1
Machine-StatusOutline: Organization
Financial aspectsRadiation SafetyCoolingSR Magnets (CESSAMag)SR VacuumSR RF
TAC-SAC-2013/11/23-E.Huttel
Erhard Huttel in Behalf of the SESAME-Team
Organization
Design/MechanicsMaher ShehabThaer Abu-HaniehAkrum Al-Homoud
Ahmad AteiehOpen position
Machine-Physics (+2)Maher Attal Mohammad Ebeni (2013)Koryun Maunkyan (2013).
Cooling/VacuumFiras MahahlehOsama Nour (C)Mohammad Al-Nadjdawi (V)Adel Amro (V)Saed Budair (V)
Beamlines (+1)XABS:Messaoud HarfoucheIR: Ibraheem YousefPD: Rabia Kaneez (2013)
Computing Salman MAtalgahMustafa Zoubi
Radiation-SafetyAdli HamadMorteza Mansouri
Power-Supplies / Electric (+1)Sofian JavarIfikhar AbidOsama Khader (2013)
Yazeed Momani Farouq Al-Omari
RF/DiagnosticsDarweesh FoudehNashat (RF)Alaa Alkurdi (RF)Hussain Al-Mohammad (D)
Administration (+4)Sonia Al-FaquesMajeda Salama ( 2013)Ayman Al-Zoubi Ibrahim RadwanAbd Al Mawla GnaimatAmeyreh Basheer(2013)Khaled Al-Zoubi (2013)Rawan Ramadan (2013)
TAC-SAC-2013/11/23-E.Huttel 2
Control (+1,-1)(Ziaulhaque Qazi) left 2013Ibrahim SalehAbdallah Ismail (2013)Open Positions
Administrative SectorTechnical SectorScientific SectorGroups working for both Sectors
(more efficient for a small facility)
Financial Aspects till 2016
Income
EU-CERN: 5.00 M€Jordan: 4 x 1.25 M$Turkey: 4 x 1.25 M$Israel: 4 x 1.25 M$Iran: 4 x 1.25 M$ ?
Sum: 26 M $ ?
Injector-upgrade 0.9 M€Magnets and PS:5.0 M€Girder: 0.8 M€Vacuum: 3.0 M€RF: 3.0 M€Diagnostics: 1.5 M€SR-Cooling: 0.5 M€Cabling: 0.5 M€Commissioning: 1.5 M€Control-System 1.1 M€Safety P+A 0.8 M€Front-Ends: 0.5 M€
Sum [€] 19.0 M€Sum [$] 23.3 M$10% 25.6 M$
Machine: 25.6 M$4 Beamlines upgrade: 8.7 M$Guesthouse+ 1.3 M$
Sum 35.6 M$
TAC-SAC-2013/11/23-E.Huttel 3
Cost Planning / Schedule Plan A
Nov 2013 till Nov 2014:Committed money 12.5 M$> provided money 7.5 M$< less spend money 6.0 M$
Date Provided [M$] 1)
Contract(cost [M$])
Committed[M$]
Spend[M$] 2)
Nov 12 3.75 Jordan+IR (0.6)SR.Vac. (2.0)Rad.Saf. (0.4)AOB. (0.3) 3.2 1.6
Nov 13 7.50 RF.Cav. (2.0)Girder (1.2)Vac.Pumps (1.2)Vac.Valves (1.2)RF-Ampl. (3.2)AOB. (0.5) 12.5 6.0
Nov 14 11.25 RF LL etc (0.5)Diagnostics (2.0)Rad.Saf. (0.5)Frontends (0.7)AOB (0.5) 16.7 11.8
Nov 15 15.00 16.7
Jan 16 Start Operation
1) Contribution Israel, Jordan, Turkey 2) due to partial payment over two years spend is less than committed money
If committed money must be less provided money Schedule must be revised! Plan B.Start of operation delayed!
The contribution of Iran is needed for the built up of the beam-lines!
TAC-SAC-2013/11/23-E.Huttel 4
Cost Planning / Schedule Plan BProvided Money (blue)> committed money (red)> spend money (green)
Date Provided [M$] 1)
Contract(cost [M$])
Committed[M$]
Spend[M$] 2)
Nov 12 3.75 Jordan+IR (0.6)SR.Vac. (2.0)Rad.Saf. (0.4)AOB. (0.3) 3.2 1.6
Nov 13 7.50 RF.Cav. (2.0)Girder (1.2)AOB. (0.5) 6.9 4.3
Nov 14 11.25 Vac.Pumps (1.2)Vac.Valves (1.2)2 RF-Ampl. (3.2)AOB (0.5) 11.4 7.1
Nov 15 15.00 2 RF Ampl. (3.2)RF LL etc (0.5)Diagnostics (2.0)Rad.Saf. (0.5)Frontends (0.7) 16.7
12.7
Nov 16 Delivery 16.7
Nov 17 Start Operation
1) Contribution Israel, Jordan, Turkey 2) due to partial payment over two y ears spend is less than committed money
The contribution of Iran is needed for the built up of the beam-lines !
TAC-SAC-2013/11/23-E.Huttel 5
Commissioning delayed to 2017!
Project-Development
TAC-SAC-2013/11/23-E.Huttel 6Still in the expected range for commissioning in 2016
No-In-kind Contribution Pakistan
TAC-SAC-2013/11/23-E.Huttel 7
Visit of SESAME Director, Scientific- and Administrative Director Jan. 2013
Visit of SESAME-Technical Director and Mechanical Group-Leader March 2013
In preparation of contracts: Our mails have not been replied
Kick off meeting at HMC3
Cooling System
TAC-SAC-2013/11/23-E.Huttel 8
Air conditioningHall (600 kW), Tunnel (30 kW)
Heat-exchanger (2x 0.9 MW)Pumps
Chillers, Cooling towers (2 x 1.1 MW)
Design by SESAME : Firas
Makahleh
Done by local provider: Alpha-Amman
Volume: 2.2 M $,
Built up: 2011-2013
Financed by: EuropAid
New Commissioning Permit for Microtron-Operation
SESAME dose calculation confirmed by JNRC:Expected dose less 1mSv/yLimit for general public access
Microtron
Dos
e [m
Sv]
TAC-SAC-2013/11/23-E.Huttel 9
Radiation Safety
Two bids (Thermo/Eberlein, Berthold (178 k$, 275 k$)On-line-Radiation Monitors (Thermo/Eberlein) delivered: Aug. 13
Radiation Monitor installed on top of the SESAME Booster
X-ray and Neutron Personal (Luxel) Dosimeter ordered from Landauer
Luxel Dosimeter
TAC-SAC-2013/11/23-E.Huttel 10
11
Personal Safety System
TAC-SAC-2013/11/23-E.Huttel
Personal-Safety System Invitation to bid: May 133 Bids received: Jul. 13 (SAM, PROCON, SELMER)
(73 k$, 163 k$, 743 k$)
Booster InstallationDone:Vacuum Installed and pumpedMagnets alignedRF InstalledSeptum, Kicker PS built upCabling doneControl system built upRadiation-Monitors installed
Commissioning Jan.2014
QuadrupoleCorrectorCavityCurrent-MonitorDipole
TAC-SAC-2013/11/23-E.Huttel 12
Control-SystemDevelopment of Virtual Servers (EPICS) and Graphical User-Interface (CSS) for: Booster -Vacuum, -RF, -Power-Supplies and -Timing
Booster fully in Control
TAC-SAC-2013/11/23-E.Huttel 13
CESSAMag-Project
TAC-SAC-2013/11/23-E.Huttel 14
Invitation to Bid (Jun. 2013)Opening of Bids (Aug.2013)Dipole: (TESLA, DANFYSIK)Quadrupole: (ELYTT, SIGMA-PHI, SCANDITRONIX, DANFYSIK,TESLA)
Cost allow Power-Supplies to be fully paid within CESSMag Project
CERNJean-Pierre KoutchoukDavide TommasiniAttilio MilaneseLouis WalckiersTheodor Tortschanoff
SESAMEErhard HuttelMaher AttalMaher ShehabFiras MakahlehMohammad Ebeni
ALBAMontse Pont
CERN SESAME agreement: 15.05.2012EU CERN agreement FP7: 11.04.2013
Paul ProudlockJean-Paul BurnetMiguel Cerqueira Bastos
Storagering Magnets
Dipole:B: 1.46 TB’:2.79 T/mL: 2.25 m
Quadrupole:B’: 17 (-9) T/mL: 0.28 (0.1) m
Sextupole:M: 90 (-140) T/m2
l.: 0.1 m First punched laminations
TAC-SAC-2013/11/23-E.Huttel 15
Measuring Bench
TAC-SAC-2013/11/23-E.Huttel 16
Measurement Radius 29 mm
Measurement Length 1200 mm
Max allowed weight 1100 Kg
Power supply 50 V, 300 A
Compensation scheme Dipole, Quadrupole
Absolute field measurement error ± 5 10-4 peak-peak
Relative harmonics resolution ± 0.1 10-4
Main field angle measurement error ± 0.5 mRad
Magnetic axis measurement ± 50 µm peak-peak
SR-Girder
Design ready (ALBA Design)6 feeds3 struts used for transverse and longitudinal adjustment3 jacks used for vertical adjustment and clampingMagnet Position defined by pins
TAC-SAC-2013/11/23-E.Huttel 17
Tender Request next week
SR-Vacuum-Chamber-Design
Electron beam chamber70 x 28 mm2
Syn.Rad. is passing into ante chamber
Syn.Rad. is absorbed on
lumped absorber,Pumps beneath
Installed Ion-Pumps:16 x ( 2x 300 l/s + 7 150 l/s)
Pressure < 2 10-9 mbar for lifetime > 10 h
TAC-SAC-2013/11/23-E.Huttel 18
Vacuum-System-Purchasing
TAC-SAC-2013/11/23-E.Huttel 19
Invitation to Bid: Jun. 133 bids received : Aug. 13 (FMB, CECOM, RCJ)
(2.0 M$, 2.2 M$, 3.9 M$)
Next:Purchasing Pumps (Varian, Gamma-Vac)Purchasing Valves, Bellows (VAT)
SR-RF Cavities
TAC-SAC-2013/11/23-E.Huttel 20
Two old ELETTRA cavities (reduced performance) available.
Disconnected and leaking cooling pipes.
Purchasing of 4 new cavities ( ELETTRA, BESSY, KEKII/PF)Invitation to bid: Sep. 2013Opening of Bids: Nov. 2013 (2.2 M$, 2.1 M$, 4.3 M$)
Two half performing cavities: 2.0 GeV (250 kV) 200 mAThree cavities: 2.5 GeV (615 kV) 100 mAFour cavities: 2.5 GeV (615 kV) 300 mA
21
Cavities
TAC-SAC-2013/11/23-E.Huttel
Invitation to Bid: Sep. 133 bids received : Nov. 13 (RI, ELETTRA, TOSHIBA)
Specification:Number: 4Frequency: 499.65 MHzShunt Impedance: > 3.3 MΩMax Cavity Voltage: > 650 kVMax Window Power: > 120 kW
HOM-Damping Properties: Wave guide (BESSY) ++Beam-Pipe (KEK/PF) +Temperature (ELETTRA) 0
RF Amplifier
TAC-SAC-2013/11/23-E.Huttel 22
Intended : Use 500 MHz solid state amplifier (0.6 kW Module) developed at SOLEIL
Needed: 4 x 80 kW from 4 x 10 x 16 x 0.5 kW
Status: 16 Modules combined and tested by SOLEIL.40 kW tower will be built up by SOLEIL for THOMX (Beginning 2014).
Export of Technology from SOLEIL to SESAME on halt (May 2013)Export approval received (Aug.2013)
Intended: Built up of one 80 kW tower (Demonstrator) by SOLEIL, sold to SESAME.Participation of SESAME.Licensing of 500 MHz technology from SOLEIL to SIGAM-PHI-Electronics?Purchasing of further 3 towers from SIGMA-PHI-Electronics? Cost?
500 MHz 80 kW Solid-State-Amplifier
X 16 X 10 4 x
Syn.Rad. Losses: (200 mA 600 kV) / 4 = 30 kWCavity Losses: (500 kV)2 / (6 MΩ)= 40 kW4 Cavities: 280 kW
0.65 kW 10 kW 80 kW
TAC-SAC-2013/11/23-E.Huttel 23
Summery
TAC-SAC-2013/11/23-E.Huttel 24
Done in 2013:Cooling plant/Air-conditioning: Installation done.Microtron: Commissioned.Booster: Installation done.Radiation Monitoring System: Installation done.SR Magnet System (CESSAMag): Design, Tendering, Contracting done.SR Vacuum Chamber: Design, Tendering, (Contracting) done. Girder System: Design, (Tendering) done.SR-RF-Cavities: Tendering done.
Thank you for your attention!
Foreseen in 2014:Booster: CommissioningSR Magnets: Testing of Prototype, Start ProductionSR Vacuum Chamber: Testing of Prototype, Start ProductionSR Girder: Testing of Prototype, Start ProductionRF amplifier: Tendering.SR Pumps: Tendering.SR valves, bellows: Tendering.
Power and Cooling
TAC-SAC-2013/11/23-E.Huttel 25
Electric Power Cooling CapacityCooling Tower Compressor 400 kW 2x 1 115 kWChilling water tankPumps 100 kWHeat Exchanger 2 x 870 kWPumps 120 kWAir-Conditioning 300 kW 600 kWDe Ionized Water Circuits:
SR Magnet 500 kWRF Amplifier 250 kWRF-Cavities 200 mA 125 kWSR Absorber (200 mA) 125 kWBooster (PS) 100 kW
Sum 2 000 kW