![Page 1: Integrated River Engineering Project on the Danube to the ... river Engineering...• river bank restoration and reconstruction of low water regulation Aims: • increasing dynamics](https://reader033.vdocument.in/reader033/viewer/2022042215/5ebba010d69028326c456c2f/html5/thumbnails/1.jpg)
MR DI Dr. Leo GRILL Budapest, January 29th 2009
Integrated River Engineering Project on the Danube to the East of Vienna
www.donau.bmvit.gv.at
![Page 2: Integrated River Engineering Project on the Danube to the ... river Engineering...• river bank restoration and reconstruction of low water regulation Aims: • increasing dynamics](https://reader033.vdocument.in/reader033/viewer/2022042215/5ebba010d69028326c456c2f/html5/thumbnails/2.jpg)
© via donau I 2
Integrated River Engineering ProjectProject area
Project area: stream-km 1.921,0 - 1.872,7from the Freudenau Power Plant to the Austrian-Slowak border
![Page 3: Integrated River Engineering Project on the Danube to the ... river Engineering...• river bank restoration and reconstruction of low water regulation Aims: • increasing dynamics](https://reader033.vdocument.in/reader033/viewer/2022042215/5ebba010d69028326c456c2f/html5/thumbnails/3.jpg)
© via donau I 3
Low water regulation
River bed stability
Improvement ofecological functions
Improvement of fairway conditions
River bank restoration Side arm
reconnection
Granulometric river bed improvement
AIMS
MEASURES
Integrated River Engineering ProjectAims and measures
![Page 4: Integrated River Engineering Project on the Danube to the ... river Engineering...• river bank restoration and reconstruction of low water regulation Aims: • increasing dynamics](https://reader033.vdocument.in/reader033/viewer/2022042215/5ebba010d69028326c456c2f/html5/thumbnails/4.jpg)
© via donau I 4
The Integrative River Engineering Project …
• is the result of an integrative planning approach(official starting point: installation of an interdisciplinary steering committee by the bmvit in 2002)
• therefore complies with the objective of the Joint Statement• presents a living and successful example for integrative
planning for combining the needs of navigation and ecology• is honoured as best practice for integrated planning approaches
in the Joint Statement
• The process for achieving the Joint Statement was supported by the bmvit, via donau and the Danube Floodplain Nationalpark by• sending experts • hosting the first workshop in April 2007
Integrated River Engineering Project & Joint Statement
![Page 5: Integrated River Engineering Project on the Danube to the ... river Engineering...• river bank restoration and reconstruction of low water regulation Aims: • increasing dynamics](https://reader033.vdocument.in/reader033/viewer/2022042215/5ebba010d69028326c456c2f/html5/thumbnails/5.jpg)
© via donau I 5
• Environmental Impact AssessmentMarch 2006 – approx. 2nd quarter of 2009
Submission of the Environmental Impact Statement (EIS) –March 2006public edition of the EIS: December 2007 – January 2008public hearing: October 21st – October 23rd, 2008
• Afterwards: detail planning, approval and construction of the lots
• Detailed Model Studies completed• Implementation of 1:1 Pilot Projects
Pilot Project Witzelsdorf: construction work started in late2007Pilot Project Bad Deutsch-Altenburg: tender in progress; beginning of construction work is anticipated for 2009
• Integrated Monitoring-Program since 2005 and further on accompanying implementation
Integrated River Engineering Project Project status
![Page 6: Integrated River Engineering Project on the Danube to the ... river Engineering...• river bank restoration and reconstruction of low water regulation Aims: • increasing dynamics](https://reader033.vdocument.in/reader033/viewer/2022042215/5ebba010d69028326c456c2f/html5/thumbnails/6.jpg)
Pilot Project Witzelsdorfexample for combining the needs of navigation and ecology
![Page 7: Integrated River Engineering Project on the Danube to the ... river Engineering...• river bank restoration and reconstruction of low water regulation Aims: • increasing dynamics](https://reader033.vdocument.in/reader033/viewer/2022042215/5ebba010d69028326c456c2f/html5/thumbnails/7.jpg)
© via donau I 7
Pilot Project WitzelsdorfOverview
innovative groynes
river bank restorationPilot Project Thurnhaufen
![Page 8: Integrated River Engineering Project on the Danube to the ... river Engineering...• river bank restoration and reconstruction of low water regulation Aims: • increasing dynamics](https://reader033.vdocument.in/reader033/viewer/2022042215/5ebba010d69028326c456c2f/html5/thumbnails/8.jpg)
© via donau I 8
Pilot Project WitzelsdorfOverview
• stream-km 1.893,4 to 1.891,7• river bank restoration and reconstruction of low water regulation
Aims:• increasing dynamics at the riverbank• implementing innovative groynes (new shape, fewer and lower
groynes with same effect during low water conditions)• gaining building experience for the Integrated River Engineering
Project
• construction works: since late 2007 to approx. March 2009
![Page 9: Integrated River Engineering Project on the Danube to the ... river Engineering...• river bank restoration and reconstruction of low water regulation Aims: • increasing dynamics](https://reader033.vdocument.in/reader033/viewer/2022042215/5ebba010d69028326c456c2f/html5/thumbnails/9.jpg)
© via donau I 9
Pilot Project WitzelsdorfReconstruction of low water regulation
New groynes are downstream faced for redirecting the current to the river bank > higher dynamics at the river bank.
old groyne
new groyne
![Page 10: Integrated River Engineering Project on the Danube to the ... river Engineering...• river bank restoration and reconstruction of low water regulation Aims: • increasing dynamics](https://reader033.vdocument.in/reader033/viewer/2022042215/5ebba010d69028326c456c2f/html5/thumbnails/10.jpg)
© via donau I 10
Pilot Project WitzelsdorfReconstruction of low water regulation
Removal of an old groyne – note the height.
![Page 11: Integrated River Engineering Project on the Danube to the ... river Engineering...• river bank restoration and reconstruction of low water regulation Aims: • increasing dynamics](https://reader033.vdocument.in/reader033/viewer/2022042215/5ebba010d69028326c456c2f/html5/thumbnails/11.jpg)
© via donau I 11
Pilot Project WitzelsdorfReconstruction of low water regulation
Lower new groyne at the same day / water level.Effective under low water conditions only.
![Page 12: Integrated River Engineering Project on the Danube to the ... river Engineering...• river bank restoration and reconstruction of low water regulation Aims: • increasing dynamics](https://reader033.vdocument.in/reader033/viewer/2022042215/5ebba010d69028326c456c2f/html5/thumbnails/12.jpg)
© via donau I 12
Pilot Project WitzelsdorfReconstruction of low water regulation
By-pass channel at low water level for higher dynamics in the groynefield and as fish path for young fish along the river bank.
![Page 13: Integrated River Engineering Project on the Danube to the ... river Engineering...• river bank restoration and reconstruction of low water regulation Aims: • increasing dynamics](https://reader033.vdocument.in/reader033/viewer/2022042215/5ebba010d69028326c456c2f/html5/thumbnails/13.jpg)
© via donau I 13
Pilot Project WitzelsdorfRiver bank restoration
River bank before the construction work
![Page 14: Integrated River Engineering Project on the Danube to the ... river Engineering...• river bank restoration and reconstruction of low water regulation Aims: • increasing dynamics](https://reader033.vdocument.in/reader033/viewer/2022042215/5ebba010d69028326c456c2f/html5/thumbnails/14.jpg)
© via donau I 14
Pilot Project WitzelsdorfRiver bank restoration
Construction work - excavators in the service for ecology.
![Page 15: Integrated River Engineering Project on the Danube to the ... river Engineering...• river bank restoration and reconstruction of low water regulation Aims: • increasing dynamics](https://reader033.vdocument.in/reader033/viewer/2022042215/5ebba010d69028326c456c2f/html5/thumbnails/15.jpg)
© via donau I 15
Pilot Project WitzelsdorfRiver bank restoration
River bank just after the construction work. The river will shape its new river bank for its own.
![Page 16: Integrated River Engineering Project on the Danube to the ... river Engineering...• river bank restoration and reconstruction of low water regulation Aims: • increasing dynamics](https://reader033.vdocument.in/reader033/viewer/2022042215/5ebba010d69028326c456c2f/html5/thumbnails/16.jpg)
© via donau I 16
Pilot Project WitzelsdorfRiver bank restoration
Typical natural river bank after some months/years (depending onhydrological conditions). Picture taken at the already completed river bank restorationsection Thurnhafen vis-à-vis Hainburg.
![Page 17: Integrated River Engineering Project on the Danube to the ... river Engineering...• river bank restoration and reconstruction of low water regulation Aims: • increasing dynamics](https://reader033.vdocument.in/reader033/viewer/2022042215/5ebba010d69028326c456c2f/html5/thumbnails/17.jpg)
© via donau I 17
MR DI Dr. Leo GRILLBundesministerium Verkehr, Innovation und
Technologie - bmvitLeiter Abteilung IV/W 3 - Bundeswasserstraßen
Radetzkystraße 2, A1030 Wientel +43 1 711 62 - 65 5960fax +43 1 711 62 - 65 5998