Download - Mott MacDonald
BIM FOR ALL STAGES OF THE PROJECT LIFECYCLEKrzysztof Nowosiński –BIM Champion
VSU PROJECT
BEST DEPLOYMENT OF BIM ON A PROJECT, 2012
AWARD WINNING BIM PROJECTS
CASEMENT PARK STADIUM
2013 BIM PROJECT OF THE YEAR
2014 FIATECH CETI AUTOMATED DESIGN AWARD
2014 BIM INITIATIVE OF THE YEAR
“The real clincher was the development of a 5D BIM process with an object based naming convention as a blueprint for future projects – both delivering and learning on the job!
Judging panel comments
To champion lean solutions, including BIM and off-site construction, to minimise carbon emissions, resource use and waste on all our projects
OUR COMMITMENT TO DfMA
“
”
Design
Construction
Design for manufacture and assembly
Planning
Asset management
Planning
Planning
New design coordinated with existing asset
VICTORIA STATION UPGRADE (VSU)
Planning
Constraints referenced directly into model
VSU – PROJECT CONSTRAINTS
Planning
Stakeholder assets modelled
VSU – DESIGN DEVELOPMENT
Planning
Geological surfaces imported from Surfer
VSU – ENGINEERING ANALYSIS INTEGRATION
Planning
SUCCESS STORIES – VSU
SUCCESSFULOUTCOMES
Design
Construction
Design for manufacture and assembly
Planning
Asset management
Design
Planning
Design
SUCCESS STORIES – WATER TREATMENT, USA
20%Cut on design time
Design
SUCCESS STORIES – ADELAIDE OVAL
30%Time saving on architectural design
SUCCESS STORIES - CASEMENT PARK
52%Time saving on Tender design
CASEMENT PARK
CLIENT – GAA
£76.4MASPIRATIONAL BRIEF
CENTRAL BIM
4D PROGRAMME 6D ASSETMANAGEMENT
5D COST PLANCLASH DETECTION
BUILDING SERVICESMODEL
ENGINEERINGANALYSIS
THERMAL,BREEAM
FIRE
LIGHTING DESIGN
ENGINEERINGDESIGN
CIVIL INFRASTRUCTURE
CUT & FILLMODELS
DRAINAGE TRAFFICMODELS
WASTESTUDIES
DELIVERY &LOADINGACCESS
STRUCTURALMODEL
WINDANALYSIS
BOWLDESIGN
ROOFDESIGN
BUILDSEQUENCE
CONCEPTUALSTUDIES
DAYLIGHTSTUDIES
SIGHT LINES
VISUALISATION
ARCHITECTURALMODEL
PEOPLEFLOW
3D FLY-THROUGH
‘RIGHT TOLIGHT’
Generative model with input parameters
Revit model exported into CSC Fastrak
Exported to Robot for dynamics calculation
Models exported to Robot
Optimised for minimum steel weight avoiding value engineering
Linked via Geometry Gym and IFC link
Intelligent properties added to rooms and spaces
3D modelling of plant areas and main distribution routes
Energy modelling
Truss feature lighting
Sports lighting analysis
BIM used for elemental quantification
Clash detection between disciplines
4D construction studies
Multidisciplinary reviews
5D PROCESS IMPROVEMENTS
Benefits- Consistent approach to naming conventions- Quantification accuracy within 1%- Real time cost reports- Delivery of better value buildings for our clients5D Publishing Guide now being used on multiple projects
80%Time saving to prepare cost plan
Design
Construction
Design for manufacture and assembly
Planning
Asset management
Construction
Design
Construction Phase
Construction Phase
JET GROUT PILING
Construction Phase
JET GROUT PLANT SELECTION
Plant modelled and maneuverability checks performed
Construction Phase
NEW APPLICATIONS: GROUND TREATMENT
Auto report extraction from model listing unique reference coordinates
Construction Phase
Water Level
Drill Rods left in-situ
Level of assumed clay
Revised level of clay from recent boreholesKnown gap between jet grout
columns
REDUCING RISK USING BIM
Extracts from 3d models used in daily site review meetings
Design
Construction
Design for manufacture and assembly
Planning
Asset management
Design for manufacture and assembly
Construction
Design for manufacture and assembly
ANGLIAN WATER PRODUCT BASED DELIVERY
BIM hugely facilitates offsite manufacture
Design for manufacture and assembly
ANGLIAN WATER PRODUCT BASED DELIVERY
20% Less Carbon
90% Time saving
Design for manufacture and assembly
MinimumAsset
Standard
3D Model
Drawings
Integration Guide
Health & Safety Risk Assessment
Calculations
Specification
Procurement Guide
FrameworkAgreement
BOMCost data
Acceptance Criteria
InstallationGuide
Commissioning Data
Functional Design Spec
Software Block
Maintenance Schedule
Spares Schedule
O&Mdata
SAP ALMdata
JoECarbon
Footprint
Telemetry Standards
Asset MonitoringFrameworks (IRIS)
STANDARDPRODUCTS
Design for manufacture and assembly
HINKLEY C ONSITE CAMPUS
Design
Construction
Design for manufacture and assembly
Planning
Asset managementAsset management
Design for manufacture and assembly
Asset management
ASSET INFORMATION
Asset data GIS dataData
Users
Performance data
Delivery partners Operators Asset Managers
Survey data
Asset management
ASSET INFORMATION
Delivery partners Operators Asset Managers
Mega databaseData
Users
Asset management
INTEGRATED ASSET INFORMATION
Asset data GIS data
Middleware
Data
Users
Performance data
Delivery partners Operators Asset Managers
Survey data
Asset management
As-Built Owner Model
As-Maintained Owner Model
Changes in Maximoupdated inOwner Model
Navisworks for visualization
Links between geometry and data
Empty Maximo Database
Populated Maximo Database
Publish key Revit Data for O&M
EMERGING ASSET MANAGEMENT