Houses to be relocatedThe consultant has cooperated with RID to relocate local houses that affect the construction.
The client (RID) had already completed the compensation for the relocation to the affected people.
Most of houses had already been relocated except SRT’s house (in process of compensation) and nursery
2/30
RELOCATION FOR WATER SUPPLY LINE
The consultant found that the existing water supply line was obstruction for the construction.
The consultant has cooperated with RID and Thetsaban Pranakorn Sri Ayutthaya Water to relocate the water supply system.
The relocation for water supply is in progress.
13/30
KRA MANG SITE
cutting pipe line relocated pipe line existing pipe line
14/30
Tunnel
(PVC) (PVC) (PVC)
Change to HDPE pipe
HAN TRA SITE
15/30
cutting pipe line relocated pipe line existing pipe line
HDPE pipe line iron pipe line
RELOCATION FOR ELECTRIC OVERHEAD LINE
The consultant found that the existing electric overhead line was the obstruction for the construction.
The consultant has cooperated with RID, contractor and PEA for the relocation of electric overhead lines.
PEA plans to commence the relocation work once the contractor constructs temporary access road.
18/30
HAN TRA SITE
RELOCATION FOR ELECTRIC OVERHEAD LINE
20/30
abadoned overhead line propose overhead
line existing overhead line
New Line
TEMPORARY RELOCATION FOR SRT’S OVERHEAD SIGNAL LINEAt Kra Mang site, the consultant found that the existing SRT overhead line was the obstruction for the construction.
The consultant has cooperated with RID and SRT for the relocation of SRT’s overhead signal line.
The relocation of SRT overhead signal line is in progress.
23/30
KRA MANG SITE
TEMPORARY RELOCATION FOR SRT SIGNAL LINE
24/30
existing cable line
relocation line
existing cable line
cutting line
SUMMARY OF RELOCATION WORKS(UPDATE 16th JULY 2013)
29/30
1 KRAMANG SITE STATUS NOTE
1.1
Houses to be relocated
1.1.1House No.1 Finish
Owner has received compensation and relocated
1.1.2House No.2 Finish
Owner has received compensation and relocated
1.1.3House No.3 On Hold
Owner has received compensation, but requestedaddition compensation
1.1.4House No.4
In Progres
sNot yet start relocation works,
internal process by SRT.
In
30/30
2 Han Tra SITE STATUS NOTE
2.1Houses to be
relocated
2.1.1 House No.5 Finish
Owner has relocated voluntarily without compensation
2.1.2 House No.6 Finish
Owner has received compensation and relocated
2.1.3 House No.7 Finish
Owner has received compensation and relocated
2.1.4 House No.8 Finish
Owner has received compensation and relocated
2.1.5 Small Arbor No.9
Not Yet Start
Owner has received compensation and plan to start relocation
Water Supply In
ProgresIn process of compensation
SUMMARY OF RELOCATION WORKS(UPDATE 16th JULY 2013)