21/19 – Technical Committee Meeting #2
▪ 7/11/19 – PLACE Task Force Meeting #2
▪ 7/23/19 – Planning Commission Work Session
![Page 9: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/9.jpg)
Speed Data
![Page 10: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/10.jpg)
Speed Data
▪ Posted Speed Limit = 35 MPH
▪ Collected 24-hour speed data (by direction) near Piedmont Ave / Montpelier St on March 19, 2019
▪ Average Speed (Full Day / Off Peak)• EB = 28 MPH / 33 MPH
• WB = 27 MPH / 31 MPH
▪ How Many Cars Exceed 35 MPH?• Full Day:
EB = 5.3%
WB = 3.3%
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
<10 <15 <20 <25 <30 <35 <40 <45
Nu
mb
er o
f V
ehic
les
Speed (MPH)
EB WB
0
50
100
150
200
250
300
350
<10 <15 <20 <25 <30 <35 <40 <45
Nu
mb
er o
f V
ehic
les
Speed (MPH)
EB WB
![Page 11: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/11.jpg)
Public Workshop #2 Recap
![Page 12: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/12.jpg)
Public Open House Outreach – April 18th
▪ To Encourage Participation, Completed the Following Outreach:• Flyers to Businesses
along Fontaine Avenue
• Flyers to UVA Housing
• UVA Bus Advertisements
• Message Board in front of Fire Station (PCMS)
• Direct Mailings / E-mail
• Social Media
![Page 13: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/13.jpg)
April 18th Public Open House: Comment Form Responses
Renter/Tenant9%
Rental Property Owner
14%
Business Owner14%
Employee of UVA14%
Own Primary Residence
26%
Employee in Study Area
23%
Student at UVA0%
Commuter0%
Other0%
INTEREST IN THE PROJECT:Public Open House #2
Interest in Project PercentageRenter/Tenant 9
Rental Property Owner 14
Business Owner 14
Employee of UVA 14
Own Primary Residence 26
Employee in Study Area 23
Student at UVA 0
Commuter 0
Other 0
![Page 14: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/14.jpg)
April 18th Public Open House: Comment Form Responses
BICYCLE ALONG FONTAINE
CROSS FONTAINE (PEDESTRIAN OR
BICYCLIST)ON-STREET PARKING PUBLIC TRANSIT
WEEKLY 4 14 1 4
MONTHLY 6 6 6 5
YEARLY 5 4 1 7
NONE 13 7 23 16
HOW THE CORRIDOR IS UTILIZED
![Page 15: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/15.jpg)
April 18th Public Open House: Comment Form Responses
On-Street Parking
Dedicated Turn Lanes
Bike Lanes with Buffers
Landscaped Buffer Between Curb
Transit Drop Off / Pick Up
Wider Sidewalks
Emergency Vehicle Access
Bike Lanes
Compiled Importance
Least Important Most Important
![Page 16: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/16.jpg)
Preliminary Concepts and Design Development
![Page 17: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/17.jpg)
Design Concepts: City Limits to Summit Street
![Page 18: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/18.jpg)
Design Concepts: City Limits to Summit Street
![Page 19: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/19.jpg)
Design Concepts: City Limits to Summit Street
![Page 20: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/20.jpg)
Design Concepts: City Limits to Summit Street
![Page 21: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/21.jpg)
Design Concepts: Summit Street to Lewis Street
![Page 22: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/22.jpg)
Design Concepts: Summit Street to Lewis Street
![Page 23: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/23.jpg)
Design Concepts: Summit Street to Lewis Street
![Page 24: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/24.jpg)
Design Concepts: Summit Street to Lewis Street
![Page 25: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/25.jpg)
Design Concepts: Lewis Street to Jefferson Park Avenue
![Page 26: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/26.jpg)
Design Concepts: Lewis Street to Jefferson Park Avenue
![Page 27: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/27.jpg)
Design Concepts: Lewis Street to Jefferson Park Avenue
![Page 28: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/28.jpg)
Design Concepts: Lewis Street to Jefferson Park Avenue
![Page 29: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/29.jpg)
Design Criteria
City of
Charlottesville
Guidelines
VDOT Guidelines
(GS-5)
AASHTO
Guidelines
Proposed
Fontaine Design
Minimum Design Speed (mph) 35* 35 35 35*
Minimum Radius ** 373' 371' 373'
Minimum Stopping Sight
Distance** 250' 250' 250'
Maximum Superelevation ** 4% 4% NC
Maximum Vertical Grade 8%8%
(Rolling Terrain)
8%
(Rolling Terrain)
8%
(Rolling Terrain)
Minimum Vertical Grade - 0.30% 0.30% 0.30%
Graded Shoulder Width 2' n/a n/a n/a
Lane Width 10'-11' 11' 11' 11'
Bike Lane Width (from face of
curb without gutter)5' 5' 5' 5' (2' Buffer)
Curb Type
6" Vertical or
Combination Curb
and 18" Gutter
CG-6 Vertical 6" Vertical
Clear Zone (C.Z.) or Lateral
Offset (L.O.)2' Min.
1.5' Min.
Lateral Offset
1.5' Min.
Lateral Offset
1.5' Min.
Lateral Offset
Minimum Sidewalk Width 5'-6' 5' 4' 6'
Maximum Cut / Fill Slope 3:1 2:1 3:1 2:1
Guardrail Offset (with curb) Back of SidewalkFace of Curb / 6'
Minimum8' Back of Sidewalk
Buffer Strip for Sidewalk 3'-6' 4' 2' 6'
* Street speed limit is currently posted at 35 mph. For Neighborhood A Streets, the recommended design speed is < 25mph
** For streets with volumes over 4000 ADT, the Standards and Design Guidelines recommend using the VDOT road desgin manual
Green signifies information from the Streets at Work Manual
Blue signifies information from the Standards and Design Manual
Fontaine Avenue Streetscape
VDOT Project # U000-104-296, P101, R201, C501
VDOT UPC #10944Geometric Overview
![Page 30: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/30.jpg)
City Limits Grading
![Page 31: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/31.jpg)
City Limits Grading
![Page 32: Fontaine Avenue Streetscape Improvements](https://reader033.vdocument.in/reader033/viewer/2022051013/6276c6b6dadebb45167cb7e5/html5/thumbnails/32.jpg)
Next Steps
▪ 7/23/19 – Planning Commission Work Session
▪ Late Summer / Fall - Steering Committee Meeting #4
▪ Concept Development
www.fontainestreetscape.com