Make Time for Good Designx
1Predesign - 1-2 Weeks
xDefi ne roles and resoponsibilities of
designer and Client
xProject goals objectives and
requiremants
xFeasibility studies
xProposed budget and schedule
2Conceptial Design 2-3 Weeks
xNeed Analysis
xFurniture inventory
xConceptural planning and fi nishes
xPreliminary Equipment and Lighting
selection
3Design Development-1-2 Weeks
xDetailed interiors planning
xDevelop conceptual design
xCoordinate with Engineering
Consultants
xFurniture specifi cation and
procurement
4Contract Documents-2-3 Week2
xConstuction Drawings and
Specifi cations
xTender Preparation and Issue
xBuilding permit submission- Up to 4
weeks
xTender review/ summary preparation
5Contract Management/Construction-
6-8 Weeks
xConstruction admin
xConstruction
xSite inspections/Defi cency walk-thru
xBudget summary preparation
For a 5000sqft space it takes at least 6 months to be able to move into your new space.