![Page 1: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee](https://reader033.vdocument.in/reader033/viewer/2022042723/58799b971a28ab082c8b4725/html5/thumbnails/1.jpg)
Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee New Champlain Bridge Corridor Project Centre Saint-Charles – April 7, 2016
LaSalle Overpass & May Street
![Page 2: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee](https://reader033.vdocument.in/reader033/viewer/2022042723/58799b971a28ab082c8b4725/html5/thumbnails/2.jpg)
New Champlain Bridge Corridor Project 2
Objective of the presentation
1. Discuss progress of the proposed LaSalle Overpass development
2. Discuss progress of the proposed May Street reconfiguration
3. Questions and discussion
![Page 3: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee](https://reader033.vdocument.in/reader033/viewer/2022042723/58799b971a28ab082c8b4725/html5/thumbnails/3.jpg)
New Champlain Bridge Corridor Project 3
1 – LaSalle overpass Looking SOUTH
![Page 4: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee](https://reader033.vdocument.in/reader033/viewer/2022042723/58799b971a28ab082c8b4725/html5/thumbnails/4.jpg)
New Champlain Bridge Corridor Project 4
1 – LaSalle overpass Looking NORTH
![Page 5: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee](https://reader033.vdocument.in/reader033/viewer/2022042723/58799b971a28ab082c8b4725/html5/thumbnails/5.jpg)
New Champlain Bridge Corridor Project 5
1 – LaSalle overpass Characteristics
![Page 6: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee](https://reader033.vdocument.in/reader033/viewer/2022042723/58799b971a28ab082c8b4725/html5/thumbnails/6.jpg)
New Champlain Bridge Corridor Project 6
Revitalization of abutment wall artwork Public bench
based on users
Pedestrian & ambient lighting
1 – LaSalle overpass Subjects under discussion
![Page 7: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee](https://reader033.vdocument.in/reader033/viewer/2022042723/58799b971a28ab082c8b4725/html5/thumbnails/7.jpg)
New Champlain Bridge Corridor Project
Lighting proposal
7
To replace bollards: proposal for lighting columns with other sources of illumination to
add to the ambient lighting on the walls
Ambient lighting
Pedestrian lighting Auto traffic lighting
![Page 8: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee](https://reader033.vdocument.in/reader033/viewer/2022042723/58799b971a28ab082c8b4725/html5/thumbnails/8.jpg)
New Champlain Bridge Corridor Project 8
Piste cyclable
2 – May Street Context
Bike Path
![Page 9: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee](https://reader033.vdocument.in/reader033/viewer/2022042723/58799b971a28ab082c8b4725/html5/thumbnails/9.jpg)
New Champlain Bridge Corridor Project 9
2 – May Street Existing abutment wall
![Page 10: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee](https://reader033.vdocument.in/reader033/viewer/2022042723/58799b971a28ab082c8b4725/html5/thumbnails/10.jpg)
New Champlain Bridge Corridor Project 10
2 – May Street Entrance to pedestrian walkway and bike lane between May and Wellington streets
![Page 11: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee](https://reader033.vdocument.in/reader033/viewer/2022042723/58799b971a28ab082c8b4725/html5/thumbnails/11.jpg)
New Champlain Bridge Corridor Project 11
2 – May Street Exit from pedestrian walkway and bike lane on May Street
![Page 12: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee](https://reader033.vdocument.in/reader033/viewer/2022042723/58799b971a28ab082c8b4725/html5/thumbnails/12.jpg)
New Champlain Bridge Corridor Project
2 – May Street Development constraints
12
JAC
QU
ES L
AUZO
N S
T.
RU
SHBR
OO
KE S
T.
WEL
LIN
GTO
N S
T.
![Page 13: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee](https://reader033.vdocument.in/reader033/viewer/2022042723/58799b971a28ab082c8b4725/html5/thumbnails/13.jpg)
New Champlain Bridge Corridor Project 13
Section of street Paving 6.0 m Sidewalk 1.5 m (south) Borough street light (south)
SMALL - Spirea latifolia
LARGE – Amelanchier canadensis
MEDIUM – Physocarpus opulifolius Green strip shrubbery: between Jacques Lauzon & Rushbrooke Sts. • Criteria: spring & summer flowering (see
photos of typical shrubbery samples) Note: Green strip shrubbery drawing is currently being prepared.
2 – May Street Development proposal
CLIMBING – parthenocissus quinquefolia
May St.
Highway
Building
Wel
lingt
on S
t.
![Page 14: LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee](https://reader033.vdocument.in/reader033/viewer/2022042723/58799b971a28ab082c8b4725/html5/thumbnails/14.jpg)
3 – Questions & Discussion