Measure H
Bond Projects Update_______________________________
Presented to the ACSS Division
8/28/2020
![Page 2: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/2.jpg)
Veterans Support and Success Center
ProjectCompletedApril 2020
![Page 3: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/3.jpg)
Veterans Support and Success Center
Lobby Entry andWater Wall Feature
![Page 4: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/4.jpg)
Regional Public Safety Training Center – Phase Two
Classroom Building
Project Substantially
Complete
![Page 5: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/5.jpg)
Regional Public Safety Training Center – Phase Two
FireAcademyClassroom
![Page 6: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/6.jpg)
Regional Public Safety Training Center – Phase Two
Agency Building
![Page 7: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/7.jpg)
Regional Public Safety Training Center – Phase Two
Agency BuildingClassroom &Locker Room
![Page 8: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/8.jpg)
CTE Building
Project Substantially
Complete
![Page 9: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/9.jpg)
CTE Building Interior
Skyfold WallWith
MarkerboardPanels
Classroom Interior
![Page 10: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/10.jpg)
CTE Building Shop (Lab Area)
Advanced ManufacturingLab Equipment
![Page 11: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/11.jpg)
CTE Quad Covered Storage
![Page 12: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/12.jpg)
CIS Building
Project Start: 1/2020
Est. Completion:7/2021
![Page 13: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/13.jpg)
CIS Building (continued)
![Page 14: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/14.jpg)
Farm Building 4500 Shade Structure
Project Start: 6/2020
Est. Completion:9/2020
![Page 15: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/15.jpg)
SC Main Campus Fiber Project
Project Start: 7/2020
Est. Completion:9/2020
![Page 16: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/16.jpg)
SC Main Campus Fiber Project (continued)
![Page 17: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/17.jpg)
Tehama Campus Student Services Building
Project Start: 9/2019
Est. Completion:10/2020
![Page 18: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/18.jpg)
Tehama Campus Student Services Building (continued)
![Page 19: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/19.jpg)
Downtown Redding Office Building Purchase
EstimatedBuilding
Completion:12/2022
Office Building
Parking Garage
Residential
FLOORS 2, 3 & 4
• Community Ed• FKCE• CalWORKs• EWD• NST
![Page 20: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/20.jpg)
Wildland Fire Tree Trimming and Brush Removal Project
FUND 41 – CAPITAL OUTLAY PROJECT
ProjectSubstantially
CompleteNorth Entrance
![Page 21: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/21.jpg)
Wildland Fire Tree Trimming and Brush Removal Project
FUND 41 – CAPITAL OUTLAY PROJECT
100 Building
View from Old Oregon Trail
![Page 22: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/22.jpg)
Other Projects
179,000
TrinityCampus
Shasta CollegeMain Campus
61 miles51 miles
• Solar Project – East Parking Lot (waiting for PG&E)
• HSUC Security Office (located in entry rotunda)
• Network Switch Replacement (replacement of core switch and networkswitches in buildings on the main campus)
• Dorms Upgrade Project (WiFi, security systems, interior refresh)
• Main Campus Old Oregon Trail Security Fencing and Gates
• Main Campus Signage (Wayfinding) Project
• Landscaping Master Plan Development
![Page 23: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/23.jpg)
Projects submitted for Potential State Funding
179,000
TrinityCampus
Shasta CollegeMain Campus
61 miles51 miles
Pre-Design Phase - FPPs and IPPs (State Funding)
• 200 Building (Library) Renovation: The 200 Building Final Project Proposal (FPP) is in process, and is subject to the following timeline:
June 2020 (postponed to September 2020): On the list for approval by the Board of Governors. Subject to their approval, it will then be forwarded to the Legislative Analyst’s Office.
November/December 2020: Legislative Analyst’s Office reviews FPP and notifies District of results. Subject to their approval, it will then be included in the Governor’s January 2021 initial budget, and should make it through to the final budget.
July 1, 2021: Funding becomes available (PROP 51).
• 800 Building Renovation: The FPP for this project was approved by the Governing Board on June 10, 2020 and has been submitted to the Chancellor’s Office.
![Page 24: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/24.jpg)
Completed Projects
179,000
TrinityCampus
Shasta CollegeMain Campus
61 miles
• 200 Building Exterior Infrastructure/ADA Walkway/Patio Project
• 2400 Building Electrical Upgrade
• Athletic Fieldhouse with Restrooms
• Campus Safety Relocation – Interior Remodel
• Campus Safety Site Work and ADA Paths of Travel
• Gymnasium Air Conditioning
• HSUC Folding Wall Replacement
• Interior/Exterior Lighting Project – Prop 39 & Bond
• Northeast Campus Infrastructure
• Regional Public Safety Training Center – Phase One
• SC Main Campus Keying & Access Control
• SC Safety & Security Standards
![Page 25: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/25.jpg)
Completed Projects (continued)
179,000
Shasta CollegeMain Campus
61 miles
• Shasta College Storage Building
• Summer 2019 Infrastructure Project
• Veterans Support & Success Center Building
![Page 26: Measure H Bond Projects Update](https://reader034.vdocument.in/reader034/viewer/2022052700/628ea23ac6bc514c636580e3/html5/thumbnails/26.jpg)
26