Lesson Plan
Name of the Faculty : SANDEEP (VTF in CIVIL ENGG.)
Discipline : CIVIL Engg.
Semester : 3rd
Subject : Applied Mechanics
Lesson plan duration : 15 Weeks(July 2018 to Nov 2018)
Week
Theory Practical Lecture Day
Topic (including assignments /tests)
Practical Day
Topic
Week-1
1st Concept of engineering mechanics definition of mechanics, statics, dynamics 1st
Overview of the subject, Importance in industry & Applications of the subject.2nd Application of engineering
mechanics in practical fields3rd Different systems of units (FPS,
CGS, MKS and SI)
2nd
Overview of the subject, Importance in industry & Applications of the subject
4th Their conversion from one to another e.g. density, force, pressure, work, power, velocity,acceleration
Week 2
1st Simple Numerical Problems
1st
Verification of the polygon law of forces using Gravesand’s apparatus.2nd Fundamental Units and Derived Units.
3rd Concept of rigid body, scalar and vector
quantities 2nd
Verification of the polygon law of forces using Gravesand’s apparatus.4th Revision
Week 3
1st Mock Test
1st
To verify the forces in different members of jib crane.
2nd Laws of forces Definition of force, Bow’s Notations, types of force
3rd Point force/concentrated force &Uniformly distributed force, effects of force, characteristics of a force.
2nd
To verify the forces in different members of jib crane.
VF4
CIVIL
4th Different force systems,principle of transmissibility offorces, law of super-position
Week4
1st Composition and resolution of coplanar concurrent forces, resultant force, method of composition of forces 1st
To verify the reaction at the supports of a simply supported beam.
2nd laws of forces, triangle law of forces
3rd polygon law of forces - graphically, analytically, resolution of forces 2nd
To verify the reaction at the supports of a simply supported beam.4th Free body diagram
Equilibrant force and itsdetermination
Week 5
1st Lami's theorem [Simple problems on abovetopics]
1st
To find the mechanicaladvantage, velocity ratioand efficiency in case of aninclined plane.2nd Moment - Concept of moment
Moment of a force and units ofmoment
3rd Varignon's theorem (definitiononly)Principle of moment and itsapplications
2nd
To find the mechanicaladvantage, velocity ratioand efficiency in case of aninclined plane.4th (Levers – simple and compound,
steel yard, safety valve, reaction at support)
Week 6
1st Parallel forces (like and unlike parallel force), calculating their resultant
1st
To find the mechanical advantage, velocity ratio and efficiency of a screw jack.
2nd Concept of couple, itsproperties and effectsGeneral conditions ofequilibrium of bodies undercoplanar forces
3rd Position of resultant force bymoment
2nd To find the mechanical advantage, velocity ratio
[Simple problems on the abovetopics] and efficiency of a screw
jack.4th Revision of Chapter
Week 7
1st Mock Test1st Practice2nd Friction- Definition and
concept of friction, types of friction, force of friction, Limiting Friction
3rd Laws of static friction,coefficient of friction, angle offriction, angle of repose.
2nd Practice4th Equilibrium of a body lying on a
horizontal plane, equilibrium of a body lying on a rough inclinedplane
Week 08
1st Calculation of least forcerequired to maintain equilibriumof a body on a rough inclinedplane subjected to a force:
a) Acting along the inclinedplane
1st
To find the mechanicaladvantage, velocity ratioand efficiency of worm andworm wheel.
2nd b) At some angle with theinclined plane
3rd Ladder frictionAdvantages and Disadvantagesof friction
2nd
To find the mechanicaladvantage, velocity ratioand efficiency of worm andworm wheel.4th Methods of
increasing/decreasing the forceof friction.(Simple problems )
Week 09
1st Assignment1st
To find mechanicaladvantage, velocity ratioand efficiency of singlepurchase crab.
2nd Test
3rd Centre of Gravity - Concept, definition of centroid of plain figures
2nd
To find mechanicaladvantage, velocity ratioand efficiency of singlepurchase crab.
4th centre of gravity of symmetricalsolid bodies, difference betweencentroid and C.G
Week 10
1st Determination of centroid of plain and composite lamina using moment method only
1st
Practice2nd centroid of bodies with removed
portion3rd Determination of center of
gravity of solid bodies - cylinder
2nd Practice
4th Determination of center of gravity of solid bodies - cube, cuboid
Week 11
1st Determination of center of gravity of solid bodies- sphere
1st
To find out center of gravityof regular lamina.
2nd Determination of center ofgravity of solid bodies-composite bodies and bodieswith portion removed
3rd Simple problems on the above topics
2nd To find out center of gravityof regular lamina.
4th Simple problems on the above topics
Week12
1st Assignment on Chapter Centre of Gravity
1st
To find out center of gravityof irregular lamina.
2nd Mock Test
3rd Simple Machines- Definitionof Simple and compoundmachine (Examples) 2nd
To find out center of gravityof irregular lamina.
4th Definition of load, effort,velocity ratio, mechanical
advantage and efficiency of amachine
Week 13
1st load, effort, velocity ratio,mechanical advantage theirrelationship, law of machinesand efficiency of a machine 1st Practice
2nd Definition of ideal machine,reversible and self lockingmachine
3rd Effort lost in friction, Load lostin friction
2nd
Practice4th Determination of maximum
mechanical advantage andmaximum efficiency
Week 14
1st System of pulleys (first, second)1st
To determine coefficient offriction between three pairsof given surface.
2nd Third system of pulleys
3rd Determination of velocity ratio,mechanical advantage andefficiency
2nd
To determine coefficient offriction between three pairsof given surface.
4th Working principle and application of wheel and axle, Weston’s Differential Pulley Block
Week 15
1st simple screw jack, worm and worm wheel 1st Practice
2nd single and double winch crab.3rd Expression for their velocity
ratio and field of theirapplication[Simple problems on the abovetopics]
2nd Practice
4th Mock Test
Lecture Day
Topic
(including assignment /
test)
Practical
DayTopic
1st Introduction 1st
2nd Classification of bdg
3rd Parts Of Bdg
4th Foundation 3rd
5th Shallow Foundation
6th Spread Foundation
7th Deep Foundation 5th
8th Earthwork
9th Walls & its Purposes
10th Load bearing walls 7th
11th Material Classification
12th Partition wall
13th Scaffolding 9th
14th Brick Masonary
15th English Bond
16th Flemish Bond 11th
17th Test
18th Wall Constn
19th Mortar & its preperation 13th
20th Rubble Stone masonary 14th
21st Ashlar Stone masonary 15th
22nd Arch & Lintels
23rd Type Of Arches
24th Parabolic Arches
25th Stone Arches 17th
26th Brick Arches
27th Door & Windows
28th Material Classification
29th Windows
30th Door Frames
31st Damp Proofing
32nd Sources of Dampness
33rd Ill Effect Of Dampness
34th Damp Proofing Material 21th
35th Basement Damp Proof
36th Floors
37th Concrete Floor
38th Wooden Floor
39th Level / Slope
40th Roof
41st Pitched roof
42nd Arched Roof
16th
18th
20th
22th
24th
To construct brick bonds (English bond only) in
one, one and half and two brick thick: Walls for L,
T and cross junction
To construct brick bonds (English bond only) in
one, one and half and two brick thick: Columns
Laying of tile flooring on an already prepared lime
concrete base
Demonstration of following items of work : -
Timbering of excavated trenching
13th23th
14th
Construction of masonry walls
Laying of tile flooring on an already prepared lime
concrete base
11th
12th
Laying damp proof courses
9th
10th19th
6th12th
7th
8th
4th8th
5th10th
2nd4th
3rd6th
Demonstration of tools and plants used in
building construction
To prepare Layout of a building: two rooms
building with front verandah
Name of Faculty : Mr Prateek Malik (T&P)
Discipline : Civil Engineering Department
Semester : 3rd
Subject : Building Construction ENGINEERING
Lesson Plan Duration : 15 Weeks (July 2018 - Nov 2018)
Week
Theory Practical
1st2nd
**Work load (lecture/practical) per week (in hours): Lectures-04 , Practicals-02
43rd Rain Water Drainage 25th
44th False Ceiling
45th Stairs
46th Assignment
47th Clasification of Stairs
48th Material Classification
49th Layout Of Staircase
50th Geometrical Stairs
51st Surface Finishes
52nd Plastering
53rd Pointing
54th Paiting
55th Exterior Surfaces
56th Grooving And Hacking
57th Test
58th Anti Termite Tmt
59th Tmt of Wooden Area
60th Tmt in Existing Building
Interlocking tiles
26th
28th
29th
30th
Plastering and pointing exercise
Constructing RCC work
Pre-construction and post construction termite
treatment of building and woodwork
19th
20th
16th27th
17th
18th
15th
Govt. Polytechnic Education Society Meham (Rohtak) Civil Engineering Department
Lesson Plan Name of the Faculty Mr. ASHOK KUMAR (VTF In Civil Engg.)
Discipline Civil Engineering
Semester 3rd
Subject Building Drawing
Lesson Plan Duration From July 2018 to Nov 2018
Work Load (Theory/Practical) per week Practical - 06
week Day Practical
1
1st Details of spread footing foundations load bearing and non-load bearing wall for Given thickness of walls with the help of given data or rule of the thumb showing Offsets ,position of DPC. The details of the concrete and brick apron have to be shown in the drawing
2nd Details of spread footing foundations load bearing and non-load bearing wall for Given thickness of walls with the help of given data or rule of the thumb showing Offsets ,position of DPC. The details of the concrete and brick apron have to be shown in the drawing
2 1st Plans of‘ T ’and Corner junction of walls of 1Brick,1-1/2 Brick and 2 brick thick in English bond
2nd Drawing plan, elevation of arches : circular arch, segmental arch
3
1st Elevation, sectional plan and sectional side elevation of flush door, glazed door, Panelled door with wire gauge shutter.
2nd Elevation, sectional plan and sectional side elevation of flush door, glazed door, Panelled door with wire gauge shutter.
4 1st Elevation, sectional plan and sectional side elevation of flush door, glazed door, Panelled door with wire gauge shutter.
2nd Drawing plan, elevation of a small building by measurement and foundation detail And sectional elevation.
5 1st Drawing plan, elevation of a small building by measurement and foundation detail And sectional elevation.
2nd Drawing detailed plan ,elevation and section of a two room residential building From a given line plan, showing details of foundations ,roof and parapet
6 1st Drawing detailed plan ,elevation and section of a two room residential building From a given line plan, showing details of foundations ,roof and parapet
2nd Drawing detailed plan ,elevation and section of a two room residential building From a given line plan, showing details of foundations ,roof and parapet
7 1st Drawing detailed plan ,elevation and section of a two room residential building From a given line plan, showing details of foundations ,roof and parapet
2nd Drawings of following floors Cement concrete floors on ground and at first floor
8 1st Wooden flooring
2nd Bonded cement concrete flooring
VF3
9 1st Ceramic / vitrified tile flooring
2nd Drawing of flat roof, showing the heat/ thermal insulation provisions.
10 1st Drawing detail s of damp proofing
2nd Show the rain water drainage arrangement also
11 1st arrangement of roof sand walls as per BIS Code
2nd Drawing Damp Proofing details in basement of buildings
12 1st Drawing Damp Proofing details in basement of buildings.
2nd Drawing Damp proofing details in water
13 1st soil retaining structures 2nd Drawing Damp Proofing details in basement of buildings.( sheet -2) after
completion
14 1st soil retaining structures.( sheet -2) after completion
2nd Drawing Damp Proofing details in basement of buildings.( sheet -2) after completion
15 1st Drawing Damp Proofing details in basement of buildings.( lecture)
2nd Drawing Damp Proofing details in basement of buildings.( lecture)
Lecture
day
Topic
(Including assignment/ Test)
Practical
Day Topic
* * 1
* * 2
* * 3
* * 4
* * 5
* * 6
* * 7
* * 8
* * 9
* * 10
* * 11
* * 12
* * 13
* * 14
* * 15
* * 16
* * 17
* * 18
* * 19
* * 20
* * 21
* * 22
* * 23
* * 24
* * 25
* * 26
* * 27
* * 28
* * 29
* * 30
* * 31
* * 32
* * 33
* * 34
* * 35
* * 36
* * 37
* * 38
* * 39
* * 40
* * 41
* * 42
* * 43
* * 44
* * 45
* * 46
* * 47
* * 48
1
2
3
Name of Faculty : Mr. Prateek Malik
Discipline : Civil Engineering Department
Semester : 5th
Subject : COMPUTER APPLCATION IN CIVIL ENGINEERING
Lesson Plan Duration : 15 Weeks (July 2018 - Nov 2018)
**Work load (lecture/practical) per week (in hours): Lectures-00 , Practicals-06
Week
Theory Practical
4
5
6
7
8
INTRODUCTION
AUTO CAD
2D DRAWINGS
ELEVATION OF 2 ROOM
BUILDING
DEMONSTRATION OF STAAD-
PRO
DEMONSTRATION OF MS
PROJECT
DEMONSTRATION OF AUTO-
CIVIL
DEMONSTRATION OF MX ROAD
* * 49
* * 50
* * 51
* * 52
* * 53
* * 54
* * 55
* * 56
* * 57
* * 58
* * 59
* * 60
* * 61
* * 62
* * 63
* * 64
* * 65
* * 66
* * 67
* * 68
* * 69
* * 70
* * 71
* * 72
* * 73
* * 74
* * 75
* * 76
* * 77
* * 78
* * 79
* * 80
* * 81
* * 82
* * 83
* * 84
* * 85
* * 86
* * 87
* * 88
* * 89
* * 90
DESIGN OF DOUBLE STOREY
BUILDING USING 2D CAD
9
10
11
12
13
DESIGN OF 2 ROOM USING 2D
CAD
14
15
DEMONSTRATION OF
PRIMAVERA PROJECT PLANNER
AUTOCAD 2D
AUTOCAD 3D
STAAD PRO
DESIGN OF SINGLE STOREY
BUILDING USING 2D CAD
GOVERNMENT POLYTECHNIC MEHAM
Name of Faculty: SANDEEP (VTF in CIVIL ENGG.)Discipline: CIVIL ENGG.Semester: 5th
Subject: Environmental Education.Lesson Plan Duration: 15weeks (July 2018-Nov. 2018)Work load (Theory/Practical) per week (in hours): Theory-03
Week
Theory
1st
Week
1st
DayDefinition, Scope
2nd
DayImportance of Environmental Education
3rd
DayBasics of ecology
2nd
Week
1st
Daybiodiversity
2nd
Dayeco system
3rd
Daysustainable development
3rd
Week
1st
DaySources of pollution - natural and manmade
2nd
Daycauses
3rd
Dayeffects
4th
Week
1st
Daycontrol measures ofpollution
2nd
DayAir
3rd
DayWater
5th
Week
1st
DayRadioactiv
2nd
DayNoise
3rd
DaySoil and Nuclear
VIKASH SANGWAN
6th
Week
1st
DayAnd their units ofmeasurement
2nd
DaySolid waste management
3rd
DayCauses
7th
Week
1st
Dayeffects and control measures of urban andindustrial waste
2nd
DayDoubt of Unit 1st will be taken.
3rd
DayTest of Unit 1st.
8th
Week
1st
DayMining and deforestation
2nd
DayCauses
3rd
Dayeffects and control measures
9th
Week
1st
DayDoubt of 2nd will be taken.
2nd
DayTest of Unit 2nd
3rd
DayEnvironmental Legislation
10th
Week
1st
DayWater (prevention and control of pollution) Act 1974,
2nd
DayAir (Prevention and Control of Pollution) Act 1981
3rd
DayEnvironmental ProtectionAct 1986
11th
Week
1st
DayRole and Function of State Pollution Control Board
2nd
DayEnvironmentalImpact Assessment (EIA)
3rd
DayDoubt of Unit 3rd will be taken.
12th
Week
1st
DayTest of Unit 3rd
2nd
DayRole of Non-conventional Energy Resources
3rd
DaySolar
13th
Week
1st
DayWind
2nd Bio
Day
3rd
DayHydro
14th
Week
1st
DayCurrent Issues in Environmental Pollution
2nd
DayGlobal Warming, Green House Effect
3rd
DayDepletion of Ozone Layer
15th
Week
1st
DayRecycling of Material, Environmental Ethics, RainWater Harvesting, Maintenance of Groundwater, Acid Rain, Carbon Credits.
2nd
DayDoubt of Unit 4th will be taken.
3rd
DayTest of Unit 4th.
Govt. Polytechnic Education Society Meham(Rohtak)
Civil Engineering DepartmentLesson Plan
Name of the Faculty Mr. ASHOK KUMAR (VTF in Civil Engg.)
Discipline Civil Engineering
Semester 3rd
Subject Fluid Mechanics
Lesson Plan Duration From July 2018 to Nov 2018
Work Load (Theory/Practical) per week
Theory – 03 / Practical - 02
week
Day Theory Day
Practical
1
1st
day1Introduction:1.1Fluids: Real and ideal fluids
1st
dayTo verify Bernoulli’s Theorem
2nd
day1.2FluidMechanics,Hydrostatics, Hydrodynamics, Hydraulics
3rd
day2.Properties ofFluids (definition only)2.1Mass density, specific weight, specific gravity, viscosity,
2
1st
daysurface tension cohesion, adhesion and capillarity, vapour pressure and compressibility
1st
dayTo find out
venturimetercoefficient
2nd
day2.2Units of measurement and their conversion
3rd
day3.Hydrostatic Pressure 3.1Pressure, intensity of pressure, pressure head,
3
1st
dayPascal's law and its applications 1st
dayTo determine coefficient
of velocity (Cv)2nd
day3.2Total pressure, resultant pressure, and centre of pressure
3rd
day3.3Total pressure and centre of pressure on horizontal,
4
1stday vertical and inclinedplane surfaces of rectangular, triangular, trapezoidal shapes and
1st
dayTo determine
coefficient of velocity (Cv)
AJAY
circular. (No derivation)2ndday Doubt will be taken3rdday 4.Measurement of Pressure:
4.1Atmospheric pressure, gauge pressure, vacuum pressure and absolute pressure.
5
1st
day4.2 Piezometer, simple manometer and differential manometer, Bourden gauge and dead weight pressure gauge
1st
dayCoefficient of contraction (Cc) of an orifice verify the between them relation
2nd
day5.Fundamentals of Fluid Flow:5.1Types of Flow: Steady and unsteady flow, laminar and turbulent flow,uniform and non uniform flow
3rd
day5.2Discharge and continuity equation (flow equation){No derivation}
6
1st
day5.3Types of hydraulic energy: Potential energy, kinetic energy, pressure energy
1st
dayTo perform Reynold's experiement
2nd
day5.4Bernoulli's theorem; statement and description (without proof of theorem)and simple numerical problems
3rd
dayUnit test will be conduct
7
1st
day6.Flow Measurements(brief description with simple numerical problems)6.1Venturimeter
1st
day To verify loss of head in pipe flow due toa)Sudden enlargement2nd
day6.2Mouthpiece and Pitot tube
3rd
day6.3Orifice and Orificemeter
8
1st
day6.4 Current meters 1st
daySudden contraction
2nd
day6.5Notches and weirs (simple numerical problems)
3rd
dayRevision of unit 6
1st
day7.Flow through Pipes: 1st Sudden bend
9 7.1Definition of pipe flow; Reynolds number
day
2nd
daylaminar and turbulent flow-explained through Reynolds’s experiment
3rd
day7.2Critical velocity and velocity distributions in a pipe for laminarFlow
10
1st
day7.3Head loss in pipe lines due to friction, sudden expansion and sudden contraction,
1st
dayDemonstration of use of current meter
2nd
dayentrance, exit, obstruction and change of direction (Noderivation of formula)
3rd
day7.4Hydraulic gradient line and total energy line
11
1st
day7.5Flow from one reservoir to another through a long pipe of uniform crosssection (simple problems)
1st
dayDemonstration of use of pitot tube
2nd
day7.6Pipes in series and parallel
3rd
day7.7Water hammer phenomenon and its effects (only definition anddescription)
12
1st
day8.Flow through open channels:8.1Definition of an open channel, uniform flow and non uniform flow
1st
dayTo determine coefficient of discharge of a rectangular notch
2nd
day8.2Discharge through channels using(i) Chezy's formula (no derivation)
3rd
dayDoubt will be taken
13
1st
dayii)Manning's formula (no derivation)iii)Simple Numerical Problems
1st
dayTo determine coefficient of discharge of a triangular notch
2nd
day8.3Most economical channel sections(no derivation)(i)Rectangular
3rd
dayii)Trapezoidal(iii)Simple Numerical Problem
14
1st
day8.4Headloss in open channel due to friction
1st
dayTo verify Bernoulli’s Theorem (revision)
2nd
dayUnit test will be conduct
3rd
day9.Hydraulic Pumps:
15
1st
dayHydraulic pump, reciprocatingpump
1st
dayVisit to Hydraulic researchstation is must to explain the various concepts
2nd
day
Centrifugal pumps(No numerical and derivations) (may be demonstrated with the help of working models)
3rd
dayStudy of previous year questions paper
Lecture
Day
Topic
(including assignment / test)
Practical
DayTopic
1st INTRODUCTION
2nd IRC CLASSIFICATION
3rd ROAD GEOMETRICS
4th AVG SPEED , SIGHT DISTANCE
5th CURVES
6th SUPERELEVATION
7th CROSS SECTION OF ROAD
8th CUTTING & FILLING
9th CURVE ALIGNMENT
10th HIGHWAY SURVEY
11th TOPOGRAPHIC MAP
12th ALIGNMENT OF ROAD IN PLAIN AREA
13th ALIGNMENT OF ROAD IN HILLY AREA
14th MARKING OF ALIGNMENT
15th DATA ANALYSIS OF TOPOGRAPHIC MAP
16th ROAD MATERIAL & ITS TYPES
17th SOIL & AGGREGATES
18th BINDER MATERIAL
19th BITUMEN
20th PROPERTIES AS PER BIS
21st TEST / ASSIGNMENT
22nd PENETRATION TEST
23rd VISCOSITY TEST
24th BITUMEN MODIFIERS
25th FLEXIBLE PAVEMENTS
26th RIGID PAVEMENTS
27th TYPICAL CROSS SECTION OF ROADS
28th CBR METHOD
29th AGGREGATE AND ITS PROPERTIES
30th ALIGNMENT OF ROAD
31st BENCH MARK & GRADIENTS
32nd STABILIZATION
33rd GRANULAR BASE COARSE
34th BITUMEN COARSE
35th METHOD OF CONSTRUCTION
36th TYPE OF SURFACING
37th SURFACE COATING
38th JOINTS IN RIGID PAVEMENTS
39th COMPACTING & FINISHING
40th TEST / ASSIGNMENT
41st TYPICAL CROSS SECTION OF HILL ROADS
42nd LANDSLIDE
43rd DRAINAGE & EROSION
44th SNOW & LAND SUBSIDENCE
45th DRAINAGE OF ROAD
**Work load (lecture/practical) per week (in hours): Lectures-05 , Practicals-02
15th
8th 8th
Name of Faculty : Mr Prateek Malik (T&P)
Discipline : Civil Engineering Department
Semester : 5th
Subject : HIGHWAY ENGINEERING
Lesson Plan Duration : 15 Weeks
Week
Theory Practical
1st
2nd
3rd
4th
5th
6th
7th
6th
7th
1st
13th
14th
9th
10th
12th
9th
10th
11th 11th
12th
2nd
3rd
4th
5th
15th
14th
13th
Determination of penetration value of
bitumen
Determination of softening point of
bitumen
Determination of ductility of bitumen
Determination of impact value of the road
aggregate
Determination of abrasion value (Los
Angeles’) of road aggregate
46th CROSS DRAINAGE WORKS
47th STORM DRAINS
48th EMBANKMENT
49th TYPICAL CROSS SECTION
50th MAINTANANCE OF ROAD
51st FAILURE OF FLEXIBLE PAVEMENT
52nd CAUSES & REMEDIES
53rd SEAL COAT & PATCH WORK
54th MAINTANANCE OF CONCRETE ROAD
55th MAINTANANCE OF TRAFFIC CONTROL DEVICE
56th CONSTRUCTION EQUIPMENT
57th TRACTOR & TRUCKS
58th ASPHALT MIXERS
59th ROAD PAVERS BOILERS
60th TEST / ASSIGNMENT
61st AIRPORT ENGINEERING
62nd AVIATION SCENARIO
63rd SITE SELECTION
64th ZONING LAWS
65th RUNWAY
66th TAXIWAYS
67th APRON
68th SUBGRAD EPREPERATION OF ROADS
69th BERMS
70th ROAD SHOULDERS
71st IRC CLASSIFICATION
72nd CRRI
73rd MORTH
74th NHAI
75th DIFF B/W RIGID & FLEXIBLE PAVEMENT
24th
25th
18th
21st
22nd
23rd
16th
17th
16th
17th
18th
19th
20th
19th
20th
21st
22nd
23rd
29th
30th
24th
25th
26th
27th
28th
Mixing and spraying equipment
A compulsory visit to Ready Mix Concrete
plant
Determination of the California bearing
ratio (CBR) for the sub-grade soil
Visit to Hot mix plant
Visit to highway construction site for
demonstration of operation of:
Tipper, tractors (wheel and crawler),
scraper, bulldozer, dumpers, shovels,
grader,
roller, dragline, road pavers, JCB etc.
Govt. Polytechnic Education Society Meham(Rohtak)
Civil Engineering DepartmentLesson Plan
Name of the Faculty Mr. ASHOK KUMAR (VTF In Civil Engg.)
Discipline Civil Engineering
Semester 5th
Subject Soil and Foundation Engineering
Lesson Plan Duration From July 2018 to Nov 2018
Work Load (Theory/Practical) per week
Theory – 04 / Practical - 02
week
Day Theory Day
Practical
1
1st
day1.Introduction:1.1 Importance of soil studies in Civil Engineering
1st
dayTo determine the moisture content of A given sample of soil
2nd
day1.2 Geological origin of soils with special reference to soil profiles in India
3rd
dayresidual and transported soil, alluvial deposits, lakedeposits, local soil found in J&K, dunes and loess,
4th
dayglacial deposits, black cotton soils,condition in which above deposits are formed and their engineering characteristics
2
1st
day1.3 Names of organizations dealing with soil engineering work in India, soil map of India
1st
day2.Auger Boring and StandardPenetration Testa)Identifying the equipment and accessoriesb)Conducting boring and SPTat a given location
2nd
dayPhysical Properties of Soils:2.1Constituents of soil and representation by a phase diagram
AJAY
3rd
day2.2Definitions of void ratio, porosity, water content,
4th
daydegree of saturation,specific gravity, unit weight, bulk density/bulk unit weight,
3
1st
daydry unit weight,saturated unit weight and submerged unit weight of soil grains and correlation between them
1st
dayc)Collecting soil samples andtheir identificationd)Preparation of boring log and SPT graphse)Interpretation of test results
2nd
day2.3Simple numerical problems with the help of phase diagrams
3rd
day3.Classification and Identification of Soils3.1.Particle size, shape and theireffect on engineering properties of soil,particle size classification of soils
4th
day3.2Gradation and its influence on engineering properties
4
1stday 3.3Relative density and its use in describing cohesionless soils
1st
dayExtraction of Disturbed andUndistrubed Samplesa)Extracting a block sampleb)Extracting a tube sample
2ndday 3.4Behaviour of cohesive soils with change in water content, Atterberg’s limit definitions, useand practical significance
3rdday 3.5Field identification tests for soils
4th
day3.6Soil classification system as
per BIS 1498; basis, symbols,major division sand sub divisions, groups, plasticity chart; procedure for classification of a given soil
5
1st
day4.Flow of Water Through Soils:4.1Concept of permeability and its importance
1st
dayc)Extracting a disturbed samples for meChemical analysis.d)Field identification of samples
2nd
day4.2Darcy's law, coefficient of permeability, seepage velocity and factors affecting permeability
3rd
day4.3Comparison of permeability of different soils as per BIS
4th
day4.4Measurement of permeability in the laboratory
6
1st
day.5Effective Stress: (Conceptonly)5.1Stresses in subsoil
1st
dayField) Density Measurement (Sand Replacement and Core Cutter MethodCalibration of sandb)Conducting field density test at a given location
2nd
day5.2Definition and meaning of total stress, effective stress and neutral stress
3rd
day5.3Principle effective stress of
4th
day5.4Importance of effective stress in engineering problems6 Deformation of Soils6.1Meaning, conditions/situations of occurrence with emphasis on practical significance of
1st
daysignificance of(a) 1st Determination of water
7
Consolidation and settlementb)Creepc)Plastic flow
day contentd)Computation and interpretation of results
2nd
dayd)Heavinge)Lateral movementf)Freeze and thaw of soil
3rd
day6.2Definition and practical significance of compression index, coefficient ofconsolidation, degree of consolidation
4th
day6.3Meaning of total settlement, uniform settlement and differential settlement;rate of settlement and their effects
8
1st
day6.4Settlement due to construction operations and lowering of water table
1st
dayLiquid Limit and Plastic Limit Determination:a)Identifying various grooving toolsb)Preparation of samplec)Conducting the testd)Observing soil behaviour during testse)Computation, plotting and interpretation of results
2nd
day6.5Tolerable settlement for different structures as per BIS
3rd
day7.Shear Strength Characteristics of Soil7.1.Concept and Significance ofshear strength
4th
day7.2Factors contributing to shear strength of cohesive and cohesion less soils,Coulomb's law
7.3Examples of shear failure in soils
9
1st
day8.Compaction:8.1Definition and necessity of compaction
1st
day6.Mechanical Analysisa)Preparation of sampleb)Conducting sieve analysisc)Computation of results
2nd
day8.2Laboratory compaction test (standard and modified proctor test as perBISdefinition and importance of optimum water content,
3rd
daymaximum drydensity; moisture dry density relationship for typical soils with differentcompactive efforts
4th
day8.3.Compaction control; Density control, measurement of field density by corecutter method and sand replacement method, moisture control,
10
1st
dayProctor'sneedle and its use, thickness control, jobs of an embankment supervisor inrelation to compaction
1st
dayd)Plotting the grain size distribution curvee)Interpretation of the curve
2nd
day9.Soil Exploration:9.1Purpose and necessity of soilexploration
3rd 9.2Reconnaissance, methods of
day soil exploration, Trial pits, borings (auger,wash, rotary, percussion to be briefly dealt
4th
day9.3Sampling; undisturbed, disturbed andrepresentative samples; selection oftype of sample; thin wall and piston samples; area ratio, recovery ratio
11
1st
daysamples and their significance, number and quantity of samples, resetting,sealing and preservation of samples.9.4Presentation of soilinvestigation results
1st
dayLaboratory Compaction Tests (Standard ProctorTest)a)Preparation of sampleb)Conducting the test
2nd
dayUnit test will be conduct
3rd
day10.1Definition and significance of ultimate bearing capacity, netsafe bearingcapacity and allowable bearing pressure
4th
day10.2 Guidelines of BIS (IS 6403) for estimation of bearing capacity of soil
12
1st
dayDoubt will be taken 1st
dayObserving soil behavior during testd)Computation of results and plotting
2nd
day10.3 Concept of vertical stress distribution in soils due to foundation loads, pressure bulb
e)Determination of optimum moisturecontentand maximum dry density
3rd
day10.4Applications of SPT, unconfined compression test and direct shear test inestimation of bearing capacity
4th
day10.5Plate load test (no procedure details) and its limitations
13
1st
day10.6 Factors affecting bearing capacity
1st
day8.Demonstration of Unconfined Compression Testa)Specimen preparationb)Conducting the test
2nd
day10.7 Bearing Capacity of soilConcept of bearing capacity
3rd
day10.8Improvement of bearing capacity by sand drain method
4th
daycompaction, use of geo synthetics
14
1st
day, use of geo synthetics 1st
dayc)Plotting the graphd)Interpretation of results andfinding/bearing capacity
2nd
dayRevision of questions paper
3rd
day11.Foundation Engineering:Concept of shallow and deep foundation;
4th
daytypes of shallow foundations:isolated combined, strip mat,and their suitability. Factors affecting the depth of shallowfoundationsUnit test will be conduct
15
1st
dayUnit test will be conduct 1st
dayDemonstration of:a)Direct Shear andVane Shear Test on sandysoil samples
2nd
daydeep foundations, type of piles and their suitability
3rd
daypile classification on the basis of material, pile group and pile
GOVERNMENT POLYTECHNIC MEHAM
Name of faculty :- Sh. SandeepDiscipline :- Civil Engg.Semester :3rdSubject :- SOFT SKILL-Ilesson plan duration :-15 weeks
Practicalweek
1st 1st day Soft Skills - Concept
2nd Soft Skills - Conceptday
2nd 1st day Soft Skills - importance
2nd Soft Skills - importanceday
3rd 1st day Communication Skills- Improving verbal communication
2nd Communication Skills- Improving verbal communicationday
4th 1st day Communication Skills practice
2nd Communication Skills practiceday
5th 1st dayReport Writing
2nd Report Writingday
6th 1st dayMethod to enhance memory and concentration
2nd Method to enhance memory and concentrationday
7th 1st day Component of overall concept of overall personality
2nd
day Component of overall concept of overall personality
8th 1st day Cultural activity
2nd Cultural activityday
9th 1st day Sports
2nd Sportsday
10th 1st day Dressing sense
2nd
day Dressing sense
11th 1st day Etiquettes
2nd Etiquettesday
12th 1st day body language
2nd body languageday
13th 1st day Set goal for overall personality
2nd Set goal for overall personalityday
14th 1st day Understand the concept of quality and its implementation.
2nd Understand the concept of quality and its implementation.day
15th 1st day Mock interview
2nd Mock interviewday
Name of the Faculty :
Discipline CIVIL ENGINEERING
Semester 5th
Subject Soft Skills
Lesson Plan Duration : From July 2018 to Nov2018
Work Load (Theory/Practical) per week: Practicals-05
Week Practical
Practical
DayTopic
1 Unit1:Career Planning-Introduction
2 Benefits of Career Planning
3 Guidelines for choosing a career
4 Myths about choosing a career
5 Tips for successful Career Planning
1 Developing career goals
2 Final Thoghts on Career Planning
3 Things one should know while starting career and during his career
4 Revision and Assignment
5 Oral Test
1 Unit 2:Body Language-Introduction
2 Body Talk
3 Voluntary and Involuntary Body Language
4 Origin of Body Language
5 Uses of Language
1 Body Language in building Interpersonal relations
2 Body Language in building Industrial relations
3 Reasons to study Body Language
4 Improving your Body Language
5 Types of Body Language
1 Gender Differences
2 Female interest
3 Shaking hands with women
4 Interpreting Body Language
5 Developing confidence with correct Body Language
1 Revision and Assignment
2 Oral Test
3 Unit 3:Time Management-Introduction
4 Take a good look at the people around you
5 Examine your work
1 Sense of Time Management
2 Time is Money
3 Features of Time
4 Three secrets of Time Management
5 Time Management Matrix
1 Effective scheduling
2 Grouping of Activities
3 Five steps to successful Time Management
4 Difficulties in Time Management
5 Evils of not planning
1 Time Management is a Myth
2 Overcoming Procastination
3 Ways to find free time
4 Time Management tips for students
5 Interesting facts about Time
1 Ideal way of spending a Day
2 Time Wasters
3 Time Savers
4 Realizing the value of Time
5 Time Circle Planner
2nd
1st
9th
8th
7th
6th
5th
4th
CIVIL ENGINEERING DEAPRTMENT
LESSON PLAN
10th
3rd
1 Revision and Assignment
2 Oral Test
3 Unit 5: Stress management-Introduction
4 Meaning of stress
5 At one level stress may be a positive aid to performance
1 At one level stress may be a negative aid to performance
2 Effects of stress
3 Kinds of stress
4 Source of stress
5 Few other common sources of stress
1 Case Studies
2 Behaviour identified with stress
3 Assessing the existence of stress
4 What are the signs of stress?
5 Spotting stress in you
1 Stree Management Tips
2 Teenage stress
3 Make the morning memorable
4 Revision and Assignment
5 Oral Test
1 Lecture on Harrasement of Women at WorkPlace
2 Lecture on Indecent Portrayal of women
3 Lecture on Harrasement of Male by Misuse of Acts
4 Revision
5 Revision
15th
14th
13th
12th
11th
GOVERNMENT POLYTECHNIC MEHAM
Name of Faculty: SANDEEP (VTF in CIVIL ENGG.)Discipline: CIVIL ENGG.Semester: 5th
Subject: Steel Structure Design.Lesson Plan Duration: 15weeks (July 2018-Nov. 2018)Work load (Theory/Practical) per week (in hours): Theory-05
Week
Theory
1st
Week
1st
DayStructural Steel and Sections
2nd
DayProperties of structural steel as per IS Code
3rd
DayDesignation of structural steel sections as per IS handbook andIS:800 - 2007
4th
DayRiveted Connections
5th
DayTypes of rivets, permissible stresses in rivets, types of riveted joints, specificationsfor riveted joints as per IS 800
2nd
Week
1st
DayFailure of a riveted joint. Assumptions in thetheory of riveted joints. Strength and efficiency of a riveted joint
2nd
DayDesign ofriveted joints for axially loaded members ( No Staggered riveting).
3rd
DayBolted and Welded connections
4th
DayTypes of bolts and bolted joints, specifications for bolted joints as per IS:800 - 2007
5th
DayTypes of welds and welded joints, advantages and disadvantages of weldedjoints and bolted joints design of fillet and butt weld
3rd
Week
1st
DayPlug and slot welds(Descriptive No numerical on plug and slot welds)
2nd
DayDoubt of Unit 1st will be taken.
3rd
DayDoubt of Unit 2nd will be taken.
4th
DayTension Members
VF3
5th
DayAnalysis and design of single
4th
Week
1st
Daydouble angle section
2nd
Daytension members and theirrivetted and welded connections
3rd
Daytension members and theirrivetted and welded connections with gusset plate.
4th
DayCompression Members
5th
DayDoubt of Unit 3rd will be taken.
5th
Week
1st
DayAnalysis and design of single angle section (Compression Member)
2nd
DayAnalysis and design of double angle section (Compression Member)
3rd
DayAnalysis and design of single and double angle sections compression members(struts) and their welded connections with gusset plate as per IS:800
4th
DayDoubt of Unit 4th will be taken.
5th
DayTest of Unit 1st.
6th
Week
1st
DayTest of Unit 2nd.
2nd
DayRoof Trusses
3rd
DayForm of trusses, pitch of roof truss
4th
Dayspacing of trusses, spacing of purlins
5th
Dayconnection between purlin and roof covering
7th
Week
1st
DayConnection between purlin andprincipal rafter (no design, only concept)
2nd
DayDoubt of unit 5th will be taken.
3rd
DayTest of unit 3rd.
4th
DayTest of unit 4th.
5th
DayColumns
8th
Week
1st
DayConcept of buckling of columns
2nd effective length and slenderness ratio
Day
3rd
Daypermissible stresses in compression as per IS:800 for different endconditions
4th
DayAnalysis and Design of axially loaded single section steelcolumn
5th
DayDoubt of Unit 6th will be taken.
9th
Week
1st
DayTest of Unit 5th.
2nd
DayTest of Unit 6th.
3rd
DayTypes of column bases (Descriptive only)
4th
DayBeam and column, frame and seated connections (descriptive only, nodesign)
5th
DayBeams
10th
Week
1st
DayAnalysis and design of single section
2nd
Daysimply supported laterally restrained steelbeams
3rd
DayIntroduction to plate girder and functions of various elements of a plategirder
4th
DayDoubt of Unit 7th will be taken.
5th
DayTest of Unit 7th.
11th
Week
1st
DayFabrication and Erection of Steel Structures like trusses
2nd
Daycolumns and girders
3rd
DayDoubt of Unit 8th will be taken.
4th
DayTest of Unit 8th.
5th
DayDoubt of Unit 9th will be taken.
12th
Week
1st
DayTest of Unit 9th.
2nd
DayMasonry structures
3rd
DayDesign of brick column
4th
DayDesign of wall Foundation
5th
DayDoubt of unit 10th will be taken.
13th
Week
1st
DayTest of Unit 10th.
2nd
DayRevised 1st Unit.
3rd
DayRevised 2nd Unit.
4th
DayRevised 3rd Unit.
5th
DayRevised 4th Unit.
14th
Week
1st
DayRevised 5th Unit.
2nd
DayRevised 6th Unit.
3rd
DayRevised 7th Unit.
4th
DayRevised 8th Unit.
5th
DayRevised 9th Unit.
15th
Week
1st
DayRevised 10th Unit.
2nd
DayPrevious question papers will be discussed
3rd
DayPrevious question papers will be discussed
4th
DayPrevious question papers will be discussed
5th
DayPrevious question papers will be discussed
GOVERNMENT POLYTECHNIC MEHAM
Name of Faculty: MOHD SHAD Discipline: CIVIL ENGG. Semester: 5th
Subject: Structural Drawing Lesson Plan Duration: 15weeks (July 2018-Nov. 2018) Work load (Theory/Practical) per week (in hours): Practical-06
Week Practical
1st Week
1st Day Drawing No. 1: RC Slabs - One way slab, Two way slab and Cantilever Slab.
2nd Day Drawing No.2 : Beams - Singly and doubly reinforced rectangular beams and Cantilever beam (All beams with vertical stirrups)
2nd Week
1st Day Drawing No.3 : Columns and Footings – Square, Rectangular and Circular Columns with lateral ties and their isolated sloped column footings.
2nd Day Drawing No. 4 : Portal Frame – Three bay two storey RC portal frame with blow up of column beam junctions
3rd Week
1st Day Revised Drawing No. 1
2nd Day Revised Drawing No. 2
4th Week
1st Day Sheet Evaluation
2nd Day Sheet Evaluation
5th Week
1st Day Drawing No.5: Dog legged stairs for single storey building
2nd Day Drawing No.6 : Draw atleast one sheet using CAD software
6th Week
1st Day Revised Drawing No. 2
2nd Day Revised Drawing No. 3
7th Week
1st Day Sheet Evaluation
2nd Day Sheet Evaluation
8th Week
1st Day Drawing No. 1: Roof Truss – Drawing of Fink Roof Truss with details of joints, fixing details of purlins and roof sheets.
2nd Day Drawing No.2 : Column and Column Bases - Drawing of splicing of steel columns
9th Week
1st Day Drawings of slab base, gusseted base and grillage base for single section steel columns
2nd Day Revised Drawing No. 4
10th Week
1st Day Sheet Evaluation
2nd Day Drawing No.3 : Column Beam Connections
VF4VF4
11th Week
1st Day Sealed and Framed Beam to Beam Connections
2nd Day Sealed and Framed beam o Column Connections
12th Week
1st Day Drawing No. 4 : Plate Girder
2nd Day Plan and Elevation
13th Week
1st Day Plate Girder with details at supports and connection of stiffness, flange angles and cover plate with web highlighting curtailment of plates.
2nd Day Drawing No. 5 : Draw atleast one sheet using CAD software
14th Week
1st Day Sheet Evaluation
2nd Day Sheet Evaluation
15th Week
1st Day Sheet Evaluation
2nd Day Sheet Evaluation