I-405 Sepulveda Pass Improvements ProjectCommunity Meeting April 24, 2014
1
2
Wilshire Segment
Wilshire Ramps Rendering
3N
Wilshire Segment—Extended Closures Complete
Ramp Tentative DateMaximum Duration
(Days)
WB Wilshire on-ramp to NB I-405 Complete 90NB I-405 off-ramp to WB Wilshire Complete 90SB I-405 off-ramp to WB Wilshire Complete 14EB Wilshire on-ramp to NB I-405 Complete 90
4
The closure of the eastbound Wilshire Bl on-ramp to northbound I-405 ended on November 7, 2013, marking the last of the Wilshire ramp extended closures.
Original ramp: 824 feetReconstructed ramp: 3,129 feet280% increase in capacity
Wilshire Segment—Bridges & Walls Done
5
Bridge Location Status (%)1 I-10/Exposition Bl 1002 Expo/Pico 100
3 Olympic Bl 1004 Santa Monica Bl 1005 Ohio Av 1006 SB to EB Wilshire Off 1007 NB to EB Wilshire Off 1008 EB Wilshire to NB On 1009 Wilshire Bl 10010 NB to WB Wilshire Off 10011 WB Wilshire to NB On 10012 Constitution Av 100
• Approximate total linear feet of retaining walls 17,375 ft complete
• Approximate total linear feet of sound walls 8,650 ftcomplete
Wilshire Segment—I-10 Connector Work
6
Work Completed Since January 2014• WB I-10 to NB I-405: roadway surface crack repair.• EB I-10 to SB I-405: lighting, guard rail installation, irrigation
installation.• EB I-10 to NB I-405: re-striping at tie-in.• NB I-405 to EB I-10: barrier and guard rail completion
Remaining WorkNB I-405 to EB I-10: Minor drainage work, ramp metering, and final striping.
Anticipated completion of connector work is end of April 2014.Anticipated completion of connector work is end of April 2014.
Wilshire Segment—Landscaping
7
Landscaping in Segment 1 Will Start in May 2014:• From mid-May through the end of June or early in July.
• Work will be done from south to north:• Start with landscaping by the I-10 connectors.• Reach the Wilshire/Sepulveda intersection in June.
Anticipated completion of landscaping in Segment 1 will be by the end of June or early in July.Anticipated completion of landscaping in Segment 1 will be by the end of June or early in July.
Wilshire Segment—Mainline Work
8
Northbound Mainline WorkNighttime activities to prepare the lanes for final configuration striping in the Wilshire Segment of the mainline started on Monday, April 14.
The northbound carpool lane in the Wilshire Segment is expected to open early next month.
Southbound Mainline WorkRestriping of the southbound lanes will be completed early this summer.
The southbound mainline will be striped to have four lanes under the I-10 freeway.
Pico Bl Street Work• Curb• Gutter • Sidewalk• Driveways into County parking lot
Current lane closures and work on Pico Bl are part of a City of Los Angeles project, unrelated to the I-405.
Wilshire Segment—Pico Bl
9
Project’s Pico Bl street improvements completed in early April.Project’s Pico Bl street improvements completed in early April.
Work Completed from Santa Monica Bl to Ohio AvPaving, sidewalk, curb, gutter, ADA ramp construction, street lighting
Work Completed from Nebraska Av to Santa Monica Bl• Full-depth roadway replacement• ADA ramp construction• Curb and gutter work• Sidewalk• Street lighting
Wilshire Segment—Beloit Av Improvements
10
Wilshire Segment—Cotner Av Improvements
11
Work Completed from Pico Bl to Olympic Bl• ADA ramps, mill and overlay, curb and gutter, sidewalk• Paving of Cotner Av parking lot• Construction of lot entrance to be completed by May
Work Completed from Olympic Bl to Santa Monica Bl• Sidewalk work at Olympic Bl• Full-depth roadway replacement, ADA ramp work, curb and gutter
work at Cotner/Nebraska Av intersection• ADA ramps at Cotner/Massachusetts Av• Paving just south of Santa Monica Bl
Wilshire Segment—Cotner Av Improvements (Contd.)
12
Work Completed between Santa Monica Bl and Ohio AvADA ramp work, mill and overlay at Cotner & Ohio Av
Work Remaining, just north of Santa Monica Bl and CotnerSewer line, curb and gutter work
Striping anticipated May/June 2014Striping anticipated May/June 2014
Wilshire Segment—Drainage Work (BMPs)
13
BMP Work Completed Since January:• On Cotner Av, between Pico Bl and Olympic Bl• By EB I-10 to NB I-405• By Dowlen Rd• On Beloit, between Santa Monica Bl and Olympic Bl• By SB I-405 to WB Wilshire off-ramp• West of SB I-405, under the I-10 bridge
Hydroseeding of bioswale BMPs will be done with landscaping.
Wilshire Segment—Wilshire and Sepulveda
14
Paving of the Sepulveda Bl and Wilshire Bl Intersection• On Sepulveda Bl- From northernmost GSA driveway to
approximately 500 ft north of Wilshire intersection• On Wilshire Bl- From east of Sepulveda intersection (Federal
Building sign), to the SB I-405 Wilshire ramp tie-ins on the west.
Work will consist of• Grinding existing asphalt• Top lift asphalt pavement of roadway• Traffic loops installation• Restriping of intersection to permanent alignment.
Wilshire Segment—Wilshire and Sepulveda
15
Sepulveda Bl/Wilshire Bl Intersection PavingTuesday, April 22 to Tuesday, May 6, from 10pm to 6am: • Wilshire Bl closed from Bonsall Av to Veteran Av• Sepulveda Bl reduced to one lane in each direction from
Constitution Av to 800 ft south of Wilshire Bl.
Detours• From WB Wilshire, left to SB Veteran Av, right to WB Santa Monica
Bl, right to NB Federal Av, and left to continue onto WB Wilshire Bl.
• From EB Wilshire, right to SB Federal Av, left to EB Santa Monica Bl, left to NB Veteran Av, and right to continue onto EB Wilshire Bl.
Wilshire Segment—Wilshire and Sepulveda
16
Sepulveda Bl/Wilshire Bl Intersection PavingRamp Closures• Ramp closures will begin at 8pm.• The SB I-405 off-ramp to WB Wilshire Bl will be open.
Sepulveda Bl/Wilshire Bl intersection final configuration anticipated for completion May 2014
Sepulveda Bl/Wilshire Bl intersection final configuration anticipated for completion May 2014
On-Ramp Closures Off-Ramp Closures
EB Wilshire Bl to NB I-405 NB I-405 to WB Wilshire Bl
WB Wilshire Bl to NB I-405 SB I-405 to EB Wilshire Bl
WB Wilshire Bl to SB I-405
Wilshire Segment—Constitution Av
17
Work Completed Since January• Irrigation line work• ADA ramp work
Remaining Work• Paving on Constitution/Sepulveda intersection- end of April• Crosswalk restoration- May• Signal work- May
18
Sunset Segment
Sepulveda Bl and Montana Av
Sound WallSound wall from 800 ft south of Cashmere St to Montana Av completed third week of January
Sound wall ongoing work (completion end of May):Staining of concrete slope
19
Montana Av undercrossing bridgeOngoing work (completion date end of May):
• Sidewalk• Curb• Gutter
• Traffic signal foundations• Pole installation• Phased asphalt paving
Sepulveda Bl Paving
The full-depth reconstruction (repaving) of Sepulveda Bl, between Montana Av and Church Ln was completed on Monday, April 7th, three weeks ahead of schedule.
• Final stage of street repaving is capping. Anticipated street capping May/early June 2014
• Reconstruction of Church intersection (requires a full weekend closure of Sepulveda Bl)
20
Anticipated completion May/June 2014Anticipated completion May/June 2014
Sepulveda Bl Paving (Contd.)
21
Sepulveda Bl at Montana Av looking north
Moraga Dr Ramps
Full restoration of the Moraga ramps is complete.Final restoration of Sepulveda Bl included double left-turn lanes onto the northbound Moraga Dr on-ramp from northbound Sepulveda Bl.
22
Striping anticipated May/June 2014Striping anticipated May/June 2014
Northbound on-ramp
Moraga Dr Ramps (Contd.)
23
Northbound off-ramp to Moraga Dr
Sunset Northbound Ramps
Nighttime Closures onlyNorthbound on-ramp and off-ramp to Sunset Bl for “pork chop” work at tie-in.
24
Striping anticipated May 2, 2014Striping anticipated May 2, 2014
Ongoing Work:• Backfill, electrical work, • Paving of ramp connection to shoulder • Irrigation
Sunset Southbound Ramps
Westbound Sunset on-ramp southbound-Merging• Final configuration completed April 2014• Shoulder and median work ongoing
25
Sunset Ramps—Completed Ramps
26
Sunset Bl and Thurston Av
Street improvements continue on westbound Sunset Bl and North Thurston Av. These include:• Widening of westbound Sunset Bl with right lane to Thurston-
completed
• Sign-completed
• Curb-completed
• Paving modifications- anticipated completion early June
27
Sepulveda Bl and Church Ln
Sound Wall Sound wall from Sunset Bl Bridge to Church Ln completed early February 2014
Ongoing work
• Electrical
• Irrigation
• Grading
28
Widening of Church Lane Bridge (ongoing)• Traffic on widened bridge – completed March 2014• Sidewalk, curb, gutter, lighting – currently underway• Removal of K-rail – anticipated May 2014
100 percent of all retaining walls and sound walls for the Sunset segment have been built.
29
Sunset Segment—Wall Status
10.1010.10
4.144.14
30
Sunset Segment—Bridge Status
Bridge LocationStatus
(%)
13 Montana Undercrossing 100
14 NB Sunset Off-ramp 100
15 NB Sunset On-ramp 100
16 Sunset Bl Overcrossing 100
17 Church Ln Undercrossing 90
18 Getty Center Dr Undercrossing 95
• Final striping
• Complete ramp meters
• Future signal to be installed July 2014
Upcoming Street Work• Repave Sepulveda Bl from
Getty Center Dr to southbound Getty on-ramp.
• Anticipated July 2014
Getty Center Dr Ramps Area
31
Northbound On-Ramp Upcoming Work
Sepulveda Bridge (near Getty Center)
32
Sepulveda Bridge (Bridge 19) is complete! Minor clean up work to the southbound median approach slabs.
East side of Bridge 19 crosses Sepulveda Bl
East side of Bridge 19 crosses Sepulveda Bl
Sepulveda Bridge Near Getty Center (contd.)
33
Sepulveda Bridge (Bridge 19) looking south
Wall 1862 (North of Bridge 19)
34
Workers prepare to drill a hole in wall to add drainage pipe.
I-405 Northbound Full Directional & NB 5 Lane extended closure
35
The I-405 northbound 5 lane will be closed from Sunset Bl to Moraga Dr beginning 10pm Friday, May 2 to 6am Monday, May 5. Northbound mainline lanes will be reduced to four lanes in this area.
The northbound I-405 will be fully closed nightly from Wilshire on-ramp to Getty Center Dr off-ramp: • The night of Friday, May 2, from midnight to 6am Saturday morning• The night of Saturday, May 3, from 1 to 6am, Sunday morning• The night of Sunday, May 4, midnight to 6am,Monday morning
36
Mulholland Segment
37
Mainline Median Construction
The majority of median work in Area 6 is complete
Major upcoming work:
• Southbound median on Sepulveda undercrossing approach slabs
• Sign foundation
The majority of median work in Area 7 is complete
Major upcoming work:
• Sign structure
• Pavement and barrier work
Anticipated completion May 2014Anticipated completion May 2014
Sherman Oaks Street Improvements
38
Upcoming Work• Roadway work
• Landscaping
Anticipated completion July 2014Anticipated completion July 2014
39
Southbound Valley Vista On-Ramp
Upcoming Work• Textured paving
• Metal beam guard rail
Work is 98 percent complete.
Signal work and reinstatement of left-turn lane from Sepulveda Blanticipated July 2014
Signal work and reinstatement of left-turn lane from Sepulveda Blanticipated July 2014
40
Southbound Valley Vista On-Ramp (Contd.)
On-ramp is fully operational.Anticipated completion May 2014On-ramp is fully operational.Anticipated completion May 2014
Southbound Valley Vista Off-Ramp
41
Upcoming Work Final striping ongoing; work is 90 percent complete.
Off-ramp is currently open in full capacity. Final configuration of the off-ramp will be after the median construction is complete: anticipated completion July 2014
Off-ramp is currently open in full capacity. Final configuration of the off-ramp will be after the median construction is complete: anticipated completion July 2014
Southbound Valley Vista Off-Ramp (Contd.)
42
4-144-14
5-125-12
Sepulveda Bridge (Sherman Oaks)
Sepulveda Bridge is complete. Remaining work on Sepulveda Bl will occur underneath the bridge.
43
Anticipated completion June 2014
Anticipated completion June 2014
Upcoming Work• Install joint seals• Install permanent fence• Complete wildlife crossing
Skirball Bridge
44
Anticipated completion June 2014Anticipated completion June 2014
Skirball Bridge
45
Mulholland Segment Retaining Walls
46
The majority of the retaining walls in the Mulholland Segment are complete. The remaining major wall under construction: Wall 1921
Upcoming Work•Soil nail wall: 100% complete (25% increase since January)•Architectural facing
Anticipated completion June 2014Anticipated completion June 2014
Mulholland Segment Retaining Walls
47
A natural break in Wall 1921 divides the wall into 1921 north and south. This photo, looking south, captures Wall 1921 north, as workers measure the correct position of piles (averaging approximately 27-feet tall).
Piles will serve as temporary support for the permanent drainage system.
Mulholland Segment Retaining Walls
48
Drainage pipes in the foreground symbolize the upcoming drainage system work at Wall 1921 south. Wall 1921 must be complete before Sepulveda Bl can be widened to its final configuration.
Sepulveda Bl, Mountaingate Dr, Skirball Center Dr
49
Completed:• Sepulveda Bl roadway of the northbound 2 lane• Sepulveda Bl by the southbound Skirball ramps raised to
final grade. Upcoming work:
• Storm drain work has started
• Southbound widening roadway construction
• Northbound 1 lane widening roadway construction
• Final signal configuration
• Final striping
Anticipated completion June 2014Anticipated completion June 2014
50
Southbound Skirball Ramps
Off-ramp Upcoming Work • Tie in with Sepulveda Bl
• Tie in to the mainline
Work is 85 percent complete.
On-ramp Upcoming Work• Complete tie-in to Sepulveda Bl
Work is 95 percent complete.
Anticipated completion June 2014Anticipated completion June 2014
Northbound Skirball Ramps
51
Off-ramp is open to full capacity; on-ramp is open to full capacity.
Anticipated completion April 2014
Anticipated completion April 2014
Southbound Skirball Off-ramp (Contd.)
52