Mock-up activities

19 July 2011

R. Vuillermet

Page 2: Mock-up activities

2

Mock up activities• Status

– 12-07-2011 :Reception of the pit table at CERN

– Since a week, installation of the optical fibbers on the mock up, side A done, side C on progress

– Installation and adjustment of the pit table on the rotating table during the week 29

– Installation of the wire tension system during week 29

Page 3: Mock-up activities

3

LPSC Tooling fabrication progress

Thin tables and container(delivery week31/32)

Pit table delivered to CERN

Pit table assemble with thin table Intermediate table assembly (delivery week30)

Page 4: Mock-up activities

4

Test schedule