Gower Facility PlansDecember 18, 2012
Gower Middle Improvements
• 3 Science Classrooms—Grades 6, 7, & 8
• New Gym, Locker Rooms, Weight/Fitness Room
• Industrial Technology, Family & Consumer Sciences, and Art
• Lighting and Ceiling Tiles Updates
• Cafeteria Remodeled
• Athletic Fields
• Classroom Casework (cabinets and shelving)
• Entrance Vestibules at East and West Doors
• Improved Parking and Traffic Flow
Gower Middle: 2013 - 2014
Gower Middle Athletic Fields
Entrances
Gymnasium
Locker Rooms
Weight/Fitness Room
Science Classrooms
Industrial Technology
Industrial Technology
Family & Consumer Science
Family & Consumer Science
Art Classroom
Art Classroom
Gower West Improvement
• 2 Early Childhood Classrooms
• Removal of Asbestos Tile in East Classrooms
• Replacement of Flooring in East Classrooms
• Pavement Replaced on West Playground
• Fencing Added to West Playground
• Art Room Storage and Shelving
• Lighting and Ceiling Tile as Needed
Gower West 2013- 2014
Early Childhood Classroom
Early Childhood Classroom
Timeline
• January 14 Bid Invitations Published
• February 19 Bid Approval
• March 1 Excavation for GM Gym and Addition Begins
• March 25 Asbestos Abatement at GM
• June 3 Interior Work at GW & GM Begins
• September 1 Substantial Completion at GW & GM