Large Wheel Installation
• Helped with initial installation in 2005
• Installed EML and EMS chambers in sector frame.
• Last chamber installed 31 October 2006
• Diagnosed and developed procedure for fixing potential o-ring leaks in EMS chamber cut-outs. Scheduled replacement of EPDM with Viton o-rings.
Small Wheel• Tooling for Phase 1.9 and Installation
– Modify Rotator Cart, with Marta and C. Weaverdyck, for Photogrammetry and Installation (especially for EIL.2-3 chambers)
– Use of Harvard lifting tool for de-crating BMC EI chambers– Create a Usage & Procedures manual, for above, and train
dedicated personnel – Modify 20mm EM chamber verticalizer for use with 12 mm EI
chambers• Coordinate/Organize Phase 1.9
– Update and modify traveler tasks for EI chambers– Compile Phase 1 information for Phase 1.9 – Develop file structure for database update– Ensure integration of Boston temperature sensors
• Understand Small wheel installation in Building 191– Space allocation and transport of chambers to 191– Develop procedure and assemble crew for chamber installation
• Commissioning small wheel with cosmic rays
Other Tasks
• Helped Integrate new BU people at CERN• Photograph and document activities in Building
180, 190 and 191• W cross section analysis, working with Di-
boson group (Bing Zhou)• Small wheel Commissioning
– DAQ for EIS and EIL chambers– Integrate MDT with CSC and TGC trigger– Final cosmic ray analysis before/after installation
• Administer Barracks computer cluster