9/7/2014 Method Statement For Installation Of Emergency Lighting System
http://www.methodstatementhq.com/method-statement-installation-emergency-lighting-system.html 1/4
H o m e Disclaimer Project HSE Plan Construction Method Statements
Method Statement Template Inspection Checklists Request A Method Statement
Project Execution Plan Customer Support Download Method Statements
Led Lights Manufactureralibaba.com
Top Deals at Factory Price. Contact Directly & Get Live Quotes!
Method Statement Free Download
RSS
You are here: Home » Method Statements » Const ruct ion Method Statements » Elect rical Method Statements »
Method Statements » Method Statement For Installat ion Of Emergency Light ing System
Method Statement For Installation Of Emergency Lighting System
Tweet
The below method statement describes some
standard operating steps to install the emergency
lighting system for any kind of project the method
statement can be modified as per different project
requirements. We have given this as a general guide
and manufacturer instruction and site specific
specification should be followed while doing the
installation of central battery emergency lighting.
The Tools generally required for installation of
emergency lighting.
1. Drill machine
2. Portable electric drill
3. Forklift
4. Step Ladder
5. Scaffolding Platform
6. Digital Multifunction tester
7. Spirit Level, Water tube & Plumb
8. Hammer
9. Hacksaw
10. Marker and Masking tape
DOWNLOAD COMPLETE PACKAGE FOR CENTRAL BATTERY SYSTEM INSTALLATION
May 20, 2013 | webmaster
contact
Crushing Plant China
Manufacturer of MiningEquipment China!
SPECIAL RECENT POSTS
Installation of Marble and Granite
Tiles on floor, stairs, walls and
counters
April 4th, 2014
This m ethod statem ent covers the
detailed procedure to be followed for
Supply & Installation of [...]
Method Of Statement For Installation
of wires and cables - Wiring
March 29th, 2014
Below is the list of equipm ent / Tools
required for installation of wires and cables,
which cab be u[...]
Method Statement For Installation &
Testing of SMATV System
March 21st, 2014
Below are the steps or m ethod statem ent
for installation & testing of SMATV System in
a project.[...]
Sanitary Ware Installation Method
Statement
March 20th, 2014
Installation of sanitary ware can be done
step wise as per m entioned procedure or
m ethod statem ent b[...]
Plastering Works Method Statement
March 20th, 2014
Below are the equipm ent involved in
Plaster works that should be arranged
before starting the plaste[...]
Method Statement for Internal Painting
Works
March 20th, 2014
Below is the procedure for doing the
painting works for internal painting. This safe
work m ethod sta[...]
Chiller installation method statement
March 17th, 2014
Below is a standard operating procedure
which can be used a a m ethod statem ent
for installation of c[...]
How To Do Installation of Suspended
False Ceilings
March 14th, 2014
0 Email Share
9/7/2014 Method Statement For Installation Of Emergency Lighting System
http://www.methodstatementhq.com/method-statement-installation-emergency-lighting-system.html 2/4
Method Statement for installation of emergency lighting
1. Exposed conduits shall be GI and parallel with or at right angles to building line, beams, or
ceiling. For all change in direction symmetrical bends or metal boxes to be used.
2. Approved emergency lighting cabling i.e. FP 200 will be used only.
3. Wherever the emergency lighting cable passes through walls, floors, floor screeds, bricks walls
etc a suitable sleeve shall be provided.
4. Before terminating the cables insulation test will be carried out.
5. Uniform color coding shall be used throughout the installation.
6. Connections to the terminals shall be tightened to avoid any loose connections, and earth
connection points should be clean in order to provide good electrical conductivity path.
7. Ensure the installation of luminaries as per approved shop drawings, Exit lights shall be installed
as per approved drawings on all escape routes and their orientation should be perfect i.e.
should be visible from all sides and exit direction to be proper.
8. Install all safety luminaries to cover the specific hazards and to locate the safety equipment
installed. Intersections with other corridors, changes level, staircases, fire alarm call points and
operation equipment and other life safety equipment will be done as shown in the approved
shop drawings.
9. All emergency lights having high frequency ballasts will have a built in or separate monitoring
facility as approved already and monitoring module to be installed and addressed before fixing
the luminaries.
10. All panels & equipment shall be connected and labelled as per approved shop drawings &
schematic diagrams.
11. Make sure that all metallic equipment, accessories & light fittings are properly earthed.
12. Circuit details to be provided in the panel board.
13. All equipment to be fully leveled, aligned and tightened properly.
14. After completion of work equipment sections and compartments should be cleaned to remove
any dust and other debris etc.
15. The following tests to be done either by approved engineer or by supplier as applicable on the
sites specific requirements i.e. polarity check, incoming power supply phase sequence check,
fixing battery fuse box, cabling of battery and panels.
DOWNLOAD COMPLETE PACKAGE FOR CENTRAL BATTERY SYSTEM INSTALLATION
Equipm ent Required For Installation of
Suspended Ceilings Leveling Instrum ents
Line dory C[...]
Transformer testing & commissioning
method statement
March 14th, 2014
Below is a standard m ethod statem ent
which can be used as learning purpose and
to prepare further pr[...]
METHOD STATEMENT FOR
INSTALLATION, TESTING AND
COMMISSIONING OF UPS
March 14th, 2014
1.0. PURPOSE: The purpose of this m ethod
statem ent defines the procedure to be
followed for Insta[...]
CATEGORIES
BMS
Cem ent & Clinker Testing
Civil Engineering
Civil Method Statem ents
Concrete Testing
Construction Method Statem ents
Drainage Pipes Installation
Duct Works
Electrical
Electrical Method Statem ents
Fire Suppression System
Health & Safety
HVAC Checklists
HVAC Maintenance
HVAC Method Statem ents
ISO 9001
Method Statem ent Tem plate
Method Statem ents
Piping Method Statem ents
Piping Works
Plum bing Method Statem ents
Pressure Testing
Project HSE Plan
Pum p Installation
Quality Assurance
Quality Managem ent
Risk
Risk Assessm ent
Risk Managem ent
Sam ple Form s & Form ats
Tem plates
Testing & Com m issioning
Water Supply Piping
Welding Risk
What Is Hazard?
What Is Risk?
Working At Height
9/7/2014 Method Statement For Installation Of Emergency Lighting System
http://www.methodstatementhq.com/method-statement-installation-emergency-lighting-system.html 3/4
« Method Statem ent For Installation Of Electric Water Heaters
Testing and Com m issioning of Fire Fighting Pum p Set »
LIKE US ON FACEBOOK
Filed under Elect rical Method Statements, Method Statements | Tags: Installat ion Of Emergency Light ing System,
Method Statement
Comments are closed.
TAGS
& Access Control System Accessories AC Duct ing
Method Statement ac duct installat ion ACMaintenance Acoust ic Lining blank performablank proforma bms system BMS TestingProcedure Building Management SystemBuilding Management System BMS control
measures Electrical Method Statement forhazard hvac HVAC Method Statements
installat ion Installation of GI Conduits &
Accessories method Method
Of Statement Method
Statement met hod
st at ement for Inst allat ion Met hodSt at ement Templat e MST MST For BMS
of pipe flushing pressure pumps risk RiskAssessment safe work method sample
check list sample checksheet Sample
Format Electrical statement swms
template test Testing & CommissioningTesting & Commissioning MethodStatement water
DOWNLOAD METHOD STATEMENTS
Download BMS Installation Method Statem ent
Download Chilled Water Pipes Installation &
Testing Method Statem ent
Download Method Statem ent For INSTALLATION
HYDRO TESTING & FLUSHING OF FIRE FIGHTING
PIPING SYSTEM INCLUDING SPRINKLERS
Download Method Statem ent For CENTRAL
BATTERY SYSTEM INSTALLATION
Download Method Statem ent For Fire Alarm
System
Download Method Statem ent For Flushing Of
Chilled Water Piping
Download Method Statem ent For Installation Of
Packaged Units
Download Method Statem ent For Installation Of
Split Units & Risk Assessm ent
Download Method Statem ent For Installation Of
Transform ers
Download Project HSE Plan With All Form s
Hom e
Privacy Policy
Disclaim er
Hom e
Privacy Policy
Disclaim er
9/7/2014 Method Statement For Installation Of Emergency Lighting System
http://www.methodstatementhq.com/method-statement-installation-emergency-lighting-system.html 4/4
Copyright © 2014 Method Statement Free Download | zBorder Theme powered by WordPress