JCM Model Project Power generation by waste heat
recovery in cement industry
2
About JFE Engineering Corporation
Project Information
Project Scheme & Schedule
Advantage & Challenge
Future Market
JFE Group Structure
3
5
42,500
Net Sales(million US$)
Employees 26,900
JFE Steel
6,200
Net Sales(million US$)
Employees 17,800
JFE Shoji Trade
JFE Holdings (holding company)
45.93 % 100 %
7,400
Net Sales(million US$)
Employees 2,840
JFE Engineering
Japan Marine United
(FY2013, US$1=JPY100)
JFE Holdings 45.93% IHI 45.93% Hitachi Zosen 8.15%
JFE Engineering Business Field
Environment
Energy
Steel Structure
Industrial Machinery
Net Sales (million $)
2,840 -Waste-to-Energy -Biomass -Water Solution
-Pipeline -LNG -Power Plant
-Bridges -Coastal structure -High rise structure
-Logistics (Bicycle Parking System, Container warehouse, Port cranes)
4
Global Network
5
Asia & Oceania
Frankfurt(Regional Head Office)
Singapore (Regional Head Office)
Singapore Kuala Lumpur (Malaysia) Jakarta (Indonesia) Hanoi, Ho Chi Minh (Vietnam) Yangon (Myanmar) Manila (Philippines) Mumbai, Pune (India) Brisbane (Australia)
Beijing (Regional Head Office)
America
Asia & Oceania Europe Frankfurt (Germany) Rome (Italy)
Long Beach (USA)
Middle East Al Khobar
China Shanghai Beijing Hong Kong
Long Beach Al Khobar
Subsidary Company J&M Steel Solutions Company Limited (Myanmar) PT. Enercon (Indonesia)
6
Project Name
Power generation by waste heat recovery in cement
industry
Project Participants
JFE Engineering Corporation PT Semen Indonesia*1
Total Investment 44 Million US$*2
Project Period July 2014~August 2016
Site Tuban Plant, East Jawa
Power Generation 28MW
GHG Reduction 122,000t-CO2/y
Tuban Plant
Tuban Plant *1: The biggest Cement Company in Indonesia *2: US$1=JPY120
Project Information
7
Cement Production Process
Hot Exhaust
Gas
350ºC
400ºC
Hot Exhaust
Gas
GHG Reduction
8
電力
Net Electricity Generation
165,126MWh
GHG Reduction 122,000tCO2/y
=165,126MWh/y *0.741tCO2e/MWh
Grid Power
Self-Consumption 21,024MWh
SP・AQC Boiler
Stack EP
Raw Mill
Suspension Preheater
Rotary Kiln Clinker Cooler
EP Stack
Coal-fired Power Plant
SP Boiler AQC Boiler
Turbine Generator
Hot Exhaust Gas
Cement Production Process
Steam Steam
9
Indonesian Government
JCM Joint Committee
JFE Engineering Corporation
PT Semen Indonesia
International Consortium
Finance (up to the half)
at least half of JCM credits issued
JCM Model Project Scheme
Japanese Government Ministry of the Environment
Project Schedule
10
FY2013 FY2014 FY2015 FY2016
Feasibility Study
Submit Proposed Methodology
Apply for Finance
Project Execution
Develop PDD
Validation
Monitoring
Registration
Verification
Issuance
Approved in May
Approved in July
Expected to complete in August
October 2016~March 2021
Expected to complete in October
JCM Model Project Advantage
11 11
Reduce Initial Investment
Employ High and Reliable Technology →Energy Save = Cost Reduction
Initial Invest ment
Low Price Low
Quality
Initial Invest ment
JCM Financing
Reduce
JCM Model Project Challenge
12 12
How to monitor power consumption efficiently?
How could we execute project successfully as consortium?
Japanese Government Ministry of the Environment
Indonesian Government
JFE Engineering Corporation
PT Semen Indonesia
Governments
Consortium
Cement Production: 22.5Mt/y Power Generation: 57MW GHG Reduction: 250,000t-CO2/y
Vietnam
Future Market
13
Cement Production: 45.0Mt/y Power Generation: 112.5MW GHG Reduction: 710,000t-CO2/y
Indonesia
Cement Production: 45.0Mt/y Power Generation: 112.5MW GHG Reduction: 490,000t-CO2/y
Cement Production: 20.3Mt/y Power Generation: 50MW GHG Reduction: 270,000t-CO2/y
Malaysia
Thailand
14