HUAWEI RTN
IMPLEMENTATION PROTOCOL
Site Code local: SiteA#(Fill in your site code plus candidate after the colon and change it in the Header and Footer as well)
Site Code far end: SiteB#(Fill in your site code plus candidate after the colon and change it in the Header and Footer as well)
Job number: JobNr#(Fill in your job number after the colon and change it in the Header and Footer as well)
File name Created by Approved Date
document.doc Alcatel Lucent Schweiz AGNetwork Rollout Mobile Peter Schippel 18.07.2011
MICROWAVE EQUIPMENT
Microwave Equipment Site Code: SiteA#HUAWEI RTN Site Code B-side: SiteB#
Job number: JobNr#
TABLE OF CONTENTS
1 INSTALLATION AND VERIFICATION DOCUMENTATION.................................................3
2 INDOOR UNIT INSTALLATION..........................................................................................42.1 SYSTEM CONFIGURATION AND CHARACTERISTICS..............................................................42.2 INDOOR UNIT INSTALLATION.............................................................................................52.3 TRANSMISSION CABLING CHECKLIST.................................................................................52.4 INDOOR UNIT GROUNDING...............................................................................................52.5 INDOOR INSTALLATION CHECKLIST....................................................................................62.6 SUPERVISION/RTN-FILES LOADED...................................................................................72.7 IP-ADDRESS INDOOR UNIT..............................................................................................7
3 OUTDOOR UNIT INSTALLATION......................................................................................83.1 IF CABLE INSTALLATION...................................................................................................83.2 OUTDOOR UNIT AND CABLE INSTALLATION........................................................................83.3 METHOD OF INSTALLATION (OUTDOOR UNIT).....................................................................83.4 DISH/ODU..................................................................................................................... 83.5 OUTDOOR INSTALLATION CHECKLIST................................................................................9
4 HUAWEI RTNCOMMISSIONING LINE UP........................................................................104.1 MODULATION SCHEME...................................................................................................104.2 FREQUENCY BAND........................................................................................................104.3 TX SETTINGS...............................................................................................................104.4 RECEIVING LEVEL.........................................................................................................104.5 LINK PERFORMANCE MONITORING (TIME SET 15MIN)........................................................104.6 STATISTICS AND ERROR COUNTERS...............................................................................10
5 DOCUMENTATION IN NETSITE......................................................................................11
6 Confirmation...................................................................................................................... 11
File name Created bydocument.doc Huawei
Page 2 of 13
Microwave Equipment Site Code: SiteA#HUAWEI RTN Site Code B-side: SiteB#
Job number: JobNr#
1 INSTALLATION AND VERIFICATION DOCUMENTATION This HUAWEI-RTN Link is Installed and Commissioned according to the following Site Specific Documentation:
OptiX RTN 910 Radio Transmission System IDU Quick Installation Guide (Indoor)(V100R003_05) HUAWEI
OptiX RTN 950 Radio Transmission System IDU Quick Installation Guide (Indoor)(V100R003_05) HUAWEI
OptiX RTN 980 Radio Transmission System IDU Quick Installation Guide (Indoor)(V100R003_05) HUAWEI
RTN 910 IDU Quick Installation Guide for Outdoor Cabinets (APM30H&TMC11H Cabinets)(V100R003_01) HUAWEI
RTN 910 IDU Quick Installation Guide for Outdoor Cabinets (OMB Cabinets)(V100R003_01) HUAWEI
RTN 950 IDU Quick Installation Guide for Outdoor Cabinets (APM30H&TMC11H Cabinets)(V100R003_01) HUAWEI
RTN 910 IDU Quick Installation Guide for Outdoor Cabinets (OMB Cabinets)(V100R003_01) HUAWEI
OptiX RTN 900 V100R003 Service Configuration(Weblct) HUAWEI
File name Created bydocument.doc Huawei
Page 3 of 13
Microwave Equipment Site Code: SiteA#HUAWEI RTN Site Code B-side: SiteB#
Job number: JobNr#
2 INDOOR UNIT INSTALLATION
2.1 System Configuration and Characteristics
RTN910 Classic
RTN950 Classic
RTN950A Classic
RTN905 2E Classic
CSHA Board for RTN910
CSHE Board for RTN910
CSH Board for RTN950
CSHU Board for RTN950
File name Created bydocument.doc Huawei
Page 4 of 13
Microwave Equipment Site Code: SiteA#HUAWEI RTN Site Code B-side: SiteB#
Job number: JobNr#
CSHO Board for RTN950A
RTN380Classic
RTN360 Classic
File name Created bydocument.doc Huawei
Page 5 of 13
Microwave Equipment Site Code: SiteA#HUAWEI RTN Site Code B-side: SiteB#
Job number: JobNr#
ISU2 Board
ISX2 Board
ISV3 Board
SP3S Board
SP3D Board
SL1D Board
EM6TA Board
EM6FA Board
EG4 Board
File name Created bydocument.doc Huawei
Page 6 of 13
Microwave Equipment Site Code: SiteA#HUAWEI RTN Site Code B-side: SiteB#
Job number: JobNr#
EG4P Board
AUX Board
2.2 Indoor Unit InstallationIs in accordance with the procedural document specified in section 1
2.3 Transmission Cabling Checklist
Description checkedHow many E1 are connected from IDU-Interface to DDF 16 32 48 64
E1 Test loops removed
Ethernet Cable or optical fiber among IDU, BBU, Router (if needed), [straight cable] done N/A
Notes on Transmission Cabling
2.4 Indoor Unit Grounding
Is in accordance with the procedural document specified in section 1
2.5 Indoor Installation checklist
Description Checked
General Appearance of Indoor Unit
Indoor Unit correctly labelled with Link_ID, Frequency and IP-Address
IF cable correctly marked & connected to the Indoor unit
P&E cable and outdoor optical fiber correctly marked & connected to the Indoor unit
Grounding of 19” Transmission Rack
Power cable connected to Indoor Unit
Checked Circuit Breaker Rating and Labelled at main DC supply
File name Created bydocument.doc Huawei
Page 7 of 13
Microwave Equipment Site Code: SiteA#HUAWEI RTN Site Code B-side: SiteB#
Job number: JobNr#
Cables arranged, secured to cable tray and labelled
Sync Cables on XPIC-Link connectedNotes on Indoor Installation Check
File name Created bydocument.doc Huawei
Page 8 of 13
Microwave Equipment Site Code: SiteA#HUAWEI RTN Site Code B-side: SiteB#
Job number: JobNr#
2.6 Supervision/RTN-Files Loaded
Description checked
RTN-Files are loaded to the Indoor Unit
Ethernet cabling is done a to the Switch/Router
GNOC can ping the RTN GNE if DCN is readyNotes on RTN-Supervision
2.7 IP-Address Indoor UnitIP-Address_______ . _______ . _______ . _______ . Sub-mask_______ . _______ . _______ . _______ .
2.8 IP-Address for RTN380 (E-Band) or RTN360 (V-Band)IP-Address_______ . _______ . _______ . _______ . Sub-mask_______ . _______ . _______ . _______ .
File name Created bydocument.doc Huawei
Page 9 of 13
Microwave Equipment Site Code: SiteA#HUAWEI RTN Site Code B-side: SiteB#
Job number: JobNr#
3 OUTDOOR UNIT INSTALLATION
3.1 IF Cable installation
Length (m)No. of
Grounding Kits
5D cable (up to 120m)
RG 214 cable (up to
100m)
Other (up to 300-350 m)See below
Allowed cable types:
Up to: Andrew Eupen NK Cable RFS
300 m 3/8 “ Hiflex FSJ2-50 EC2-50-HF RFF 3/8” - 50 SCF38-50 350 m 1/2 “ Hiflex FSJ4-50B EC4-50-HF RFF 1/2” - 50 SCF12-50
3.2 P&E Cable and outdoor optical fiber installation
Length (m)No. of
Grounding Kits
P&E cable (up to 100m)
Outdoor fiber (up to 150m)
3.3 Outdoor Unit and Cable Installation Is in accordance with the procedural document specified in section 1
3.4 Method of Installation (Outdoor Unit)Roof mounting Wall mounting
Tower installation Pole installation
3.5 Dish/ODU
Description checked
Dish Size 30cm 60cm 80cm 120cm
Vendor RFS Andrew
Polarisation Horizontal Vertical Dual polarization
Horizontal Vertical Dual polarization
Hardware Attenuator 10dB (52GHz) N/A 1 x 10dB 2 x 10dB
File name Created bydocument.doc Huawei
Page 10 of 13
Microwave Equipment Site Code: SiteA#HUAWEI RTN Site Code B-side: SiteB#
Job number: JobNr#
Outdoor Installation Checklist
Description Checked
General appearance of outdoor Unit
IF cable correctly marked and connected to the outdoor unit
P&E cable and outdoor optical fiber correctly marked & connected to the outdoor unit
Grounding kits are installed in the specified location
All external connectors and cables checked for correct sealing
Grounding of outdoor unit and alignment unit
Outdoor Unit is labelled, designating Direction and Link Information
File name Created bydocument.doc Huawei
Page 11 of 13
Microwave Equipment Site Code: SiteA#HUAWEI RTN Site Code B-side: SiteB#
Job number: JobNr#
4 HUAWEI RTNCOMMISSIONING LINE UP
4.1 Modulation Scheme
QPSK 16-QAM 32-QAM 64-QAM 128-QAM 256-QAM
512-QAM 1024-QAM 2048-QAM
4.2 Frequency Band
7MHz 14 MHz 28 MHz 56 MHz 250 MHz 500 MHz
4.3 TX Settings
adjusted to expected Checked
TX Frequency TXMHz# MHz TXMHz# MHz
TX Power TXdBm# dBm TXdBm# dBmTX Power Control dBm ATPC MTPC
4.4 Receiving LevelReceived Signal level should be +/- 2dB from calculated value provided by Transmission Planning.If the required level is not achievable, contact the transmission planner for further checks.
indicated expected o.k.
RX Level IndRXdBm# dBm ExpRXdBm# dBm
4.5 Link Performance Monitoring (Time set 15min)
ES Error Second Passed Ok
SES Severely Error Second Passed Ok
UAS Unavailable Second Passed Ok
BBE Background Block Error Passed Ok
OFS Out of Frame Seconds Passed Ok
5 DOCUMENTATION IN NETSITE
Implementation Protocol stored in NetSite (A- and B-End) Checked
File name Created bydocument.doc Huawei
Page 12 of 13
Microwave Equipment Site Code: SiteA#HUAWEI RTN Site Code B-side: SiteB#
Job number: JobNr#
Photos from Indoorunit, TRM-Rack and Outdoorunit/Dish stored in NetSite (A- and B-End) Checked
Photos from DDF/ODF/EDF stored in NetSite (A- and B-End) Checked
Photos from Monitor-Cabling stored in NetSite (Master) Checked
6 CONFIRMATION
This is to confirm that all of the above listed points are done in order to the current Guidelines, and that this document is filled in correctly.
ON BEHALF OF:
Implementation Subcontractor Company:
________________________________________________________________________
NAME: Klemen Kecman SIGNED: DATE:
File name Created bydocument.doc Huawei
Page 13 of 13