University of New South Wales
Loading Dock Traffic Management Plan
Upper Campus Store
Shauna Simon
09/11/2017
LoadingDockTrafficManagementPlan
2
Contents
Purpose ......................................................................................................................................... 3
General Operations ........................................................................................................................ 3
Upper Campus Store Operating Hours ............................................................................................... 3
Access and Route for Waste Management and Shared Gas Store ..................................................... 3
Collection of Store Orders and Deliveries ........................................................................................... 3
Multiplex – Shared Access .................................................................................................................. 4
Loading and Unloading ....................................................................................................................... 4
Security‐ Store Areas ........................................................................................................................... 4
Traffic Control ................................................................................................................................ 5
Access Routes ...................................................................................................................................... 5
Forklift Usage ...................................................................................................................................... 5
General Waste Removal ..................................................................................................................... 5
Liquid Nitrogen Fills and Dry Ice ......................................................................................................... 5
Removal of Chemical Waste ............................................................................................................... 6
Delivery of Dangerous Goods ............................................................................................................. 6
Biological Waste Removal ................................................................................................................... 6
Cardboard/Waste Paper removal ....................................................................................................... 6
Skip Bin ................................................................................................................................................ 6
Multiplex ............................................................................................................................................. 6
Health and Safety .......................................................................................................................... 6
Forklift, Pedestrians, Couriers ............................................................................................................. 6
Noise ................................................................................................................................................... 7
Multiplex ............................................................................................................................................. 7
Dangerous Goods ................................................................................................................................ 7
Equipment and Machinery .................................................................................................................. 7
External Companies ............................................................................................................................ 8
Communication ............................................................................................................................. 8
Loading Dock Activities ....................................................................................................................... 8
Store Activities .................................................................................................................................... 8
Multiplex ............................................................................................................................................. 8
LoadingDockTrafficManagementPlan
3
PurposeThe purpose of this document is to provide information on the traffic management associated with
the daily operations of the Upper Campus Store and E26 Loading Dock.
Information contained in this document is relevant to all regularly accessing the loading dock. It is
the responsibility of the Upper Campus Store Manager, Multiplex and other relevant UNSW
operational staff to ensure that the policies and procedures referred to in this document are
observed and performed by all which includes contractors, couriers and all UNSW staff carrying out
regular daily operations within the area.
GeneralOperations
UpperCampusStoreOperatingHoursAll Upper Campus Store operations will be conducted between the following times:
7:30am – 4pm Monday to Friday
CLOSED Saturday and Sunday
Location
E26, Bioscience South
LG018 Loading Dock, Via Gate 11 Botany Street,
UNSW, Kensington, SYDNEY, NSW, 2052
Map – Attachment 1
D26 LG Hoarding and UNSW Shared Access Routes – Attachment 2
AccessandRouteforWasteManagementandSharedGasStoreClear pathways have been marked for all buildings within the upper campus precinct to access waste
rooms.
Inductions are to be completed for the following areas before access can be given:
General Waste Store
Chemical Waste Store
Biological Waste Store
Gas Cylinder Store
Inductions for all stores are to be conducted by area or laboratory manager.
D26 LG Hoarding and UNSW Shared Access Routes – Attachment 2
CollectionofStoreOrdersandDeliveriesClear pathways have been marked for all to access the Store.
D26 LG Hoarding and UNSW Shared Access Routes – Attachment 2
LoadingDockTrafficManagementPlan
4
Multiplex–SharedAccessShared accessed with MPX will continue into 2019 for Multiplex to continue to carry out works on
E26 Bioscience South and D26 Bioscience Building.
Rubbish removal for D26 demolishment and refurbishment will continue to be 6am to 7am daily and
7am to 5pm Saturdays.
Any access required outside the above mentioned must be discussed and coordinated between the
Upper Campus Store and Multiplex.
MPX D26 LG Demolition Hoardings and Access Routes – Attachment 2
MPX D26 LG Demolition Dust Control – Attachment 3
MPX D26 LG Demolition HAZMAT and Dust Control – Attachment 4
LoadingandUnloadingThe loading dock will only be used for vehicles and trucks to unload deliveries, equipment and any
items that are to be delivered to the precinct (Bioscience, Samuels, Wallace Wurth, Lowy and
occasionally Matthews). Each bay is a restricted 15‐minute loading and unloading zone only, strict
fines will apply.
Parking vehicles are not permitted in the area as this is used for deliveries only. No courier or parking
vehicle is to park outside the spaces indicated to allow continuous movement of traffic as the area is
also used as an emergency egress.
Use of the area after hours is permitted to those with access to buildings within the precinct
(Bioscience, Samuels, Wallace Wurth, Lowy and Matthews). It is the responsibility of the
user/operator to coordinate with UNSW security and ensure work is conducted in line with UNSW’s
Health and Safety’s Working After Hours Guideline. It is courtesy to make The Upper Campus Store
aware of any after‐hours movements within the loading dock, approval from Store Manager is not
required unless there are possibly disruptions during Store operating hours.
Security‐StoreAreasStrict access to main store areas during operational hours apply unless accompanied by store staff.
Access is limited outside of regular operational hours to those who have been granted access by
Store Manager, this includes stores staff and contractors who have been inducted into the area/s.
Anyone requiring access to the holding area to load/unload will need to arrange prior with Store and
be accompanied by Stores staff.
Any after‐hours work to be conducted will need to be approved by the Store Manager and will need
to be coordinated with UNSW security and conducted in line with UNSW’s Health and Safety’s
Working After Hours Guideline. Any person found inside a building after hours without authorisation
or an access card (with their name and photo on it) will be asked to leave the building immediately.
LoadingDockTrafficManagementPlan
5
All store areas are locked by either swipe or key. Strict access to chemical, liquid nitrogen and gas
cylinder holding areas applies always, only stores staff and those who have been inducted have
access to these areas. Access will only be given to gas cylinder holding area once an induction has
been completed as this is a shared zone. Access will only be given to liquid nitrogen holding area by
Store Manager or Cold Storage Systems Manager. There will be no access given to stores chemical
holding area unless in certain circumstances where the Store Manager sees necessary.
TrafficControl
AccessRoutesAccess routes for forklift and pedestrians have been clearly marked and communicated to all
regularly accessing the area. There is to be no pedestrian access through the loading bays,
pedestrians must stick to the routes marked on the map and marked pathways within the loading
dock. Store have barricades for those crossing from Samuels into the loading dock area.
D26 LG Hoarding and UNSW Shared Access Routes – Attachment 2
ForkliftUsageForklift is operated daily within the loading dock and main store areas (holding and main store
warehouse). Forklift route is shared with pedestrians, pathways have been marked however high
traffic is expected during D26 demolition from Monday 13th November 2017 until advised by MPX.
D26 LG Hoarding and UNSW Shared Access Routes – Attachment 2
GeneralWasteRemovalThe removal of general waste occurs before midday each day and will impact on the pathway to the
general waste store. It is advised that all general waste operations happen after this time to
minimise congestion and any possible hazard. There are clearly marked pathways within the loading
dock for general waste access. Forklift is also operated along this route, pathways have been marked
however high traffic is expected during D26 demolition from Monday 13th November 2017 until
advised by MPX.
D26 LG Hoarding and UNSW Shared Access Routes – Attachment 2
LiquidNitrogenFillsandDryIceLiquid Nitrogen is filled by Air Liquide trucks as required. The tank is parked as close as possible to
the fill point/cage still allowing traffic flow to the loading dock. The average delivery time is 45
minutes. Anyone requiring use of the loading dock during this time will need to be aware of the
operation and plan accordingly.
Access for suppliers will be directly in front of LG071within the yellow line marking (no parking area).
This has been marked as a reserved spot for these deliveries.
LoadingDockTrafficManagementPlan
6
RemovalofChemicalWasteThe removal of chemical waste is scheduled weekly (Thursday), access is required mostly during the
morning and most likely at points during the day depending. The waste truck has been allocated to
loading bay 8 & 6, travel path is front of the loading docks holding area into the chemical waste
room. Part of this path is shared access, pedestrians using this path must be aware of the operation
and plan accordingly to avoid any possible hazard.
DeliveryofDangerousGoodsGas cylinder deliveries can occur between the times of 6am to 4pm. The truck will be parked within
the loading dock in a space appropriate still allowing access for pedestrians and traffic flow. The
average delivery time is approximately 30 minutes. Part of the travel path is shared access with
pedestrians, pedestrians using this path must be aware of the operation and plan accordingly to
avoid any possible hazard.
BiologicalWasteRemovalThe removal of biological waste is scheduled between 5pm and 7am falling outside regular operating
hours. Anyone requiring the use of the loading dock during this time will need to be aware of the
operation and plan accordingly.
Cardboard/WastePaperremovalRemoval of cardboard/waste paper is twice a week. Driver will use loading bay 8. Anyone requiring
the use of the loading dock during this time will need to be aware of the operation and plan
accordingly.
SkipBinThere is a designated area for the skip bin within the loading dock. Access will be Monday to Friday
during usual business hours and closed weekends. Removal is as required. Anyone requiring the use
of the loading dock will need to be aware of the operation and plan accordingly when necessary.
MultiplexWork carried out by Multiplex should be scheduled outside usual Store operating hours. Work
scheduled during Store operating hours is to be coordinated with UNSW Store, additional to that
already mentioned on page 4 of this document.
HealthandSafetyForklift,Pedestrians,CouriersThe following traffic control measures have been put into place:
Signage
Barriers
Mirrors
LoadingDockTrafficManagementPlan
7
People Management (Store Staff)
Designated forklift parking
Clearly marked pathways for pedestrians and forklift
High traffic areas have been separated where possible from forklift, cars and trucks
Safe Work Procedures
Loading Dock Traffic Management Plan
NoiseRequired work is regularly carried out within the loading dock between the hours 6am and 5pm,
noise is mostly generated by trucks, cars and forklift. Noise levels produced within the area are low
risk to staff and are isolated by distance to the wider UNSW community and residences within the
area.
UNSW must consult, coordinate and communicate with the Upper Campus Store and other relevant
parties on any activities whereby noise within the loading dock may be hazardous so that all risks are
eliminated or minimised where possible.
MultiplexD26 demolition works commencing Monday 13th will generate noise. Noise levels will be monitored
throughout the works. These works could last up to 4 weeks of the major noisy works (demo works).
Multiplex are to coordinate and communicate with the Upper Campus Store and UNSW on any
additional work to that already mentioned on page 4 of this document, and are responsible for
ensuring any noise is compliant with NSW WHS Act.
DangerousGoodsGoods delivered directly to the Upper Campus Store are loaded/unloaded by Stores staff only, all
staff are trained to handle dangerous goods and are compliant as per safe work procedures.
Any dangerous goods to be unloaded directly by the end user are the responsibility of the end user,
the paths marked out for pedestrians must be used.
Gas cylinder companies delivering directly to the shared cylinder store and liquid nitrogen store have
been inducted into the area and must use loading zones and pathways as directed. It is the
responsibility of the company to ensure they are compliant as per their own safe work procedures.
EquipmentandMachineryEquipment can be loaded/unloaded with forklift or gantry crane, only to be operated by the Upper
Campus Store staff. Stores staff are trained on forklift and gantry crane and compliant as per safe
work procedures. Any equipment or machinery unloaded by courier or supplier is not the
responsibility of UNSW, it is the responsibility of the company to ensure they are compliant as per
their own safe work procedures.
LoadingDockTrafficManagementPlan
8
ExternalCompaniesIt is the responsibility of all external companies delivering goods to the Store or the precinct to
ensure they are carrying out the correct handling and safety procedures as per their own safe work
procedures as well as working in line with the Upper Campus Store Loading Dock Traffic
Management procedures. This includes:
Delivery of liquid nitrogen
Delivery of gas cylinders
Removal of general, biological and chemical waste
All couriers
Removal of skip bins
Multiplex activities
Communication
LoadingDockActivitiesAny changes with the following procedures should be communicated to the Upper Campus Store to
ensure best management of the loading dock and the procedures within this document are kept up
to date.
Liquid nitrogen delivery
Delivery of gas cylinders
Removal of general, biological and chemical waste
General usage of dock
Removal of skip bins
Special deliveries – animals, equipment etc.
Multiplex works
StoreActivitiesThe Upper Campus Store will communicate all Store and loading dock activities to the precinct,
couriers and suppliers where required and relay all relevant information from within the precinct
where general operations may be impacted.
MultiplexMultiplex and The Upper Campus Store will communicate on all activities when required where
operations may be impacted, this also includes work after hours.
abov
e
abov
e
abov
eab
ove
FHR
FH
FHR
FH
BLBL
LG1 LG3
LGQ9LG2
LG4 LGQ2
LGQ10
LIFT11
LG25
LG24
LGQ4
LGQ3
LGQ1
LG20
LG26
LG21
LG23
LG22D
LG22A LG22B
LG22CLGQ7
LGQ8
HYD
ELE
COM
HYD
LG05
LG06 LG07
LG09 LG11B LG10D
LG11LG11A
LG10LG10C
LG10B
LG10A
LG08
LGQ5
LGQ3
LG02
LGQ4
LG30
LIFT5LIFT6
LG03LG04
LG04
A
LG05
A
LG05
BLG06
LG05
LG09
LG10
LGQ5
LGQ6
LG11LG11A
LG11BLG29
LIFTPIT
LGQ7
LG12LG13
LGQ9
LGQ8
LG16
LG07
LG09B
LG08 LG09A
LGQ4A
FHR
LG04B
LG03A
LG01LGQ5A
LGQ7A
LGQ23A
12m2
26m2
17m2
234m2
6m26m2
9m225m2
15m2
9m2
9m220m2
10m2
25m2
45m2
172m2
55m2
14m28m2
24m227m2
11m2
51m2
46m213m2
6m2
11m2
9m2
65m2
9m2
15m2 21m2
2m2
2m2
306m24m2
3m2
eB eD eF eH eK eL eM eN eO eP eQ eR eS
e1
e2
e3
SPRINKLER/PUMPLGQ79
FIELD GEAR PREPLG030
GAS METER ROOMLGQ76
STORELG008
RADIOACTIVE WASTELG002
HERBARIUM PREPLG006
MAIN STORESLG016
WORKPLACELG015
RECEIPTLG018
HOLDINGLG017
MAIN SWITCHROOMLGQ74
COMPACTUS STORELG021
SHELL SPACELG009
CHILLERSLGQ78
CHEMICAL STORESLG020
LOADING AREALG033
CIRCULATIONLGQ16
STAIR 01LGQ01
MALE WCLGQ52
LIFTLGLS01
COMMLG060
COLD 4cLG016A
PALEO PREP-SAMPLELG001
FIELD GEAR STORELG029
LEAD INLG061
STAIR 02LGQ03
DIESEL TANK ROOMLGQ75
HYDRAULIC PUMPLGQ77
PALAEO PREP- ACID BATHSLG010
HERB FRZLG004
HERBARIUM COMPACTUSLG003
STAIRLGQ06
4c STORELG019
ROCK CRUSHLG014
PETRO PREPLG012
ROCK CUTLG011
BIO. WASTELG024
GEN. WASTELG025
VEHICLE BAYSLG032
COMPUTATIONLG007
STORELG005
BULK GASESLGQ71
GAS CYLLG023
CHEM WASTELG026
ROCK POLLG013
STORELG036
RISERMLGQ01
FHRFLGQ01
USATLGQ51
ELECELGQ01
??
CLEANERSLG034
DIVE GEARLG031
FEMALE WCLGQ53
LIFTLGLS02 LIFT
LGLS02LIFT
LGLS02
CRYO STORELG028
TEALG037
CIRCULATIONLGQ13
CIRCULATIONLGQ18
UPS/ BATTERY RACK ROOMLGQ27
CIRCULATIONLGQ20
CIRCULATIONLGQ19
CIRCULATIONLGQ24
CIRC
ULAT
ION
LGQ2
1
CIRCULATIONLGQ23
CIRCULATIONLGQ22
FHRFLGQ07
FHRFLGQ06
FHRFLGQ04
CIRC
ULAT
ION
LGQ1
1CI
RCUL
ATIO
NLG
Q12
CIRC
ULAT
ION
LGQ1
5
CIRC
ULAT
ION
LGQ2
6
FHRFLGQ05
FHRFLGQ03
BOOSTER VALVE SETHLGQ01
PFCLGQ73
GLASS WASHLG022
8128
8128
8128 8128 8128 8128 8128 8128 8128 8128 8128 8128 8128 8128
111000
211000
111001
211001
eA
DOCUMENT REVIEWBrookfield Multiplex Constructions Pty Ltd
A - Acceptable for ConstructionB - Acceptable for Construction subject to comments. Correct and ResubmitC - Unacceptable for Construction. Correct and Resubmit for ReviewD - Drawing on Hold
These documents have been reviewed for conformity with design intent. Acceptance does notmean approval of dimensions, sizes or weights nor does it relieve the Subcontractor and/or theConsultant from responsibility for errors, omissions or compliance with his obligations and/orrequirements of the Contract and/or Subconract.
Reviewed ............................................................. Date ...............................
Contractor must verify all dimensions on site before commencing workor preparing shop drawings. Do not scale drawings.
Revision
Status
Sheet number
Sheet title
Scale
Project number
Checked Approved
25mm
Sheet sizeA1
Size check
Project
Client
Notes & Legend
© Woods Bagot
# Description DateStatusRecent revision history
TM
Architect
Builder
Project Manager
Mechanical / Gases / VT
Electrical / ICT / AV
Hydraulic / Fire
Structure / Civil
Landscape
BS2-WB-AR- 4
1 : 200
10000
PRELIMINARY
120922
AP CS
UNSW Australia
BIOLOGICAL SCIENCES PROJECTSTAGE 2Botany StreetKensington CampusNSW 2052
EXISTING FLOOR PLANS - LOWERGROUND FLOOR
1 SD ISSUED FOR INFORMATION 20/07/162 DD DD ISSUE 14/12/163 DD DD ISSUE 05/01/174 PRELIMINARY E26 ROOM NUMBERS ADDED 05/10/17
abov
e
abov
e
abov
eab
ove
FHR
FH
FHR
FH
BLBL
LG1 LG3
LGQ9LG2
LG4 LGQ2
LGQ10
LIFT11
LG25
LG24
LGQ4
LGQ3
LGQ1
LG20
LG26
LG21
LG23
LG22D
LG22A LG22B
LG22CLGQ7
LGQ8
HYD
ELE
COM
HYD
LG05
LG06 LG07
LG09 LG11B LG10D
LG11LG11A
LG10LG10C
LG10B
LG10A
LG08
LGQ5
LGQ3
LG02
LGQ4
LG30
LIFT5LIFT6
LG03LG04
LG04
A
LG05
A
LG05
BLG06
LG05
LG09
LG10
LGQ5
LGQ6
LG11LG11A
LG11BLG29
LIFTPIT
LGQ7
LG12LG13
LGQ9
LGQ8
LG16
LG07
LG09B
LG08 LG09A
LGQ4A
FHR
LG04B
LG03A
LG01LGQ5A
LGQ7A
LGQ23A
12m2
26m2
17m2
234m2
6m26m2
9m225m2
15m2
9m2
9m220m2
10m2
25m2
45m2
172m2
55m2
14m28m2
24m227m2
11m2
51m2
46m213m2
6m2
11m2
9m2
65m2
9m2
15m2 21m2
2m2
2m2
306m24m2
3m2
eB eD eF eH eK eL eM eN eO eP eQ eR eS
e1
e2
e3
SPRINKLER/PUMPLGQ79
FIELD GEAR PREPLG030
GAS METER ROOMLGQ76
STORELG008
RADIOACTIVE WASTELG002
HERBARIUM PREPLG006
MAIN STORESLG016
WORKPLACELG015
RECEIPTLG018
HOLDINGLG017
MAIN SWITCHROOMLGQ74
COMPACTUS STORELG021
SHELL SPACELG009
CHILLERSLGQ78
CHEMICAL STORESLG020
LOADING AREALG033
CIRCULATIONLGQ16
STAIR 01LGQ01
MALE WCLGQ52
LIFTLGLS01
COMMLG060
COLD 4cLG016A
PALEO PREP-SAMPLELG001
FIELD GEAR STORELG029
LEAD INLG061
STAIR 02LGQ03
DIESEL TANK ROOMLGQ75
HYDRAULIC PUMPLGQ77
PALAEO PREP- ACID BATHSLG010
HERB FRZLG004
HERBARIUM COMPACTUSLG003
STAIRLGQ06
4c STORELG019
ROCK CRUSHLG014
PETRO PREPLG012
ROCK CUTLG011
BIO. WASTELG024
GEN. WASTELG025
VEHICLE BAYSLG032
COMPUTATIONLG007
STORELG005
BULK GASESLGQ71
GAS CYLLG023
CHEM WASTELG026
ROCK POLLG013
STORELG036
RISERMLGQ01
FHRFLGQ01
USATLGQ51
ELECELGQ01
??
CLEANERSLG034
DIVE GEARLG031
FEMALE WCLGQ53
LIFTLGLS02 LIFT
LGLS02LIFT
LGLS02
CRYO STORELG028
TEALG037
CIRCULATIONLGQ13
CIRCULATIONLGQ18
UPS/ BATTERY RACK ROOMLGQ27
CIRCULATIONLGQ20
CIRCULATIONLGQ19
CIRCULATIONLGQ24
CIRC
ULAT
ION
LGQ2
1
CIRCULATIONLGQ23
CIRCULATIONLGQ22
FHRFLGQ07
FHRFLGQ06
FHRFLGQ04
CIRC
ULAT
ION
LGQ1
1CI
RCUL
ATIO
NLG
Q12
CIRC
ULAT
ION
LGQ1
5
CIRC
ULAT
ION
LGQ2
6
FHRFLGQ05
FHRFLGQ03
BOOSTER VALVE SETHLGQ01
PFCLGQ73
GLASS WASHLG022
8128
8128
8128 8128 8128 8128 8128 8128 8128 8128 8128 8128 8128 8128
111000
211000
111001
211001
eA
DOCUMENT REVIEWBrookfield Multiplex Constructions Pty Ltd
A - Acceptable for ConstructionB - Acceptable for Construction subject to comments. Correct and ResubmitC - Unacceptable for Construction. Correct and Resubmit for ReviewD - Drawing on Hold
These documents have been reviewed for conformity with design intent. Acceptance does notmean approval of dimensions, sizes or weights nor does it relieve the Subcontractor and/or theConsultant from responsibility for errors, omissions or compliance with his obligations and/orrequirements of the Contract and/or Subconract.
Reviewed ............................................................. Date ...............................
Contractor must verify all dimensions on site before commencing workor preparing shop drawings. Do not scale drawings.
Revision
Status
Sheet number
Sheet title
Scale
Project number
Checked Approved
25mm
Sheet sizeA1
Size check
Project
Client
Notes & Legend
© Woods Bagot
# Description DateStatusRecent revision history
TM
Architect
Builder
Project Manager
Mechanical / Gases / VT
Electrical / ICT / AV
Hydraulic / Fire
Structure / Civil
Landscape
BS2-WB-AR- 4
1 : 200
10000
PRELIMINARY
120922
AP CS
UNSW Australia
BIOLOGICAL SCIENCES PROJECTSTAGE 2Botany StreetKensington CampusNSW 2052
EXISTING FLOOR PLANS - LOWERGROUND FLOOR
1 SD ISSUED FOR INFORMATION 20/07/162 DD DD ISSUE 14/12/163 DD DD ISSUE 05/01/174 PRELIMINARY E26 ROOM NUMBERS ADDED 05/10/17
abov
e
abov
e
abov
eab
ove
FHR
FH
FHR
FH
BLBL
LG1 LG3
LGQ9LG2
LG4 LGQ2
LGQ10
LIFT11
LG25
LG24
LGQ4
LGQ3
LGQ1
LG20
LG26
LG21
LG23
LG22D
LG22A LG22B
LG22CLGQ7
LGQ8
HYD
ELE
COM
HYD
LG05
LG06 LG07
LG09 LG11B LG10D
LG11LG11A
LG10LG10C
LG10B
LG10A
LG08
LGQ5
LGQ3
LG02
LGQ4
LG30
LIFT5LIFT6
LG03LG04
LG04
A
LG05
A
LG05
BLG06
LG05
LG09
LG10
LGQ5
LGQ6
LG11LG11A
LG11BLG29
LIFTPIT
LGQ7
LG12LG13
LGQ9
LGQ8
LG16
LG07
LG09B
LG08 LG09A
LGQ4A
FHR
LG04B
LG03A
LG01LGQ5A
LGQ7A
LGQ23A
12m2
26m2
17m2
234m2
6m26m2
9m225m2
15m2
9m2
9m220m2
10m2
25m2
45m2
172m2
55m2
14m28m2
24m227m2
11m2
51m2
46m213m2
6m2
11m2
9m2
65m2
9m2
15m2 21m2
2m2
2m2
306m24m2
3m2
eB eD eF eH eK eL eM eN eO eP eQ eR eS
e1
e2
e3
SPRINKLER/PUMPLGQ79
FIELD GEAR PREPLG030
GAS METER ROOMLGQ76
STORELG008
RADIOACTIVE WASTELG002
HERBARIUM PREPLG006
MAIN STORESLG016
WORKPLACELG015
RECEIPTLG018
HOLDINGLG017
MAIN SWITCHROOMLGQ74
COMPACTUS STORELG021
SHELL SPACELG009
CHILLERSLGQ78
CHEMICAL STORESLG020
LOADING AREALG033
CIRCULATIONLGQ16
STAIR 01LGQ01
MALE WCLGQ52
LIFTLGLS01
COMMLG060
COLD 4cLG016A
PALEO PREP-SAMPLELG001
FIELD GEAR STORELG029
LEAD INLG061
STAIR 02LGQ03
DIESEL TANK ROOMLGQ75
HYDRAULIC PUMPLGQ77
PALAEO PREP- ACID BATHSLG010
HERB FRZLG004
HERBARIUM COMPACTUSLG003
STAIRLGQ06
4c STORELG019
ROCK CRUSHLG014
PETRO PREPLG012
ROCK CUTLG011
BIO. WASTELG024
GEN. WASTELG025
VEHICLE BAYSLG032
COMPUTATIONLG007
STORELG005
BULK GASESLGQ71
GAS CYLLG023
CHEM WASTELG026
ROCK POLLG013
STORELG036
RISERMLGQ01
FHRFLGQ01
USATLGQ51
ELECELGQ01
??
CLEANERSLG034
DIVE GEARLG031
FEMALE WCLGQ53
LIFTLGLS02 LIFT
LGLS02LIFT
LGLS02
CRYO STORELG028
TEALG037
CIRCULATIONLGQ13
CIRCULATIONLGQ18
UPS/ BATTERY RACK ROOMLGQ27
CIRCULATIONLGQ20
CIRCULATIONLGQ19
CIRCULATIONLGQ24
CIRC
ULAT
ION
LGQ2
1
CIRCULATIONLGQ23
CIRCULATIONLGQ22
FHRFLGQ07
FHRFLGQ06
FHRFLGQ04
CIRC
ULAT
ION
LGQ1
1CI
RCUL
ATIO
NLG
Q12
CIRC
ULAT
ION
LGQ1
5
CIRC
ULAT
ION
LGQ2
6
FHRFLGQ05
FHRFLGQ03
BOOSTER VALVE SETHLGQ01
PFCLGQ73
GLASS WASHLG022
8128
8128
8128 8128 8128 8128 8128 8128 8128 8128 8128 8128 8128 8128
111000
211000
111001
211001
eA
DOCUMENT REVIEWBrookfield Multiplex Constructions Pty Ltd
A - Acceptable for ConstructionB - Acceptable for Construction subject to comments. Correct and ResubmitC - Unacceptable for Construction. Correct and Resubmit for ReviewD - Drawing on Hold
These documents have been reviewed for conformity with design intent. Acceptance does notmean approval of dimensions, sizes or weights nor does it relieve the Subcontractor and/or theConsultant from responsibility for errors, omissions or compliance with his obligations and/orrequirements of the Contract and/or Subconract.
Reviewed ............................................................. Date ...............................
Contractor must verify all dimensions on site before commencing workor preparing shop drawings. Do not scale drawings.
Revision
Status
Sheet number
Sheet title
Scale
Project number
Checked Approved
25mm
Sheet sizeA1
Size check
Project
Client
Notes & Legend
© Woods Bagot
# Description DateStatusRecent revision history
TM
Architect
Builder
Project Manager
Mechanical / Gases / VT
Electrical / ICT / AV
Hydraulic / Fire
Structure / Civil
Landscape
BS2-WB-AR- 4
1 : 200
10000
PRELIMINARY
120922
AP CS
UNSW Australia
BIOLOGICAL SCIENCES PROJECTSTAGE 2Botany StreetKensington CampusNSW 2052
EXISTING FLOOR PLANS - LOWERGROUND FLOOR
1 SD ISSUED FOR INFORMATION 20/07/162 DD DD ISSUE 14/12/163 DD DD ISSUE 05/01/174 PRELIMINARY E26 ROOM NUMBERS ADDED 05/10/17