• Recap points regarding system request and feasibility analysis
• Understand the big picture of the analysis phase• Understand the objectives and techniques for
gathering business requirements (e.g., what to ask in an interview)
• Understand expectations for Assignment 2
Today’s Objectives
![Page 3: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/3.jpg)
Course Map
Contents
1. Introduction
Planning Phase2. Project Initiation3. Project Management
Analysis Phase4. Systems Analysis5. Gathering Information6. Process Modeling7. Data Modeling
1 2 3 4 6 7 8 9 10 115
Assignments
QuizzesFinal
Week
CoreExamReview
![Page 4: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/4.jpg)
Topic Duration
• Recap Planning Phase 30 minutes
• Analysis Phase Overview 40 minutes
*** Break 15 minutes
• Information Gathering Techniques 60 minutes
• Interviewing Exercise 30 minutes
• Assignment 2 Intro 15 minutes
Today’s agenda
![Page 5: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/5.jpg)
SDLC
The systems development life cycle (SDLC) is a description of the phases of an information system
Planning Analysis Design Implementation
Sep. 23 focus Sep. 30 - Oct. 28 focus
![Page 6: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/6.jpg)
SDLC: Planning Phase
IdentifyBusinessValue
Analyze TechnicalFeasibility
Analyze EconomicFeasibility
Analyze OrganizationalFeasibility
ProjectManagement
Project Initiation
Approval Approval
![Page 7: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/7.jpg)
SDLC: Planning Phase
IdentifyBusinessValue
Analyze TechnicalFeasibility
Analyze EconomicFeasibility
Analyze OrganizationalFeasibility
ProjectManagement
Approval Approval
Deliverables SystemRequest
Feasibility Analysis
![Page 8: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/8.jpg)
Key Roles
• Project Sponsor– The project sponsor is a key person proposing
development or adoption of the new information
technology
• Approval Committee– The approval committee reviews proposals from
various groups and units in the organization and decides which to commit to developing
![Page 9: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/9.jpg)
Technical Feasibility
Familiarity with applicationKnowledge of business domain
Familiarity with technologyExtension of existing firm technologies
Project sizeSchedule, quality, workdays, personnel.
Technical feasibility addresses the question: Can we build it?
![Page 10: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/10.jpg)
Economic Feasibility
Benefits (cash inflows)Development costs (initial cash outflows)Operational costs (ongoing cash outflows)Totals
Economic feasibility addresses the question: Should we build it?
![Page 11: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/11.jpg)
Payback Period
![Page 12: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/12.jpg)
Economic Feasibility
Total (benefits - costs)
Total costs
RETURN ON INVESTMENT EQUALS
Divided by
![Page 13: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/13.jpg)
Economic Feasibility
(1 + interest rate)n
Some amount of money
NET PRESENT VALUE EQUALS
Divided by
Where “n” equals the number of periods
![Page 14: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/14.jpg)
Organizational Feasibility
Stakeholder analysisProject champion(s)Organizational managementSystem users
Organizational feasibility addresses the question: If we build it, will they come?
![Page 15: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/15.jpg)
Summary
Project initiation involves creating and assessing goals and expectations for a new system
Identifying the business value of the new project is a key to successFeasibility study is concerned with insuring that technical, economic, and organizational benefits outweigh costs and risks
![Page 16: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/16.jpg)
Topic Duration
• Recap Planning Phase 30 minutes
• Analysis Phase Overview 40 minutes
*** Break 15 minutes
• Information Gathering Techniques 60 minutes
• Interviewing Exercise 30 minutes
• Assignment 2 Intro 15 minutes
Today’s agenda
![Page 17: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/17.jpg)
Key Definitions
• The As-Is system is the current system and may or may not be computerized
• The To-Be system is the new system that is based on updated requirements
![Page 18: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/18.jpg)
Why Do Analysis
![Page 19: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/19.jpg)
THE ANALYSIS PHASE
![Page 20: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/20.jpg)
Analysis Phase
Key Question: Deliverables
Steps Techniques
What does the system need to do?Functional requirementsQuality requirementsData modelProcess model
1. Gather requirements2. Create data model3. Create process model
InterviewingObservationEntity-relationship modelingNormalizationData flow modeling
![Page 21: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/21.jpg)
Analysis Phase
![Page 22: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/22.jpg)
Analysis Phase
FromPlanningPhase:
System requestFeasibility analysisWorkplan . . .
DevAnalysisPlan
Examine-As-is
IdentifyImprove-ments
DevelopBasicSystemConcepts
DevelopDataModel
DevelopProcessModel
PrepareProposal
SystemWalkthrough
ToDesignPhase:
Deliverables:
Analysis Plan Functional Requirements
Quality Requirements
SystemConcept
Data Model
Process Model
System Proposal
![Page 23: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/23.jpg)
Analysis Phase
FromPlanningPhase:
System requestFeasibility analysisWorkplan . . .
DevAnalysisPlan
Examine-As-is
IdentifyImprove-ments
DevelopBasicSystemConcepts
DevelopDataModel
DevelopProcessModel
PrepareProposal
ToDesignPhase:
Deliverables:
Analysis Plan Functional Requirements
Quality Requirements
SystemConcept
Data Model
Process Model
System Proposal
Develop Conceptfor To-Be System
![Page 24: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/24.jpg)
Analysis Phase
FromPlanningPhase:
System requestFeasibility analysisWorkplan . . .
DevAnalysisPlan
Examine-As-is
IdentifyImprove-ments
DevelopBasicSystemConcepts
DevelopDataModel
DevelopProcessModel
PrepareProposal
ToDesignPhase:
Develop Conceptfor To-Be System
Gather Analyze Specify
![Page 25: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/25.jpg)
Analysis Plan/Strategy
![Page 26: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/26.jpg)
Begin with the End in Mind
• Table of contents• Executive summary• System request• Work plan• Analysis strategy• Recommended
system• Feasibility analysis
• Process model• Data model• Appendices
System Proposal Outline
![Page 27: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/27.jpg)
Three Fundamental Analysis Strategies
• Business process Automation (BPA)• Business Process Improvement (BPI)• Business Process Reengineering (BPR)
![Page 28: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/28.jpg)
High-Level Work Plan for Analysis
Step Deliverable Technique
Planning PhaseAnalysis Phase
Examine As-Is System Information SummariesUse CasesProcess ModelData Model
Gather Information
Develop Process ModelDevelop Data Model
Identify Improvements Ideas for System Problem AnalysisRoot Cause AnalysisDuration AnalysisActivity-based CostingInformal BenchmarkingFormal BenchmarkingOutcome AnalysisBreaking AssumptionsTechnology AnalysisActivity EliminationProxy BenchmarkingProcess Simplification
Develop Concept for To-Be System
System ConceptUse CasesProcess ModelData Model
Gather Information
Develop Process ModelDevelop Data Model
![Page 29: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/29.jpg)
Topic Duration
• Recap Planning Phase 30 minutes
• Analysis Phase Overview 40 minutes
*** Break 15 minutes
• Information Gathering Techniques 60 minutes
• Interviewing Exercise 30 minutes
• Assignment 2 Intro 15 minutes
Today’s agenda
![Page 30: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/30.jpg)
Understand As-Is
![Page 31: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/31.jpg)
Analysis Phase
FromPlanningPhase:
System requestFeasibility analysisWorkplan . . .
DevAnalysisPlan
Examine-As-is
IdentifyImprove-ments
DevelopBasicSystemConcepts
DevelopDataModel
DevelopProcessModel
PrepareProposal
ToDesignPhase:
Deliverables:
Analysis Plan Functional Requirements
Quality Requirements
SystemConcept
Data Model
Process Model
System Proposal
Develop Conceptfor To-Be System
![Page 32: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/32.jpg)
As-Is System
What is the purpose of studying the current As-Is system?
Is there ever a situation in which the As-Is system should not be studied extensively?
![Page 33: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/33.jpg)
Information Gathering Techniques
• Interviewing• Joint application design• Questionnaires• Document Analysis• Observation
![Page 34: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/34.jpg)
Interviews
![Page 35: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/35.jpg)
Interviews -- Five Basic Steps
• Selecting Interviewees• Designing Interview Questions• Preparing for the Interview• Conducting the Interview• Post-Interview Follow-up
![Page 36: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/36.jpg)
Selecting Interviewees
• Based on Information Needed• Often Good to Get Different Perspectives
– Managers
– Users
– Ideally, All Key Stakeholders
![Page 37: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/37.jpg)
Types of Questions
Types of Questions Examples
Closed-Ended Questions * How many telephone orders are received per day?
* How do customers place orders?* What additional information would you like the new system to provide?
Open-Ended Questions * What do you think about the current system?* What are some of the problems you face on a daily basis?* How do you decide what types of marketing campaign to run?
Probing Questions * Why?* Can you give me an example?* Can you explain that in a bit more detail?
![Page 38: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/38.jpg)
Designing Interview Questions
• Unstructured interview– Broad, Roughly Defined Information
• Structured interview– More Specific Information
![Page 39: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/39.jpg)
Questioning Strategies
High LevelVery General
Medium-LevelModeratelySpecific
Low-LevelVery Specific
TOP DOWN
BOTTOM UP
EXAMPLES?
![Page 40: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/40.jpg)
Interview Preparation Steps
• Prepare General Interview Plan– List of Questions– Anticipated Answers and Follow-Ups
• Confirm Areas of Knowledge• Set Priorities in Case of Time Shortage• Prepare the Interviewee
– Schedule– Inform of Reason for Interview– Inform of Areas of Discussion
![Page 41: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/41.jpg)
Conducting the Interview
• Appear professional and unbiased• Record all information• Check on organizational policy regarding tape
recording• Be sure you understand all issues and terms• Separate facts from opinions• Give interviewee time to ask questions• Be sure to thank the interviewee• End on time
![Page 42: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/42.jpg)
Conducting the InterviewPractical Tips
• Don’t Worry, Be Happy• Pay Attention• Summarize Key Points• Be Succinct• Be Honest• Watch Body Language• And, don’t ask unnecessary questions!
![Page 43: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/43.jpg)
Post-Interview Follow-Up
• Prepare Interview Notes• Prepare Interview Report• Look for Gaps and New Questions• “If it isn’t in the fieldnotes, it never happened.”
![Page 44: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/44.jpg)
Interview Report
INTERVIEW REPORT
Interview notes approved by: ____________
Person interviewed ______________Interviewer _______________Date _______________Primary Purpose:
Summary of Interview:
Open Items:
Detailed Notes:
![Page 45: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/45.jpg)
JOINT APPLICATION DESIGN (JAD)
![Page 46: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/46.jpg)
JAD Key Ideas
• Allows project managers, users, and developers to work together
• May reduce scope creep by 50%• Avoids requirements being too specific or too
vague
![Page 47: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/47.jpg)
Joint Application Design (JAD) Important Roles
• Facilitator• Scribe
![Page 48: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/48.jpg)
Joint Application Design (JAD) Setting
• U-Shaped seating• Away from distractions• Whiteboard/flip chart• Prototyping tools• e-JAD
![Page 49: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/49.jpg)
JAD Meeting Room
JPEG Figure 5-5 Goes Here
![Page 50: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/50.jpg)
The JAD Session
• Tend to last 5 to 10 days over a three week period• Prepare questions as with interviews• Formal agenda and groundrules• Facilitator activities
– Keep session on track
– Help with technical terms and jargon
– Record group input
– Help resolve issues• Post-session follow-up
![Page 51: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/51.jpg)
Managing Problems in JAD Sessions
• Reducing domination• Encouraging non-contributors• Side discussions• Agenda merry-go-round• Violent agreement• Unresolved conflict• True conflict• Use humor
![Page 52: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/52.jpg)
QUESTIONNAIRES
![Page 53: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/53.jpg)
Questionnaire Steps
• Selecting participants
– Using samples of the population• Designing the questionnaire
– Careful question selection• Administering the questionnaire
– Working to get good response rate• Questionnaire follow-up
– Send results to participants
![Page 54: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/54.jpg)
Good Questionnaire Design
Begin with non-threatening and interesting questions
Group items into logically coherent sections
Do not put important items at the very end of the questionnaire
Do not crowd a page with too many items
Avoid abbreviations
Avoid biased or suggestive items or terms
Number questions to avoid confusion
Pretest the questionnaire to identify confusing questions
Provide anonymity to respondents
![Page 55: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/55.jpg)
Document Analysis
• Provides clues about existing “as-is” system• Typical documents
– Forms
– Reports
– Policy manuals• Look for user additions to forms• Look for unused form elements
![Page 56: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/56.jpg)
Observation
• Users/managers often don’t remember everything they do• Checks validity of information gathered other ways• Behaviors change when people are watched• Careful not to ignore periodic activities
– Weekly … Monthly … Annual
![Page 57: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/57.jpg)
Criteria for Selecting the Appropriate Techniques
• Type of information• Depth of information• Breadth of information• Integration of information• User involvement• Cost• Combining techniques
![Page 58: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/58.jpg)
Selecting the Appropriate Techniques
Interviews JAD Questionnaires Document Observation Analysis
Type of As-Is As-Is As-Is As-Is As-IsInformation Improve. Improve. Improve. To-Be To-Be
Depth of High High Medium Low LowInformation
Breadth of Low Medium High High LowInformation
Integration Low High Low Low Lowof Info.
User Medium High Low Low LowInvolvement
Cost Medium Low- Low Low Low- Medium Medium
![Page 59: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/59.jpg)
• Suggest how CD Selections should proceed in eliciting requirements.
• Consider steps, techniques and goals, who and how.
![Page 60: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/60.jpg)
• How would you identify possible improvements?
• What possible improvements would you suggest?
![Page 61: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/61.jpg)
Summary
• There are five major information gathering techniques that all systems analysts must be able to use: Interviews, JAD, Questionnaires, Document Analysis, and Observation.
• Systems analysts must also know how and when to use each as well as how to combine methods.
![Page 62: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/62.jpg)
Topic Duration
• Recap Planning Phase 30 minutes
• Analysis Phase Overview 40 minutes
*** Break 15 minutes
• Information Gathering Techniques 60 minutes
• Interviewing Exercise 30 minutes
• Assignment 2 Intro 15 minutes
Today’s agenda
![Page 63: IS 421 Information Systems Analysis James Nowotarski 30 September 2002](https://reader035.vdocument.in/reader035/viewer/2022062516/56649d435503460f94a1fd63/html5/thumbnails/63.jpg)
End of Slides