Design Optimization for Dadant Product Work CellsBridgeway | Group #2
Students: Arielle Anderson-VenerableJordan PalmerKelsey Schreiber
Advisor: Prof. Sewoong Oh
Contact: Tammy DiefendorfScott TeelBrittany Aten
1
![Page 2: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/2.jpg)
OverviewBridgeway Introduction
Dadant & Sons
Assembly Tasks
Problem Statement
Objectives
Air Flow and Drying Options
Systematic Layout Planning
Line Balancing Analysis
Economic Analysis
Conclusions and Recommendations
Q & A
2
![Page 3: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/3.jpg)
“Creating Solutions for Everyone.”
Affirmative Employment ServicePhysical and/or mental disabilities
Consumer vs. Productionist
Contract Work Dadant & Sons -- Beekeeping Supplies
3
![Page 4: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/4.jpg)
Production Overview
Final Assembly and Packaging
4
Frame Production
Hive Body Production
Shipping Box Construction
![Page 5: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/5.jpg)
Frame Production (1 of 2)
5
![Page 6: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/6.jpg)
Frame Production (2 of 2)6
![Page 7: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/7.jpg)
Hive Body Production (1 of 3)
7
![Page 8: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/8.jpg)
Hive Body Production (2 of 3)
8
![Page 9: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/9.jpg)
Hive Body Production (3 of 3)
9
![Page 10: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/10.jpg)
Final Assembly and Packaging
10
![Page 11: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/11.jpg)
Problem StatementImprove efficiency of facility layout
Reduce non-value added work & work in process
Decrease drying time for painted/primed hive bodies
11
![Page 12: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/12.jpg)
Objectives
Conduct time studies
Use Systematic Layout Planning (SLP)
Line Balancing Analysis
Establish and improve paint/primer drying time
Conduct economic analysis
Recommend improvements
12
![Page 13: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/13.jpg)
Paint Drying - Current State13
Primer Paint
Bridgeway Estimate 175 min - Overnight* 55 min - Overnight*
Label Estimate 60 min 60 min
*Current drying time highly variable due to environmental conditions.
![Page 14: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/14.jpg)
Paint Drying - Environmental Improvements Move drying into paint room
Temperature Control
Dehumidifier
Air Ventilation
14
[Ivation 2016, Vornado 2016]
![Page 15: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/15.jpg)
Paint Drying - Systematic Improvements
● Digital/Kitchen Timers● Dry Erase Time Notation● Time Stamp Labeling
15
[Amazer 2016, Cosmos 2016, Demarkt 2016]
![Page 16: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/16.jpg)
SLP- Introduction
Quick material flow
Less WIP
Reduced handling
Subjective -> objectiveFlowPlanner
16
[Muther 1973]
![Page 17: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/17.jpg)
SLP- Flow Planner Initial Analysis17
● Product/Part Routes Mapped in AutoCad● Routes along Aisles● Wage and Walking Speed along paths● Aggregate per Monthly production
![Page 18: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/18.jpg)
SLP - AEIOUX Analysis18
![Page 19: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/19.jpg)
SLP - Design and Analysis Phase Used AEIOUX to guide design of new layouts
Maximize A, E, and I relationships
Analyze layouts in FlowPlanner
19
![Page 20: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/20.jpg)
SLP- Consulting with Bridgeway
● Selected layout 4● Not most Efficient but…
○ Sound Accommodations
20
![Page 21: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/21.jpg)
SLP - Layout Implementation
21
![Page 22: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/22.jpg)
Balance workload among workstations
Decrease Idle Time
Decrease work pile-ups
22
Line Balancing- Introduction
![Page 23: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/23.jpg)
Line Balancing- Unique Challenges
Typical Line Balancing
Involves assigning different tasks to same workstation or worker to balance workload
The Challenge
Consumers and Productionists are limited to very specific tasks based on abilities
23
![Page 24: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/24.jpg)
Line Balancing- Typical Method24
● A new unit enters next workstation every 15 minutes● Number of tasks/worker varies
![Page 25: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/25.jpg)
Line Balancing- Alternative Approach
25
● A new unit enters the next workstation every 5 minutes● Number of workers/task varies
![Page 26: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/26.jpg)
Line Balancing- Precedence Diagram
26
Must happen 10 times before next step:Total Time = 8.7 minutes
![Page 27: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/27.jpg)
Line Balancing Summary
66% consumer employment increase
Minimum Cycle Time: 2.31 minutes
Constraint: Hive Body Construction
27
![Page 28: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/28.jpg)
Economic Analysis
Initial Cost: $1,629.00
Monthly Savings: $2,593.00
Monthly Recurring Costs: $24.00
Payback Period: 19 days
Monthly IRR: 155%
Yearly IRR: 1633%
28
![Page 29: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/29.jpg)
Economic Analysis- Supply Increase
97 bodies per day → 2143/month
Current average: 1664/month
Revenue increase: $2,933.00Total increase: $5,526.00
54% increase in average hive body revenue
29% increase in product throughput
29
![Page 30: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/30.jpg)
ConclusionsLoss of profit each month due to
layout
Hive body drying process is long
Bridgeway's supply from Dadant is inconsistent
30
![Page 31: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/31.jpg)
RecommendationsDesign
Drying Room
Dadant supplies
31
![Page 32: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/32.jpg)
Questions?
32
![Page 33: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/33.jpg)
Option #1
33
![Page 34: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/34.jpg)
Option #2
34
![Page 35: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/35.jpg)
Option #3
35
![Page 36: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/36.jpg)
Option #4
36
![Page 37: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/37.jpg)
Option #5
37
![Page 38: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/38.jpg)
Budget/Economic Analysis
Grant-based funding
Non-profit organization
Previous work with Dadant & SonsNon-standard payment setup
Short-term loss for long-term success
Supply restrictions
38
![Page 39: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/39.jpg)
Project Constraints
There are some constraints that the project team must account for, including: 1. Tasks, and how they are completed, must remain the same. Both consumers and
productionists are trained by an outside team, and restructuring training and specific tasks is not an option.
2. Productionists must complete all steps involving the movement of materials around the plant.
3. Frame stapling and box hammering must be kept away from the office as they interfere with communication.
4. Stapling equipment is not owned by Bridgeway, and thus is not eligible for possible design updates.
39
![Page 40: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/40.jpg)
Flow Planner - Aisle Routes (Large Hive Bodies)
40
![Page 41: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/41.jpg)
Flow Planner- Direct Paths (Large Hive Bodies)
41
![Page 42: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/42.jpg)
Flow Planner- Configuration,1 (Large Hive Bodies)
42
![Page 43: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/43.jpg)
Flow Planner- Configuration.2 (Large Hive Bodies)
43
![Page 44: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/44.jpg)
“Creating Solutions for Everyone.”
Est. 1993
Affirmative Employment ServicePhysical and/or mental disabilities
9000 people employed/served per year
Contract Work
44
![Page 45: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/45.jpg)
Project Location | Macomb, IL.
45
Production Areas
Storage
Storage
StorageArea
![Page 46: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/46.jpg)
Air Flow/Drying
46
![Page 47: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/47.jpg)
Space for Temporary Jobs
47
![Page 48: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/48.jpg)
Work in Process
48
![Page 49: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/49.jpg)
Drying Room Stairs
49
![Page 50: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/50.jpg)
Project Gantt Chart50
![Page 51: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/51.jpg)
Work Flow51
![Page 52: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/52.jpg)
SLP - Noise Constraints52
![Page 53: GE 494 Final Presentation](https://reader035.vdocument.in/reader035/viewer/2022062218/58998aa31a28abb97c8b7de9/html5/thumbnails/53.jpg)
ISO Certification
Provide guidelines that can be used consistently to ensure that materials, products, processes and services are fit for their purpose
21000+ standards (for purchase)
Ensure products and services are safe, reliable, and good quality
Reduce costs by minimizing waste and errors, and increasing productivity