From VDC to the Digitalization of Construction
Martin Fischer Professor, Civil + Environmental Engineeringand (by courtesy) Computer Science
http://www.stanford.edu/[email protected]
§ Director, CIFE (Center for Integrated Facility Engineering)
§ Foreign Member, Royal Swedish Academy of Engineering Sciences
![Page 2: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/2.jpg)
• 100%fundedbyindustry– Buildingowners– Designandconstructioncompanies– Softwareandhardwarevendors
• 1988-2000– BuildingInformationModeling
(BIM)
• 2000-2010– VirtualDesignandConstruction
(VDC)
• 2010+– OptimizeFacilityPerformance
2
![Page 3: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/3.jpg)
VDCCertificateProgramGraduatesAwardCeremonyonSept.6,2016inSola,Norway
![Page 4: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/4.jpg)
Last Modified 8/15/2016 5:47 P
M P
acific Standard Tim
eP
rinted 8/12/2016 9:10 AM
Central S
tandard Time
4McKinsey & Company
Construction labour productivity has not kept pace with overall economic productivityLabor productivity (gross value added per hour worked, constant prices1)
SOURCE: OECD Industry Stats (http://stats.oecd.org)
1 Based on 2010 prices
$57 trillion of infrastructure investments required by 2030 (McKinsey Global Institute)
Data from Roberto Charron, McKinsey and Paul Teicholz, CIFE
![Page 5: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/5.jpg)
Last Modified 8/15/2016 5:47 P
M P
acific Standard Tim
eP
rinted 8/12/2016 9:10 AM
Central S
tandard Time
5McKinsey & Company
Challenges affecting the construction sector
Internal challenges
▪Shortfalls in accountability▪Talent management▪Reinventing the wheel▪Failure to adapt to new technology▪Coping with complexity
External challenges
▪Fragmented value chains▪Extensive subcontracting▪Complex portfolios▪Competitive pressure
Data from Roberto Charron, McKinsey
![Page 6: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/6.jpg)
©2016
We still produce too much rework …
![Page 7: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/7.jpg)
©2016
… and work too inefficiently
![Page 8: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/8.jpg)
©2016
Would your projects benefit if …Everyone is working on the right tasks at the right time all the time.
We are designing what the client wants.
We will be productive as possible next week.
We are certain that everything fits.
We are sure that we are building everything safely and with the best methods.
We are installing everything fast and right the first time.
We are installing everything accurately based on the latest, correct information. Paper-free.
We gave the client exactly what he wanted.
![Page 9: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/9.jpg)
©2016
What capabilities have really changed in the last decade?
Digital modeling
Amount of data we can handle
Communication
Pictures courtesy SPS, Beck, and DPR
![Page 10: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/10.jpg)
©2016
Illustrations of good VDC practice
Pictures courtesy DPR
![Page 11: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/11.jpg)
©2016
Would your projects benefit if …Everyone is working on the right tasks at the right time all the time.
We are designing what the client wants.
We will be productive as possible next week.
We are certain that everything fits.
We are sure that we are build everything safely and with the best methods.
We are installing everything fast and right the first time.
We are installing everything accurately based on the latest, correct information. Paper-free.
We gave the client exactly what he wanted.
![Page 12: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/12.jpg)
©2016
VDC method to give the client everything he wants
Open whole scope of hospital on budget and 30% earlier than typical
Highly reliable construction
Combine everyone’s
detailed design
Everyone works with the same plan
Confirm constructability of detailed design
![Page 13: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/13.jpg)
©2016
VDC Overview Client Business
Objectives
ProjectObjectives
IntegratedConcurrent Engineering
(ICE)
Product ModelingBIM++
ProjectProduction
Management
![Page 14: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/14.jpg)
©2016
Client/Business Objectives
ProjectObjectives
IntegratedConcurrent Engineering
(ICE)
Product ModelingBIM++
Process ModelingProduction
Management
WHY is the client doing the project?
WHAT does the project team need to achieve?
HOW is the project team accomplishing the project objectives?
BUILDING PERFORMANCE• Usable • Operable• Sustainable
PROJECT PERFORMANCE• Buildable
Safety, Budget, Schedule, Quality
PROCESS PERFORMANCE• Production metrics
• Controllable factors of production
![Page 15: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/15.jpg)
©2015
Vivienda Multifamiliar “Residencial Varela”
Javier OtinianoProject ManagerPROYEC Contratistas Generales S.A.
Monthly Report N° 6Date: 3 May. 2016
Example of Application of VDC on a Multi-Family Housing Project in Lima, Perufrom the CIFE-SPS VDC Certificate Program Implementation Phase
![Page 16: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/16.jpg)
©2015
USING THE BIM FOR INSTALLATION OF PRECAST SLABS IN BASEMENT CEILING (FLOOR PARKING)
PRECASTSLABMODULESACCORDINGTOTHESECTORIZATION“7SECTORS”
- INSTALLATIONTIMEOFPRECASTSLABS:8-10minc/u
- INSTALLATIONTEAM:3People
![Page 17: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/17.jpg)
©2015
$.1,742.00
$.373.00
$.8,430.00
$.5,411.00
0100020003000400050006000700080009000
ConcreteSavings Steel1/4"Savings JoistandFlooringBlocksSavings
SavingsinPlastering,painting,ceiling
(basementceiling)
$.8,873.00
$.2,159.00
0
2000
4000
6000
8000
10000
LightenedPrecastSlabs SolidPrecastSlabs
ECONOMICBENEFIT/ITEMSFORUSEOFPRECASTSLABS
$. 15,956.00
$. 11,032
( - )
E C O N O M I C B E N E F I T F O R U S E O F P R E C A S T S L A B S
$. 4,924.00
D I R EC T CO S T FOR U S E O F P R ECA S T S L A B S
31%savingsinstructurecost
![Page 18: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/18.jpg)
©2015
18WORKINGMEETINGSWITHTECHNICALTEAM
EVALUATINGTHE4DPLANNINGMEETING,WITHTECHNICALEQUIPMENTONTHECONSTRUCTIONSITE
PROPOSALFORIMPROVEMENTMEETING,WITHTHEDESIGNEROFTHEGASSYSTEMANDTECHNICALTEAM
![Page 19: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/19.jpg)
©2015
R E S I D E N C I A L
VARELA
CU S TOMER
CREATEVALUE
IMPLEMENTATIONVDCM A N A G E M E N T , P L A N N I N G , A N D P R O D U C T I O N P R O C E S S E S T O A C H I V E T H E T A R G E T
REDUCECONSTRUCTIONTIMEBY5%- TARGETGOAL
DESIGNERSConfirm
attendanceCheckqueries
Contributionstoimprovements
Identifydeficienciesin
design
ConveneMeeting
PresentSchedule
Contributionstoimprovements
PROJECTMANAGER
YES Makingofimprovement
metrics
BIMSUPPORT ModelPresentation
DevelopModeling
Plan
MakequeriesoftheModel
Contributionstoimprovements
NO
BIMMANAGERIdentify
deficienciesindesign
Contributionstoimprovements
Specifycontributions
Reviewbylevelsandspecialities
DecisionMaking
ICE SESSIONS
MAPPINGPROCESSES
COLLABORATIVEMEETINGS
IMPROVEMENTPROJECT
OPTIMIZEDSCHEDULED
SECTORIZATION/WORKTRAINS4DMODEL
![Page 20: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/20.jpg)
©2016
Key technology and management developmentsMobile• from just-in-case to just-the-right informationCloud• anytime (push and pull, bi-directional, ”unlimited”)Parallelization• fastLocation / dimensional measurement• accuracy, dimensional control, off-site / on-siteMachine learning• experience and dataRobotics, additive manufacturing• virtual ßà real, safety, environmental impactInternet of Things (IoT)• virtual ßà realVirtual Environments• test!Collaboration• concurrent knowledgeLean• lower uncertainty, lower risk, customer, pull, purpose à value
![Page 21: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/21.jpg)
©2016
Wake-up CallsThe following slides show several innovations that show dramatic improvement opportunities.
![Page 22: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/22.jpg)
Daily Process & Feedback Loop
einsite
• Create Material Requests for planned work on SiteMan App
• Write Requests on Smart Card
• Collect Material at Plant
• Data captured by Cabin Controller and Vehicle Unit
• Verify at Weigh-Station• Data captured by
Cabin Controller and Vehicle Unit
• Drop material at work-site, and perform work using relevant machinery
• Acknowledgement made by supervisor ID card on device • Enter Daily Progress
Reports• Entries cross checked
with device Data
u All data and activities verified by Device based Locational and Transactional Data, in the context of the project plan and operations
u Reduced data-entry (only once at start and end of day)u Minimal Training required
• Whole day’s activity visualized and analyzed on Software portal
• Work plan for next day created based on recommendations by Einsite
START OF DAY
END OF DAY
Anirudh Reddy
![Page 23: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/23.jpg)
©2016
Fully automated design of a house from a sketch (elilbre)
![Page 24: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/24.jpg)
©2015
R E D U C I N G T H E C O S T O F S T E E L S T R U C T U R E S U S I N G C OMPU TAT I O N A L D E S I G N O P T IM I Z AT I O N
Wo r k b y F o r e s t F l a g e r i n C o l l a b o r a t i o n w i t h A r u p a n d J o h n H a ym a k e r
conventionaldesign method
FCD (128 cpu)
design method
PROCESS
Design cycle time 4 hrs 3 secAlternatives evaluated 39 12,800
Total design time 216 hrs 151 hrs
PRODUCT
Total steel weight2,728 met t 2,292 met t
Est. cost saving (USD)
- $4 M (-19%)
CASE STUDY RESULTS
GEOMETRIC MODEL
GEOMETRICMODEL
OPTIMIZESHAPE
ANALYTICMODEL
OPTIMIZESIZING
1
BiOPT METHODhttp://cife.stanford.edu/sites/default/files/TR202.pdf
DESIGN PROBLEM
2
3
4
FCDSizingAlgorithmhttp://cife.stanford.edu/sites/default/files/TR201_0.pdf
SEQOPTAlgorithm(Booker,etal.1999)
• Ordersofmagnitudereductionindesigncycletime
• Evaluationofagreaternumberofdesignalternatives
• Improvedproductquality
Objective:Minimizesteelweight
Constraints:Safetyandserviceability
Possibledesignalternatives:~102435Variables:1955sizeandshapevariables
![Page 25: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/25.jpg)
Copyright Ó 2016CIFE 2016
Original Frame Value-Engineered FrameSteel Weight - +8%
Total Cost - -13%Procurement Time - -20%
A Tale of Two Moment Frames
W14X176
W24X117W18X86
W14X132
W14X233
Doubler Plate
3 Continuity Plates
KEY
Work by Forest Flager, Pratyush Havelia, Henry Hamamji, Filippo Ranalli, Bo Peng, Thomas TrinelleIn collaboration with SOM, Herrick, Autodesk
![Page 26: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/26.jpg)
Copyright Ó 2016CIFE 2016
Steel Frame Cost Components
Material 27%
Fabrication
Erection
Other
DESIGN DECISION BASIS
SUPPLY CHAIN EXPERTISE
Design Cycle: 8-24 weeks
![Page 27: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/27.jpg)
©2016
Automatic as-built BIM from laser scans
In collaboration with Iro Armeni, Silvio Savarese, Amir Zamir, and Ozan Sener
![Page 28: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/28.jpg)
©2016
“Theautomatedexecutionofprocesseschangeseverything.”(AlanPerlis,1961)
![Page 29: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/29.jpg)
Flow-based Construction Site Management
September 2016
N E L LY G A R C I A - L O P E Z
I N C O L L A B O R AT I O N W I T H G R A Ñ A Y M O N T E R O
![Page 30: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/30.jpg)
Case study: Applying the flow-based site management method
Project info:• Graña y Montero jobsite in Peru• 11 basements + 21 floors• 18-week period (8 weeks on site)• Structural phase
Objectives:1. Can the flow-based model
represent the look-ahead plan?
2. Does the method help field managers make decisions during look-ahead and daily planning?
![Page 31: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/31.jpg)
Case study project adopted best practices for production planning
Master plan• Processes• Gross
constraints
Takt plan• Sector
definition• Quantities• Trade
sequence• Crew
balancing
Look-ahead plan• Constraints
analysis• Productivity• PPC +
reasons
Daily plan• Quantities• Productivity• Daily PPC• Visual
planning
![Page 32: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/32.jpg)
Example of daily plan
32
19th floor
18th floor
RiskTimeCrew (type & number)Activities
![Page 33: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/33.jpg)
So, why was it so difficult for the project team to stick to the plan?
Video link: https://youtu.be/sT6kkvE2WXU
![Page 34: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/34.jpg)
Activities require a set of flows to start execution
34
Activity
Koskela (1999)
Labor
Workspace
Precedence
Materials/components
Information
Equipment
External(Permits,inspections)
FlowKey:
![Page 35: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/35.jpg)
Existing construction models do not formally represent, track, or quantify the activity flowsExisting transformation view
Build deck
form A1
Install slab
rebar A1
Pour slab A1
Build deck
form A2
Install slab
rebar A2
Pour slab A2
What flow?
What caused delay?
Did one of these flows fail?By how much?
Was it something else? Are we representing all the flows?
How are these flows affected?
∆
![Page 36: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/36.jpg)
Existing construction models do not formally represent, track, or quantify the activity flows
36
Proposed flow view
Build deck
form A1
Install slab rebar
A1
Pour slab A1
Build deck
form A2
Install slab rebar
A2
Pour slab A2
What flow?What caused the delay?
Did one of these flows fail?By how much?
How are these flows affected?
∆
Labor
Workspace
Precedence
Materials/components
Information
Equipment
External(Permits,ispections)
FlowKey:
Concrete crew idle
Steel crew availability
Are we representing all the flows?
![Page 37: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/37.jpg)
Weekly data collected by the app
Aggregate metrics
WIP
Aggregate activity statuses
10 variables
Activity metrics
Activity info
Activity execution variability
17 variables
Flow metrics
Flow info
Flow execution variability
24 variables
High level of detail data about the plan, its execution, and reasons for variability
![Page 38: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/38.jpg)
GyM case study data (18 weeks)Total Per week
# Activities 1,153 64# Flows 4,192 232# Data points 415,008 23,056
Large dataset for supporting:
Performance analyticsPredictive models
(data mining + machine learning
Total additional data collection effort: 45 hours
![Page 39: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/39.jpg)
Feedback from field management team“The analytics allow me to dig deeper into the design of the production system … [and] which teams have the best and worst performance.” Project Superintendent
“Keeping track of the historical flow performance is key. We might have a hunch about what flows are consistently late, but we don’t have the data to identify performance issues.” Project Engineer
“It’s very useful that we now have a tool that formally maps the flows that are needed to execute an activity … we think about these things, but there is no formal tool that allows us to check that all the flows are ready so the activity is not in danger.” Project Engineer
![Page 40: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/40.jpg)
©2016
It’snotexperienceOR data
it’sExperienceAND data
![Page 41: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/41.jpg)
©2016
I have made all my generals out of mud. Napoleon
![Page 42: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/42.jpg)
©2016
• Rapidly understand target, team, roles, progress, obstacles, challenges
• Frequent communication, feedback
Interact in a virtual
environment
Screenshots courtesy Brandon Fischer
![Page 43: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/43.jpg)
©2016
Tor
Steinar
Gunnar
Scaffolding
82%/100% 1,640kg / 2,000kg
200kg/150kg
70kg/100kg
54 #8, 5m
![Page 44: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/44.jpg)
©2016
The future looks different, but the future is now
Strategic Implications
Ø Projects vs. Corporate
Ø Staff Development
Ø Partners
44
![Page 45: From VDC to the Digitalization of Construction1g3wsovzb9d25b6dr2wrklqe.wpengine.netdna-cdn.com/... · From VDC to the Digitalization of Construction Martin Fischer Professor, Civil](https://reader033.vdocument.in/reader033/viewer/2022042102/5e7f1e8042fc3202a25acd4d/html5/thumbnails/45.jpg)
©2016
Do you want to continue to be a player or become a spectator?