Howard Middle School551 John Wesley Dobbs Drive NE, Atlanta, GA 30312
Architect Pre-Proposal BriefingAtlanta Public Schools Facilities Service Center
March 25, 2010
Facilities Services Department
September 27, 2016
![Page 2: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/2.jpg)
Project Overview
• Grades: 6 – 8
• Site Size: 7.5 acres
• Organization History: Multiple buildings. Constructed 1924 - 1967
• Status: Closed in 1976. Last operated as a high school.
• Core Classrooms: +/- 33 (existing)
• Student Capacity +/- 825 @ 25 students per classroom (current)
• Core Classrooms: +/- 55 (proposed)
• Student Capacity: +/- 1,375 @ 25 students per classroom (proposed)
• Approximate Size: +/- 121,000 sf (existing)
• Tentative Schedule: July 2018 – July 2020
![Page 3: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/3.jpg)
Project Outline
• Rehabilitation and renovation of the existing historic buildings to accommodate current middle school occupancy and function
• Construction of a historically sensitive theater addition
• Construction of a complementary new classroom / support space building
• Renovated and new classrooms, instructional support spaces and common spaces should be designed to house a population of +/- 1,375 students
• New doors, windows, roof and exterior skin
• New identity of main / public entry and bus / carpool entry
• Improved pedestrian access and flow with comprehensive ADA accessibility
• New visitor and staff parking and bus and carpool areas
• New kitchen, cafeteria and service areas
• Attention to security through environmental design
• New monument signage, exterior signage and exterior lighting
• Controlled security and access to building and main office
• New HVAC, electrical and plumbing systems
• New low voltage, data, voice, video, life safety and security systems
• New landscape, hardscape, parking and drives, fencing and gates
• New athletic field and support structures
![Page 4: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/4.jpg)
Project Location
Aerial View of Existing Site
![Page 5: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/5.jpg)
Site Plan
Existing Site Plan
![Page 6: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/6.jpg)
Floor Plans
Existing Ground Floor Plan
![Page 7: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/7.jpg)
Floor Plans
Existing First Floor Plan
![Page 8: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/8.jpg)
Floor Plans
Existing Second & Third Floor Plans
![Page 9: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/9.jpg)
Floor Plans
Existing Annex & Portable Classroom Foor Plans
![Page 10: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/10.jpg)
Project Photo
Front Elevation from Street
![Page 11: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/11.jpg)
Project Image
1924 Rendering of Proposed Auditorium
![Page 12: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/12.jpg)
Project Photo
West Elevation
![Page 13: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/13.jpg)
Project Photo
Courtyard Elevation
![Page 14: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/14.jpg)
Project Photo
East Elevation
![Page 15: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/15.jpg)
Project Photo
East Elevation
![Page 16: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/16.jpg)
Project Photo
Typical Classroom
![Page 17: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/17.jpg)
Project Photo
Gymnasium
![Page 18: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/18.jpg)
Project Photo
Gymnasium Entry
![Page 19: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/19.jpg)
Project Timeline (Tentative)
• Architect RFP Issued Sep 20, 2016
• Architect Pre-Proposal Briefing Sep 27, 2016
• Site Inspection Sep 30, 2016
• Architect Proposals Due Oct 20, 2016
• Architect Presentations TBD
• Select Architect TBD
• Draft Design Narrative TBD
• Project Committee Meeting TBD
• Request for Proposal out to CMs TBD
• Construction Documents Complete Oct 01, 2017
• Recommend CM to Board May 2018
• Project Start (site work, reno and add) Jul 2018
• Project Completion Jul 2020
![Page 20: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/20.jpg)
Site Inspection Date and Time
10:00 amFriday, September 30, 2016
at the Howard Middle School Site
If you have any questions contact the Project Manager.
![Page 21: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/21.jpg)
Proposal Due Date and Time
2:00 pmThursday, October 20, 2016
at APS Facilities Service Center
![Page 22: Howard Middle School - Atlanta Public Schools · Howard Middle School ... Atlanta, GA 30312 Architect Pre-Proposal Briefing Atlanta Public Schools Facilities Service Center ... •New](https://reader034.vdocument.in/reader034/viewer/2022042311/5eda0d8db3745412b570ad5a/html5/thumbnails/22.jpg)
Questions & Answers
During Construction progress reports for the Howard Middle School can be accessed at:
http://www.atlanta.k12.ga.us