Page 1: Make Time For Good Design

Make Time for Good Designx

1Predesign - 1-2 Weeks

xDefi ne roles and resoponsibilities of

designer and Client

xProject goals objectives and

requiremants

xFeasibility studies

xProposed budget and schedule

2Conceptial Design 2-3 Weeks

xNeed Analysis

xFurniture inventory

xConceptural planning and fi nishes

xPreliminary Equipment and Lighting

selection

3Design Development-1-2 Weeks

xDetailed interiors planning

xDevelop conceptual design

xCoordinate with Engineering

Consultants

xFurniture specifi cation and

procurement

4Contract Documents-2-3 Week2

xConstuction Drawings and

Specifi cations

xTender Preparation and Issue

xBuilding permit submission- Up to 4

weeks

xTender review/ summary preparation

5Contract Management/Construction-

6-8 Weeks

xConstruction admin

xConstruction

xSite inspections/Defi cency walk-thru

xBudget summary preparation

For a 5000sqft space it takes at least 6 months to be able to move into your new space.