Metro North
![Page 2: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/2.jpg)
Metro North
St Stephen’s Green to Estuary
• 16.5km total length – 11 km in tunnel (City centre to Ballymun and
Airport)– 5.5 km in retained cut, at-grade or elevated
• 14 stops – 9 underground stops from St. Stephen’s Green to
Ballymun and at Airport– 5 surface stops
• High quality service– Capacity – 8,000 ppdph initially, capable of
growing to 20,000– Frequency - 5 minute peak headway initially,
capable of going to 2 minute– Speed – Airport to city in 20 minutes; Swords to
city in under 30 minutes; Ballymun to city in 13 minutes
● Estuary● Swords● Fosterstown● Airport● Dardistown● Northwood● Ballymun● DCU● Griffith Avenue● Drumcondra● Mater● Parnell Square● O’Connell Bridge● St Stephen’s Green
![Page 3: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/3.jpg)
Westmoreland Street Works
![Page 4: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/4.jpg)
O’Connell Street – Westmoreland Street
![Page 5: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/5.jpg)
The Aim
The aim for RPA is to design and construct the works without materially impacting on the existing businesses
• Keeping Dublin Open for Business
• Ensuring that City centre remains an attractive destination for shoppers
![Page 6: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/6.jpg)
How we keep Dublin Open for Business? • By maintaining pedestrian access to all premises• By maintaining access for servicing and deliveries• By maintaining access to all existing car parks• Getting the message across to the Public
All of this is achieved through • Careful planning and execution of the works
![Page 7: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/7.jpg)
How we ensure the City centre remains an attractive destination?
• Noise and dust limits strictly controlled and monitored• High quality, well maintained attractive hoarding• Good lighting will be provided between the worksites
and the shops so that a safe environment is created• Good housekeeping, plant and equipment cleaned and
fully serviced, worksites kept tidy and dust free• By RPA and its contractor working closely with you the
business community throughout the construction period
![Page 8: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/8.jpg)
Enabling Works - Spring 2011 to Autumn 2012
![Page 9: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/9.jpg)
What are the Enabling Works?
• Heritage works• Tree Removal• Service diversions
![Page 10: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/10.jpg)
Extent of Enabling Works
![Page 11: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/11.jpg)
Enabling Works Phase 1
![Page 12: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/12.jpg)
Enabling Works Phase 2
![Page 13: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/13.jpg)
Enabling Works Phase 3
![Page 14: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/14.jpg)
Enabling Works Phase 4
![Page 15: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/15.jpg)
Enabling Works Phase 5
![Page 16: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/16.jpg)
Enabling Works Phase 6
![Page 17: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/17.jpg)
Enabling Works Phase 7
![Page 18: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/18.jpg)
Enabling Works Phase 8
![Page 19: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/19.jpg)
Enabling Works Phase 9
![Page 20: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/20.jpg)
Enabling Works Phase 10
![Page 21: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/21.jpg)
Enabling Works Phase 11
![Page 22: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/22.jpg)
Enabling Works Phase 12
![Page 23: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/23.jpg)
Enabling Works Phase 13
![Page 24: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/24.jpg)
Enabling Works Phase 14
![Page 25: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/25.jpg)
Enabling Works Phase 15
![Page 26: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/26.jpg)
Enabling Works Phase 16
![Page 27: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/27.jpg)
Enabling works in Westmoreland Street
![Page 28: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/28.jpg)
Construction of Service Tunnels
• Most surface works adjacent to buildings will happen outside business hours
• Excavations covered over during business hours• Work continues below ground during the day and is
serviced from small hoarded areas(7.5m x 3.0m)• Footpaths widened into the roads by 3 to 5m improving
pedestrian flows during the day• Works are phased• All existing traffic movements maintained
![Page 29: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/29.jpg)
Works by day Westmoreland Street East
![Page 30: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/30.jpg)
Works by Day Westmoreland Street East
![Page 31: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/31.jpg)
Works by Day Westmoreland Street West
![Page 32: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/32.jpg)
Works by Day Westmoreland Street West
![Page 33: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/33.jpg)
Worksite by nightWorks by night Westmoreland Street East
![Page 34: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/34.jpg)
Works by night Westmoreland Street West
![Page 35: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/35.jpg)
Works by night Westmoreland Street West
![Page 36: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/36.jpg)
Main Works – 2012 to 2016
![Page 37: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/37.jpg)
Main Works
Station Construction• Main works 36 months (excavation and concrete
works) 2012 to 2016• Equipping the Station 12 months• Testing and commissioning the system 12months• Main works is carried out in 6 distinct phases to ensure
pedestrian access and traffic flow is maintained• Westmoreland Street will remain open for Public
transport and deliveries
![Page 38: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/38.jpg)
Extent of the Works
![Page 39: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/39.jpg)
Work Site Phase 1
![Page 40: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/40.jpg)
Works will be split into different phases so as to minimise the impact of the works.
Main Works Phase 1 (4 months)
![Page 41: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/41.jpg)
Main Works Phase 2 (5 months)
![Page 42: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/42.jpg)
Main Works Phase 3 - 5 months
![Page 43: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/43.jpg)
Phase 4 Piling Worksite Duration approx: 4 Months
Main Works Phase 4 (4 months)
![Page 44: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/44.jpg)
Phase 5 Excavation & Concrete Worksite Duration approx 18 months
Main Works Phase 5 (18 months)
![Page 45: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/45.jpg)
Fit out of Stop Phase 6 (12 months)
![Page 46: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/46.jpg)
Traffic Management Measures
Public Transport Bridge
Banned Right Turns
Banned Left Turns
Single Lane
![Page 47: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/47.jpg)
Current Situation
13ft 4inches - 4.1m
![Page 48: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/48.jpg)
During Phase 2 – Approx 5 Months
12ft – 3.6 m
![Page 49: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/49.jpg)
Current Situation
14ft – 4.6m min width
![Page 50: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/50.jpg)
During Phase 3 – 5 months
12ft – 3.6m min width
![Page 51: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/51.jpg)
Current Situation
![Page 52: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/52.jpg)
Phase 3 – 5 months
12ft – 3.6m min width
![Page 53: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/53.jpg)
Car Park Access
• Access is maintained to all car parks.• Information on routes will be provided to
car park users via leafleting from 3 months before the route change
• Signage to each car park will be provided
• A
![Page 54: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/54.jpg)
![Page 55: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/55.jpg)
![Page 56: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/56.jpg)
![Page 57: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/57.jpg)
![Page 58: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/58.jpg)
Our commitment to you
• Access will be maintained to all premises fronting on to the works during business hours
• Westmoreland Street will remain the main pedestrian thoroughfare between the two main shopping districts
• Access will be maintained to all premises for servicing and deliveries
• Noise and dust limits will be strictly controlled and monitored
![Page 59: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/59.jpg)
Our commitment to you
A public information centre will be established• Communications HQ & media centre for press briefings • Venue for open forums with local businesses and
residents • 24/7 telephone hotline for queries and complaints • up to date public information on the works• a marketing campaign to advertise the city as being
“open for business as usual”
Community Liaison Officers will be available during the works for you to communicate with
![Page 60: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/60.jpg)
How does RPA honour its commitments to you?
RPA will • Have an ongoing role throughout the works• Review the contractor’s method of work to
ensure compliance• Ensure you have been consulted about the
works before they happen• Audit and monitor the works as they happen• Be available and answerable to you
![Page 61: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/61.jpg)
Contractors Commitments
• Comply with conditions of contract the Railway Order & EIS
• Will plan his works in line with best practice• Will be a good neighbour• Educate and brief his workforce on an
ongoing basis• Will engage with you
![Page 62: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/62.jpg)
Next StepsNovember 2010• Provide presentation to affected businesses
• O’Connell Street 17th November• St Stephen’s Green 24th November• Parnell Square 30th November
November 2010 – March 2011• Meet with individual businesses to discuss impacts
and agree appropriate measures
![Page 63: Metro North Westmoreland St Presentation held on 10th November 2010](https://reader031.vdocument.in/reader031/viewer/2022013100/54556904af79593f4a8b69ce/html5/thumbnails/63.jpg)
Thank You for Listening