Project Update
January 9th, 2012
![Page 2: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/2.jpg)
Roadway Projects
![Page 3: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/3.jpg)
• Temporary lanes have been installed on the east side and all traffic has been shifted towards the east
• The bridge over clear creek has been partially demolished to allow work to begin on the new bridge
• Work has begun on the installation of the storm trunk along the west right of way beginning at the creek
Cullen Parkway – Phase II
![Page 4: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/4.jpg)
Phase II – Mary’s Creek Bypass to SH35 • Remaining punchlist items re-
communicated to TxDOT • Streetlight installation underway
Dixie Farm Road
![Page 5: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/5.jpg)
• Completed installation of the irrigation system and landscaping
• Quantity overruns on existing storm sewer removal • The subcontractor completed the asphalt overlay
segments • Quantity overruns on base repairs • Full opening of SH35 intersection is dependent upon
TxDOT completion of the new signal
Walnut Reconstruction
![Page 6: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/6.jpg)
![Page 7: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/7.jpg)
• Traffic signal at Mykawa installation is complete. The signal was operational on December 9th
• Traffic switch completed last week • Potentially will extend beyond mid-February
completion date
Orange Street
![Page 8: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/8.jpg)
![Page 9: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/9.jpg)
• Cable and phone companies relocating • Waiting on a proposal from WSA for
modifications to the plans to address TxDOT comments at FM 1128 intersection
Bailey Road (Veterans to FM1128)
![Page 10: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/10.jpg)
• 90% plans have been reviewed and returned to engineer
• Continued coordination with developer, County staff and CR59 designers
• 100% plans will be submitted in January
Business Center Drive
![Page 11: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/11.jpg)
• Work to demo existing paving in the center lane and medians began and drainage laterals will be extended to the existing northbound lanes
• Contractor is preparing to begin lime stabilization at the north end
• TxDOT working with TCEQ on intersection with FM 518
• Mitigation Ponds bid opening on December 8th
SH35 – BW8 to FM518
![Page 12: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/12.jpg)
![Page 13: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/13.jpg)
• All signal poles installed • Project is on schedule for completion in
January 2012
FM 2234 Widening
![Page 14: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/14.jpg)
• System has been running in full automated control since late November
• Tactics system required some debugging and went through several weeks of adjustments
• The system was determined to be Substantially Complete on Dec. 15th and a punch list was developed and transmitted to Siemens
Adaptive Traffic Signal Improvements
![Page 15: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/15.jpg)
Drainage Projects
![Page 16: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/16.jpg)
Diversion Ditch • DD4 continued excavation of diversion ditch west
of CR 143 Pump Station • Awarded the final design and construction phase
services contract to Montgomery & Barnes. Issued NTP
Re-grading of Roadside Ditches • Awaiting County response regarding exceptions to
the standard design criteria for the maintenance portion of the project
Cowart Creek Diversion
![Page 17: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/17.jpg)
Facility Projects
![Page 18: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/18.jpg)
• Punchlist near completion • Addressing warranty issues as necessary • Fuel island is functioning • Working on closeout documents
Hillhouse Road Service Center
![Page 19: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/19.jpg)
![Page 20: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/20.jpg)
• January is the latest completion date • Working on interior finishes
Fire Station #6
![Page 21: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/21.jpg)
![Page 22: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/22.jpg)
• Foundation piers were drilled the week of Dec. 12th
• Structural inspections complete • Monument base formed and poured • Architect reviewing stone and decorative
steel submittals
Pearland Gateway – Project Stars
![Page 23: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/23.jpg)
![Page 24: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/24.jpg)
Parks
![Page 25: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/25.jpg)
• Trail areas around Park and along McLean
to Magnolia are cut and ready for forms • All concrete should be completed by the end
of January • Site furnishings received
Trail Connectivity
![Page 26: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/26.jpg)
![Page 27: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/27.jpg)
• Transmitted Interlocal Agreement and MOU to BDD4; approval scheduled for tomorrow
• Property acquisition ongoing • Developer Agreement scheduled for next CC
meeting • USACE responded requesting more information
and clarification on PCN for outfalls and weir to USACE for review
Sports Complex at Max Road
![Page 28: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/28.jpg)
Utility Projects
![Page 29: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/29.jpg)
30” Waterline Interconnect
• CoH flushed and disinfected the 72” line but did not pass BTs
• Re-flushed line and new tests scheduled for today • HMI should begin flushing & disinfection the 30”
water line system this week if 72” line passed
City of Houston Interconnect
![Page 30: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/30.jpg)
City of Houston Interconnect
Alice Street Water Plant • Awaiting CoH water for startup of plant
![Page 31: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/31.jpg)
![Page 32: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/32.jpg)
• Staff reviewed 60% submittal and returned comments
• Held follow-up meeting to discuss plan review comments for clarification
Longwood WWTP Rehabilitation
![Page 33: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/33.jpg)
• Design completed • Technical review meeting was held • Staff is loading bid information into the E-
Bid system • Advertise for bids by the end of January
Barry Rose WWTP Rehabilitation
![Page 34: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/34.jpg)
• PER is under review
Hatfield Basin Trunk Sewer
![Page 35: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/35.jpg)
• 90% review underway
Twin Creek Regional Lift Station
![Page 36: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/36.jpg)
Far Northwest Wastewater Treatment Plant Improvements
• Design contract will be on the January 23rd agenda
![Page 37: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/37.jpg)
Old Alvin 20” Waterline
• Received PER; currently in review process with staff
• Phase II ESA field work performed; contaminated soils issues identified near FM518 and Old Alvin
![Page 38: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/38.jpg)
BellaVita Waterline Interconnect
• Requesting USACE to review wetland findings and environmental reports for Dixie Farm Rd Park property
• Survey work ongoing • Bella Vita HOA for right of entry obtained • Public Works began work at Bella Vita in mid
December
![Page 39: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/39.jpg)
![Page 40: January 2012 Presentation](https://reader034.vdocument.in/reader034/viewer/2022042618/568cc6901a28ab8c668b713d/html5/thumbnails/40.jpg)
Project Update
Questions/Comments
January 9th, 2012