![Page 1: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/1.jpg)
Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0
(SH-61) Jodhpur – Osian (I Phase)
RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION &
CORPORATION LTD. JAIPUR
1
Development of Project on Public Private Partnership
(Annuity Model)
![Page 2: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/2.jpg)
PROJECT LOCATION
2
![Page 3: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/3.jpg)
NECESSITY OSIAN – JODHPUR (NH-65)
1) This road provides good connectivity from Jodhpur to Phalodi via Mathania & Osian.
2) It connects NH-15 to NH-65.
3) This is an Important route for the Army. Its provides alternate route for the strategic traffic leading to Jaiselmer.
4) It starts where the NH-15, (Bikaner – Jaiselmer) take of point is 2/100 at Phalodi after City Limits and ends at NH-65 (Jodhpur) at 122/000 of SH-61 before City Limits of Jodhpur.
5) It lies on the Osian which is very famous for Osian Mata & Jain Temples. Osian Mata Temple was built in 7th Century and its architecture has its own credit. Lot of Hindu Pilgrims daily came to visit these temples. This area has got historical and religious importance.
6) It has got 3 LC’s on the route in which 2 LC’s has TVU more than 2.0 Lac. The Solution is required.
3
![Page 4: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/4.jpg)
NECESSITY 1) Mathania is a Busy Industrial Town and Traffic intensity is
much more as the Road width is available in Built Up area. Mathania Bye Pass is required.
2) Commercial traffic is available due to Mining, Agriculture & Industrial activities
3) Number of Sharp Horizontal & Vertical Curves has be redesigned as per Guidelines of IRC.
4) Few new Culverts are required.
5) Lifting of Causeways and Vented Causeways are required.
4
![Page 5: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/5.jpg)
PROJECT PROPOSAL1) 2 Lane Carriageway with Paved Shoulder is Proposed.
2) Mathania Bye Pass is proposed.
3) The Bye Pass is proposed to Bye Pass 2 Busy Level Crossing at 105/000 & 114/0, in place of construction of 2 ROB’s over it.
4) At Osian (Built up area), the road is proposed with 4 Lane CC road with Paved Shoulder & Drain. (Approx. 2.0 km).
5) Osian Circle at Osian mata Temple is Bye passed with new shorter alignment which is with more flat Curve.
6) A hairpin bend at Ummednagar is Bye passed with proposed new Bye pass before Ummednagar.
7) All Horizontal & Vertical Curves shall be designed as per designated speed with all the requirements of Highway Design.
5
![Page 6: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/6.jpg)
BYE PASS OF 2 LC’S AT MATHANIA & MANAKLAV
6
![Page 7: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/7.jpg)
MATHANIA BYE - PASS
7
![Page 8: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/8.jpg)
COST BENEFIT OF NEW ALIGNMENT WRT 2 ROB’S AT LC’S
8
S. N
2 Level Crossing New alignment between 2 LC’s
Description Time Cost Description Time Cost
1. Land acquire at 2 LC’s & Mathania Bye Pass (almost 2.0 Km)
6 M 0.50 Land acquire for New Alignment including Bye Pass at Mathania (Almost 11.0 Km)
6 M 2.75
2. Construction of 2 Nos. 4 Lane ROB
1 Y 6M 40.00
Construction of New Road
6 M 22.00
3. Liaison with Railway Required Not Required
4. Existing Road of 9 km - 4.50 Mathania Village Road 2.0 Km
- 1.0
Total 2Y 0M 45.00
1Y 0M 25.75
This Comparison Shows that Choosing new alignment is more economical & Time Saving. The New alignment of road will also enhance the Infrastructure of near by area. The land acquisition is not a problem in this area.
![Page 9: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/9.jpg)
UMMED NAGAR BYE PASS
9
![Page 10: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/10.jpg)
OSIAN REALIGNMENT
10
![Page 11: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/11.jpg)
OSIAN BUS BAY & FACILITY CENTRE
11
![Page 12: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/12.jpg)
EXISTING SCENARIO(DETAILS OF CARRIAGEWAY)
Road Section
Length
(Km)
Existing carriageway
(m)
Remarks
Osian - Mathania
29.00 97/00 – 102/00~ 5.5m
74/00 – 97/000 ~ 7.0m
102/00 ~ 103/00 - 7.0m
5.0 Km – 5.5m (1.5 Lane with
Hard Shoulder)24.0 Km – 7.0m
(2 Lane with Hard Shoulder)
Mathania - Jodhpur (NH-65)
19.00 103/00 – 122/00 ~ 7.0m
(2 Lane with Hard Shoulder)
TOTAL 48.00 Km
12
![Page 13: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/13.jpg)
EXISTING SCENARIO(DETAILS OF HABITATIONS)
ROAD SECTION VILLAGES / TOWNS
Osian - Mathania Osian – (km 76/000)Ummaid Nagar – (km 98/000)
Mathania - Jodhpur Matahnia – (km 105/000)Rampura – (km 108/600)Manaklav– (km 114/000)Daijar- (km 120/000)NH-65 (Jodhpur)– (km 122/000)
13
![Page 14: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/14.jpg)
EXISTING SCENARIO(DETAILS OF EXISTING LEVEL CROSSINGS)
LC No. Nr. Village / Town
Chainage TVU / Year
LC No. C-42-E-2
Osian 72/800 34285 / 07
LC No. C-23-T-2
Mathania 103/500 242232 / 09
LC No. C-18-E-2
Manakalav 114/5500 224904 / 09
14
Due to Bye Pass of 2 Lc’s at Mathania & Manaklav only 1 LC will be left & it’s TVU is less 40000, so there is no requirement of ROB over it.
![Page 15: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/15.jpg)
PROPOSAL FOR ROAD IMPROVEMENT
ROAD SECTION TRAFFIC PROPOSAL
Osian – Mathania (SH-61)(Km 76/000 - Km 90/000)
2632 PCU550 CVD
Renewal & Widening of C/W with Paved Shoulder.Short realignment of Route at Osian Temple intersection.Bye Pass of Ummaid Nagar (Hair Pin Bend)
Mathania – Jodhpur NH-65 (SH-61)(km 90/000 – km 122/000 )
4298 PCU862 CVD
Renewal & Widening of C/W with Paved Shoulder.By Pass of Mathania Village with By – Pass of 2 LC’s.
15
![Page 16: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/16.jpg)
PROPOSED ROAD CROSS SECTIONS
16
![Page 17: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/17.jpg)
PROPOSED ROAD CROSS SECTIONS
17
![Page 18: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/18.jpg)
PROPOSED TOLL PLAZA
18
![Page 19: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/19.jpg)
PROPOSED TOLL PLAZA- OPT-2
19
![Page 20: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/20.jpg)
PROPOSED BUS STOP
20
![Page 21: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/21.jpg)
WORK DONE AT SITE TILL DATE
1. Topographical survey including field data for L section & X-
Section.
2. Geotechnical Investigations required for Road.
3. Pavement Condition survey with Core Composition & BBD
Test.
4. CD works Condition Survey
5. Road Inventory Survey
6. Traffic Census
7. Fixing of Bench Mark Pillars started.
8. Alignment Finalised of Bye Passes. Bye Pass survey started.
21
![Page 22: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/22.jpg)
ESTIMATES
22
![Page 23: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/23.jpg)
ABSTRACT OF COST OF DEVELOPMENT(WITH PAVED SHOULDER)
S. No.
ParticularsEstimated Cost (Rs. In Crores)
1. Improvement of Existing Road 46.37
2. CD Works (including new Culverts ) 2.54
3. ROB 0.00
4. CC Road 5.45
5. Bye Passes 19.93
6. Road Furniture 1.40
7. Road Work for Toll Plaza, Lay Bye’s etc.
4.36
8. Toll Plaza 0.88
9. Lay bye’s 0.24
10. Public Utility Services 0.71
11. Landscaping & Tree Plantation 0.56
12. Facility Centre at Osian 2.00
Total Cost 84.44
23
![Page 24: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/24.jpg)
ABSTRACT OF COST OF DEVELOPMENTS.
No.Particulars
Estimated Cost (Rs. In Crores)
Base Cost 84.73
13. Add: 10% Escalation for 2 year 0.00
14. Tender Premium @ 10% 8.44
15. Cost of contingencies 5% 4.22
16. Quality Control (1%) 0.84
17. Guarantee Commission to State Govt. (1%) 0.84
18. Cost of Land Acquisition 3.61
Sub Total 102.40
19. A & F Charges (10%) 10.24
20. Application Fee and Front end fee (0.5%) 0.51
Sub Total 113.16
21. Interest during construction 7.86
Grand Total 121.0224
![Page 25: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/25.jpg)
ABSTRACT OF COST OF MAJOR MAINTENANCE
S. No.
Particulars Treatment
Estimated Cost (Rs. In Crores)
in respective year
Major Maintenance with Paved Shoulders
1.Renewal Cost 7h Year
40mm BC 17.64
2.Strengthening Cost14th Year
50 DBM + 40mm BC
50.80
25
![Page 26: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/26.jpg)
FINANCIAL ANALYSIS
26
![Page 27: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/27.jpg)
TRAFFIC SCENARIO(7 DAYS CVC 21/05/10 TO 28/05/10)
Census Point PCU Tractor
Trolly
Car /JeepCat. 1(b)
BusesCat. 2
Trucks <5 TCat. 3(a)
Trucks >5 TCat. 3(b)
Multi Axle
Cat. 4
Osian - Jodhpur
(km 90/000)
3132 85 601 156 222 132 40
Mathania - Jodhpur
(km 109/500)
4506 75 1104 236 473 123 30
27
![Page 28: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/28.jpg)
%AGE OF TOLLABLE TRAFFIC
Tractor Trolley
(Commercial Use)
Cat. 1(a)
Car /JeepCat. 1(b)
BusesCat. 2
Trucks <5 T
Cat. 3(a)
Trucks >5 T
Cat. 3(b)
Multi AxleCat. 4
0% 60% 50% 70% 70% 70%
28
Assumed traffic growth per year 5%
![Page 29: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/29.jpg)
TOLLABLE ROUTES
Road SectionLength
(Km)
Osian - Jodhpur 47.00
Mathania - Jodhpur 19.00
29
![Page 30: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/30.jpg)
TOLLABLE TRAFFIC
Road Section
Tractor Trolly
(Commercial Use)Cat. 1(a)
Car /JeepCat. 1(b)
BusesCat. 2
Trucks <5 TCat. 3(a)
Trucks >5 T
Cat. 3(b)
Multi Axle
Cat. 4
Osian – Jodhpur
(47.00 km)0 295 92 152 90 27
Mathabia - Jodhpur (19.0 Km)
0 189 49 114 29 7
30
![Page 31: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/31.jpg)
TOLL PLAZA LOCATIONS
LOCATIONTOLLABLE LENGTH
(KM)RAOD SECTION
At Km. 90/000 47.00Osian - Jodhpur
At Km. 109/500 19.00 Mathania - Jodhpur
31
![Page 32: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/32.jpg)
SUMMARY OF PROPOSAL
Construction Period – 1 Years 0 Months Repayment Period – 19 Years 0 Months Concession Period – 20 Year 0 Months Annuity Model with Toll Annuity – 13.32 Crores Without 20% Subsidy Annuity – 10.69 Crores With 20% Subsidy
32
![Page 33: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/33.jpg)
SUMMARY OF PROJECT
S. No.
Particulars Detail
1 Length of road 48.00 Km
2 Design Life 20 Years
3 Project Cost Rs. 121.02 Crores
4 Construction Period 1 Year 0 months
5 Tollable Period 19 Years 0 months
6 Concession Period 20 Years 0 months
7 Rate of Interest 11.75%
8 Toll Plaza 2 Nos.
33
![Page 34: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/34.jpg)
MODELS OF PPP
S. No.
DescriptionInitial Cost
(Cr.)
Major Maintenanc
e
Viability
1.With Paved Shoulder
121.02 17.64 – 7th 50.80 – 14th
Non Viable
34
BOT
30% VGF (20% CENTRAL + 10% - O&M - STATE GOVT.)
S. N.
DescriptionInitial
Cost (Cr.)
IRR in 20 Years
DSCRViability
1.With Paved Shoulder 121.02 < 1.0 0.09 Non Viable
![Page 35: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/35.jpg)
MODELS OF PPP
S. No.
DescriptionInitial
Cost (Cr.)Annuity (Cr)
Viability
1. With Paved Shoulder 121.0213.32
10.69Viable
35
ANNUITY WITH TOLL
ANNUITY WITHOUT TOLL
S. No.
DescriptionInitial
Cost (Cr.)Annuity (Cr)
Viability
1. With Paved Shoulder 121.0216.28
13.65Viable
![Page 36: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/36.jpg)
RECOMMENDATION
Annuity Model with Toll Collection shall be adopted.
Toll Shall be nominal charged by Car & Public Transport. Only Commercial Vehicles like LCV’s, Trucks shall be charged.
Initially 2 Lane road with paved shoulder.
Facility Centre at Osian shall be worked out for revenue Generation to the Government.
Construction Period – 1 Years 0 Months
Repayment Period – 19 Years 0 Months
Concession Period – 20 Year 0 Months 36
![Page 37: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/37.jpg)
37
43
THANKTHANKSS
![Page 38: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/38.jpg)
38
![Page 39: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/39.jpg)
39
![Page 40: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/40.jpg)
TOLLABLE TRAFFIC - COMPARISON
Road Section
Tractor Trolly
(Commercial Use)Cat. 1(a)
Car /JeepCat. 1(b)
BusesCat. 2
Trucks <5 TCat. 3(a)
Trucks >5 T
Cat. 3(b)
Multi Axle
Cat. 4
Phalodi – Osian
(73.90 km)
0 348 48 139 96 21
Osian - Jodhpur (46.0 Km)
0 585 116 238 87 25
40
![Page 41: Jodhpur – Osian – Phalodi Phalodi (NH-15) Km 2/100 to Jodhpur (NH-65) km122/0 (SH-61) Jodhpur – Osian (I Phase) RAJASTHAN STATE ROAD DEVELOPMENT CONSTRUCTION](https://reader033.vdocument.in/reader033/viewer/2022050908/56649f435503460f94c63a88/html5/thumbnails/41.jpg)
DETAILS OF PROPOSED WORK & DEFECT LIABILITY PERIOD
S. No.
Stretch Year & Description
1 Km 57/0 to Km 91/0 2014 (Widening)
2 Km 69/0 to Km 70/0 2014 (Widening)
3 Km 81/0 to Km 89/0 CRF Tender Due
4 Km 63/0 to Km 74/0 CRF Tender Due
5 Km 118/0 to Km 122/0 Proposal for Jodhpur Bye – Pass
41