Transcript
Page 1: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Introduction To Earned Value

November 14, 2002

Page 2: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Definition

• Earned Value is a method for measuring project performance. It compares the amount of work that was planned with what was actually accomplished to determine if cost and schedule performance is as planned. (PMBOK)

• In other words, its a way of determining for the money we spent, are we on budget and on schedule?

• EV is in Monetary terms $$$

Page 3: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

The Basics

• BCWS– Budgeted Cost of Work Scheduled

• BCWP (also referred to as Earned Value)– Budgeted Cost of Work Performed

• ACWP– Actual Cost of Work Performed

Page 4: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

BCWS

• Budget applied to tasks in a schedule

• Example– Task X Start Date 1/1/01 End date 2/28/01

• Duration = 2 months– Task Y Start Date 2/1/01 End Date 2/28/01

• Duration = 1 month– Task Z Start Date 3/1/01 End Date 3/31/01

• Duration = 1 month

Page 5: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

BCWS

• If resources were applied to each task and the cost of those resource worked out to :– Task X $100 Task Y $100 Task Z $100

– Then assuming an even distribution over the duration of the task, the budget would be :

• Incremental Task(s) Cumulative

– Jan $50 X $50– Feb $150 X,Y $200– Mar $100 Z $300

Page 6: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Earned Value Analysis

50

200

300

400

500

550

600 600

0

100

200

300

400

500

600

700

J an-01 Feb-01 Mar-01 Apr-01 May-01 J un-01 J ul-01 Aug-01 Sep-01 Oct-01 Nov-01 Dec-01

BCWS 50 200 300 400 500 550 600 600J an-01 Feb-01 Mar-01 Apr-01 May-01 J un-01 J ul-01 Aug-01 Sep-01 Oct-01 Nov-01 Dec-01

Page 7: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

BCWP

• BCWP is how much work was accomplished• Example:

– At the end of January, we find that we are 25% complete with Task X

• BCWP for Task X = .25*$100=$25– Task Y & Z have not started (and not scheduled to start),

Therefore 0% complete– Incremental BCWP for Jan = $25– Cumulative BCWP for end of Jan = $25

Page 8: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

BCWP

• At the end of February, we find that we are 75% complete with Task X– BCWP for Task X = .75*$100=$75

• BCWP for Feb for Task X = $75-$25 = $50

• At end of February, Task Y is complete.– BCWP for Task Y = $100

• At end of February, Task Z is 25% complete.– BCWP for Task Z = .25*$100=$25

• Incremental BCWP for Feb = $175 ($50+100+$25)• Cumulative BCWP for end of Feb = $200

Page 9: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Earned Value Analysis

50

200

300

400

500

550

600 600

25

200

0

100

200

300

400

500

600

700

Jan-01 Feb-01 Mar-01 Apr-01 May-01 Jun-01 Jul-01 Aug-01 Sep-01 Oct-01 Nov-01 Dec-01

BCWS 50 200 300 400 500 550 600 600

BCWP 25 200

Jan-01 Feb-01 Mar-01 Apr-01 May-01 Jun-01 Jul-01 Aug-01 Sep-01 Oct-01 Nov-01 Dec-01

Page 10: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

BCWP

• For end of February, the overall project is on schedule– Task X: BCWS = $100, BCWP = $75– Task Y: BCWS = $100, BCWP = $100– Task Z: BCWS = $0, BCWP = $25

• Schedule Variance = BCWP - BCWS– Negative Schedule variance indicates behind schedule– Positive Schedule Variance indicates ahead of schedule

Page 11: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Schedule Variance

• For end of February, the overall project is on schedule, but the individual tasks are:

• Task X: BCWS = $100, BCWP = $75$75 - $100 = -$25 BEHIND SCHEDULE

• Task Y: BCWS = $100, BCWP = $100$100 - $100 = $0 ON SCHEDULE

• Task Z: BCWS = $0, BCWP = $25$25 - $0 = +$25 AHEAD OF SCHEDULE

Page 12: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Percent Complete

• Engineering Estimate• Based on quantitative means such as number of

programs coded• 0 / 100 rule : receive 100% when task is complete• 20 / 80 rule : receive 20% when you start a task,

the other 80% when you complete • 50 / 50 rule: 50% complete when you start an

activity, the other 50% when you complete

Page 13: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

ACWP

• ACWP is the actual cost spent to accomplish work– Labor $ (Salaries, Benefits, Overhead)– Other Direct Costs (Software costs, Hardware costs,

Maintenance fees, License fees, Supplies)• Example

– At end of January, Task X has accumulated costs of $50

Page 14: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

ACWP

• At end of February– Task X has accumulated costs of $150– Task Y has accumulated costs of $150– Task Z has accumulated costs of $10– TOTAL ACWP = $310 (end of Feb.)

Page 15: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Earned Value Analysis

50

200

300

400

500

550

600 600

25

200

50

310

0

100

200

300

400

500

600

700

Jan-01 Feb-01 Mar-01 Apr-01 May-01 Jun-01 Jul-01 Aug-01 Sep-01 Oct-01 Nov-01 Dec-01

BCWS 50 200 300 400 500 550 600 600

BCWP 25 200

ACWP 50 310

Jan-01 Feb-01 Mar-01 Apr-01 May-01 Jun-01 Jul-01 Aug-01 Sep-01 Oct-01 Nov-01 Dec-01

Page 16: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

ACWP

• Overall, through the end of February, the project is over cost for the work that has been performed.– BCWP = $200– ACWP = $310

• Cost Variance = BCWP - ACWP– Negative Cost Variance indicates you spent more than

you performed in $– Positive Cost Variance indicates you spent less than

you performed in $

Page 17: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Cost Variance

• At end of February– Task X BCWP = $75, ACWP = $150– Task Y BCWP = $100, ACWP = $150– Task Z BCWP = $25, ACWP = $10– TOTAL BCWP = $200, ACWP = $310

Page 18: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Cost Variance

• At end of February– Task X BCWP = $75, ACWP = $150

• CV = -$75, Over Cost– Task Y BCWP = $100, ACWP = $150

• CV = -$50, Over Cost– Task Z BCWP = $25, ACWP = $10

• CV = $15, Under Cost– Overall Project BCWP = $200, ACWP = $310

• CV = -$110, Over Cost

Page 19: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Indexes

• Schedule Performance Index– BCWP / BCWS– Greater than 1 indicates ahead of schedule– Less than 1 indicates behind schedule– Examples:

• SPI = .75, means for $1 of work scheduled, you only performed $.75 of work.

• SPI = 1.25, means for $1 of work scheduled, you performed $1.25 of work.

Page 20: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Indexes

• Cost Performance Index– BCWP / ACWP– Greater than 1 indicates under cost– Less than 1 indicates over cost– Examples:

• CPI = 1.35, means for every $1 spent, you performed $1.35 of work

• CPI = .5, means for every $1 spent, you accomplished $.50 of work

Page 21: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Indexes

• End of January – BCWS = $50, BCWP = $25, ACWP = $50– SPI = $25/$50 = .50 Behind Schedule– CPI = $25/$50 = .50 Over Budget

• End of February– BCWS = $200, BCWP = $200, ACWP = $310– SPI = $200/$200 = 1 On Schedule– CPI = $200/$310 = .65 Over Budget

Page 22: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Indexes

• Typically don’t calculate these at Task level– How do you divide a number by zero when you

perform work before it is scheduled?

• CPI can be used to project costs at completion.

Page 23: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Budget At Completion

• Total value of incremental BCWS.

• Should be total budget for project as allocated to the tasks to complete the project.

• If not all budget allocated to tasks, it is usually unallocated or held in reserve. It is however, still considered to be part of the budget at completion. This varies by application area.

Page 24: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Estimate At Completion

• Total cost to be incurred based on actual dollars spent to date + estimate to complete (ETC)

• (Latest Revised Estimate (LRE) = Estimate at Completion (EAC))

• Calculation 1° EAC = ACWP + (Remaining BCWS /CPI)° EAC = $310 + ( $400/.65) = $925– Compare to BAC of $600. This infers that we will

continue to work at same efficiency we’ve incurred to date.

Page 25: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Estimate At Completion

• Calculation 2° EAC = BAC+CV° EAC = $600+$110 = $710° This infers that we will work to plan from this point

forward

Page 26: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Estimate to Complete

• Cost of remaining work– Formula based (BCWS/CPI)

• Beware of formulas using one or two data points– Engineering estimate

• SWAG• Bottoms-Up detailed estimate

– Straight remaining budget

Page 27: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Earned Value Analysis

50

200

300

400

500

550

600 600

25

200

50

310

600 600 600 600 600 600 600 600 600 600 600 600625

710

0

100

200

300

400

500

600

700

800

Jan-01 Feb-01 Mar-01 Apr-01 May-01 Jun-01 Jul-01 Aug-01 Sep-01 Oct-01 Nov-01 Dec-01

BCWS 50 200 300 400 500 550 600 600

BCWP 25 200

ACWP 50 310

BAC 600 600 600 600 600 600 600 600 600 600 600 600

EAC 625 710

Jan-01 Feb-01 Mar-01 Apr-01 May-01 Jun-01 Jul-01 Aug-01 Sep-01 Oct-01 Nov-01 Dec-01

Page 28: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Variance at Completion

• Difference between BAC and EAC– BAC - EAC = VAC– Positive is Good– Negative is bad

Page 29: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Earned Value Analysis

• Charts or reports are used to identify trends so that corrective action can occur– Project level or group of significant like tasks.– Cost/Schedule Status Report (C/SSR)or Cost

Performance Report (CPR)• Establishing parameters (% or $) on variances help

management not overreact to natural aberrations.• Project Manager wants to be able to explain

unfavorable variances and actions taken to correct.

Page 30: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Corrective Actions?

• Schedule slippage for a specific task on the critical path or for the project as a whole.

• Cost overrun on a specific task on the critical path of for the project as a whole.

• Insufficient or inadequate resources• Changes in scope that affect project cost or schedule• Quality problems resulting in excessive rework• Material shortages from suppliers• Changes in customer or user requirements

Page 31: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Summary

• BCWS : Budgeted Cost of Work Scheduled• BCWP : Budgeted Cost of Work Performed• ACWP: Actual Cost of Work Performed• SV: Schedule Variance: BCWP - BCWS

– Negative is Bad, Positive is good• CV: Cost Variance: BCWP - ACWP

– Negative is bad, positive is good• SPI: Schedule Performance Index: BCWP/BCWS

– Greater than 1 is good, Less than 1 is bad

Page 32: Introduction To Earned Value November 14, 2002. Definition Earned Value is a method for measuring project performance. It compares the amount of work

Summary

• CPI: Cost Performance Index: BCWP/ACWP– Greater than 1 is good, Less than 1 is bad

• BAC: Budget at Completion• EAC (LRE): Estimate at Completion / Latest

Revised Estimate• VAC: variance at Completion: BAC - EAC

– Negative is bad, positive is good• ETC: Estimate To Complete


Top Related