Gujarat Solar Park World’s first Multi developer, Multi facility, Multi
Technology and Multi beneficiary solar park At Charanka Village, Dist Patan - Gujarat
1
![Page 2: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/2.jpg)
Gujarat Solar Park…. What it means ?
• Multi Developer • 21 Developers from India and abroad have already commissioned the project totaling to 224 MW • With varied capacities ranging from 1 MW to 25 MW
• Multi Technology • Thin Film PV Technology • Crystalline Silicon Technology • Tracker based technology
•Multi Facility (Facilitated by GPCL – Nodal Agency) • Requisite size Plot Allotment • Approach & Access Roads • Smart Power Evacuation network up to the Project premises • Water Supply System etc
![Page 3: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/3.jpg)
Project Location Charanka Village, Santalpur
Taluka, Patan District, Gujarat
The
Site
Radhanpur
Santalpur
Kutch Branch
Canal
Little Runn
of Kutch
Charanka
Village
Nearest Urban
Area: Radhanpur
Nearest NH: NH 15
@ 20 km
Nearest Rly
Station: Santalpur
• Total Identified Land by GPCL:
~ 2,500 Ha
• Land Selected for the
Proposed Park: ~ 2000 Ha
• Ownership: ~ 60% Govt.
Land (mostly wasteland) 3
![Page 4: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/4.jpg)
Basic Facilities available…..
Roads uptp Plot
Raw Water Pipeline
Water Treatment Plant
Water Distribution Network
Water Tank (GLSR/OHT)
400/220/66 KV & 66 KV Auxiliary SS
Ready to Use Construction Power Distribution Network
Telecom (Broad Band) Network
Fencing to Solar Park(Boundary)
Security Towers
Availability of Construction Power
Wide ( Highway standard ) Approach Road
Power Evacuation at Door step of Plot
Proper Entrance Gate
Helipad
Solar Park Administrative Office
24 Hrs Solar Park Security
Single window facility for
Canteen facility
Medical Facility ( In near future)
![Page 5: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/5.jpg)
In addition , Gujarat Solar Park will
facilitate …..
Ready to Use Contour data of Land allotted
Soil Investigation Data
Past two year actually measured Solar Radiation Data
Past two year actually measured Weather Data
Quick delivery of Ready to use plot
Provide facilitation to avail Construction Power
Provide facilitation to avail Power Evacuation System at Door step of Plot
Allow to create charge on the plot allotted to avail bank loans
Facilitate developer to receive necessary clearance from State / Central Government
![Page 6: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/6.jpg)
Master Plan
6
Patrolling road
Internal roads
Nala
Reservoir
Water Pipe Line
Envisaged Capacity:
500MW
Present Installed
Capacity: 224 MW
No. of Developers : 21
Well defined Plot
Allotment Policy and
timely allocation of plots
to developers
![Page 7: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/7.jpg)
Infrastructure development - Roads
Before After
Existing Charanka- Fangli – Jamwada village road is upgraded to 10 m wide approach road.
![Page 8: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/8.jpg)
Existing simple earthen dam is converted to RCC dam
Capacity – 8 Lakh m3
Can provide water for irrigation to 300 Ha land – double cropping
Infrastructure Development - Water Reservoir
Before After
![Page 9: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/9.jpg)
Existing simple culvert is converted to RCC weir cum culvert channeling water through RCC canal
Infrastructure Development - Culverts
Before After
![Page 10: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/10.jpg)
Adoption of Innovative scheme of loop in loop out at 66 KV level,
400 x 200 x 66 KV substation is set up for evacuation of power
Infrastructure Development - Power
Before After
![Page 11: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/11.jpg)
Other Infrastructure Development
Canal Street Lights Water supply pipeline
Continuous supply of water: Water supply pipeline is provided along canal from KBC to Water Reservoir
HDPE pipeline to prevent corrosion due to high
chloride and sulphate in soil
Astronomical switches for switching automatically.
Provision of two channel switches for timely switching
![Page 12: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/12.jpg)
Pilot scale of 4.2 MW Windmill Implemented at Solar Park
Solar – Wind Hybridization
![Page 13: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/13.jpg)
Gujarat Solar Park - National Award Winner
![Page 14: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/14.jpg)
Other Prestigious Awards to Gujarat Solar Park
Project Management Institute (PMI)
"Best Project of the Year Award - Medium Term Duration (1 to 3 years)"
![Page 15: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/15.jpg)
Other Prestigious Awards to Gujarat Solar Park
National Award, 2012 by CII Category: Most Innovative Environmental Project.
Inter Solar Awards 2012 Category: Utility-Scale Projects
6th Enertia Awards 2012 Category: Power Generation Awards - Renewable Energy - Solar"
14th Power India Awards - 2012 “Special Merit Certificate" to Gujarat Solar Park Project Management Awards - 2012 “Best Project of the Year Category“ – Medium Term
![Page 16: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/16.jpg)
Media Reviews for Gujarat Solar Park
![Page 17: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/17.jpg)
Gujarat Solar Park at Glance
![Page 18: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/18.jpg)
Panoramic View of Gujarat Solar Park
19
![Page 19: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/19.jpg)
Aerial view of Gujarat Solar Park
Aerial View of Solar Project Development
Aerial View of Observatory Deck for 360 Degree View
![Page 20: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/20.jpg)
Night View of the Observatory Deck
![Page 21: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/21.jpg)
![Page 22: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/22.jpg)
![Page 23: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/23.jpg)
![Page 24: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/24.jpg)
25
Future Generation is eyeing to you for next generation technology for their
energy security…..
So…..
![Page 25: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/25.jpg)
Don’t hesitate
Come &
Just plug your solar project in Asia’s largest Solar Power Park
![Page 26: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity](https://reader031.vdocument.in/reader031/viewer/2022022505/5abc8a657f8b9a24028def30/html5/thumbnails/26.jpg)
Want to know more about Gujarat Solar Park………….