![Page 1: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/1.jpg)
MWG Report to the MOPC
January 12-13, 2016
Richard Ross
Chairman Market Working Group
![Page 2: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/2.jpg)
MWG UGLY SWEATER CONTEST
2
![Page 3: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/3.jpg)
3
![Page 4: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/4.jpg)
4
![Page 5: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/5.jpg)
5
Agenda• Approved Revision Requests
– RR111 – Local Reliability Make Whole Payment Distribution Amount
• MOPC Action Item #261
– Review MMU Recommendations from 2014 Annual State of the Market Report
• Approved Revision Requests for Consent agenda
• Appendix - Marketplace Revision Request Estimated Cost Summary
![Page 6: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/6.jpg)
MARKETPLACE PROTOCOL REVISION REQUESTS (RRS)
6
![Page 7: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/7.jpg)
RR111 – Local Reliability Make Whole Payment Distribution Amount
Background:
• Local RUC MWP Distribution Amount is allocated by load to a single Settlement Area
• Certain loads are paying for other utilities not building out their local infrastructure
7
![Page 8: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/8.jpg)
RR111 – Local Reliability Make Whole Payment Distribution Amount
RR111 proposes to:
• Allocate cost of manual commitments for voltage related Local Reliability Issues to Asset Owner based on impacted loads
• All non-voltage related Local Reliability Issues will continue to use current allocation method
8
![Page 9: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/9.jpg)
RR111 – Local Reliability Make Whole Payment Distribution Amount
• Working Group Voting Results
– MWG approved 10/20/2015
Four abstentions
Six oppositions
– RTWG approved with modifications 11/19/2015
Six abstentions
One opposition
– MWG approved RTWG modifications 12/15/2015
Two abstentions
• MWG recommends MOPC approve RR111 9
![Page 10: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/10.jpg)
MOPC ACTION ITEM #261: REVIEW MMU RECOMMENDATIONS FROM 2014 ANNUAL STATE OF MARKET REPORT
10
![Page 11: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/11.jpg)
Background • During the July 2015 SPP Board of Directors (BOD) meeting, the SPP
MMU presented its Annual State of the Market (ASOM) report
– 2014 ASOM includes nine recommendations from the MMU for changes or enhancements to the Integrated Marketplace design
• Board requested the Chairs of the MOPC and MWG review the 2014 ASOM MMU recommendations and develop an action plan
• MWG finalized responses to the MMU recommendations in November 2015 for presentation to MOPC and BOD in January 2016
11
![Page 12: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/12.jpg)
1. Quick Start Logic
MMU Summary
• The MMU supports the development of new rules governing the dispatch of quick-start resources that (1) do not subject quick-starts to RUC commitment; and (2) do not provide make whole payment eligibility for RTBM dispatch.
MWG Action/Response
• RR99-Short-Term RUC and RR116-Quick Start Enhancements have been approved and will be implemented in 2016
– RR99 implements an Intra-Day RUC with more granularity than 1 hour
– RR116 delays Quick Start Resource commitment to the RTBM
12
![Page 13: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/13.jpg)
2. Ramp-Constrained Shortage Pricing
MMU Summary
• Ramp-constrained Operating Reserve shortages should be priced in a manner similar to the Operating Reserve capacity shortages.
MWG Action/Response
• Price Formation Task Force formed
– Focus on several areas of Marketplace pricing, including shortage pricing, and will be reporting research results and information back to the MWG
– FERC released a NOPR on 9/17/15 related to shortage pricing
MWG proposes to wait for the associated FERC Order before taking any action towards revisions related to pricing during ramp shortages
13
![Page 14: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/14.jpg)
3. Potential Manipulation of Make Whole Payment Provisions
MMU Summary
• Potential for make whole payment manipulation for resources committed across the midnight hour, fixed regulation bids, Out-of-Merit energy payments, and jointly-owned units should be eliminated.
14
Area of potential MWP Manipulation
MMU Concerns/Recommendations
Resources committed across the midnight hour
Evaluate solutions adopted by other RTOs to reduce exposure to market manipulation in make whole payment provisions for resources committed across the midnight hours.
Fixed Regulation Bids
Disqualify resources with fixed Regulation bids from receiving the Regulation Deployment Adjustment Charge.
Out-of-Merit energy (OOME) payments
Utilize automatic mitigation provisions for local reliability commitments for local reliability OOME events.
Jointly-Owned Units (JOUs)
Remove the ability to manipulate make whole payments under the JOU Combined Resource Option and improve market efficiency in the JOU design.
![Page 15: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/15.jpg)
3. Potential Manipulation of Make Whole Payment Provisions (cont’d)
15
Area of potential MWP Manipulation
MWG Action/Response
Resources committed across the midnight hour
SPP Staff and MMU will research further, including a look at what other RTOs/ISOs have done
Fixed Regulation Bids
SPP Staff and MMU will research further
Out-of-Merit energy (OOME) payments
MMU will research and submit a Revision Request
Jointly-Owned Units (JOUs)
On 11/17/15, the MWG approved Revision Request 127, which proposes market design changes to eliminate the ability to manipulate make whole payments under the JOU Combined Resource Option, and to improve market efficiency in the JOU design.
![Page 16: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/16.jpg)
4. Day-Ahead Must-Offer Requirement
MMU Summary
• The MMU recommends that SPP eliminate the limited day-ahead must-offer provision and revise the Physical Withholding rules to include a penalty for non-compliance. In the event that the limited must-offer provision is continued, SPP should address design weaknesses.
MWG Action/Response
– RR125-Removal of Day-Ahead Limited Must Offer was approved by the MWG on 11/17/15
MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding
– MMU submitted RR135 (Revision of Physical Withholding Rules) for review at December MWG
Members and SPP RTO raised concerns with RR135 that need to be addressed at the 1/19/16 MWG meeting
16
![Page 17: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/17.jpg)
5. TCR and ARR System Availability
MMU Summary
• TCR and ARR system availability should be reduced to minimize the over-allocation of TCRs and ARRs that Day-Ahead Market congestion revenues do not support
MWG Action/Response
• RR91-Annual Allocation Percent Change will be implemented in time for the 2016 TCR Annual Auction Process
• MWG will re-evaluate the TCR Market after seeing results of the TCR Year 2016-2017
17
![Page 18: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/18.jpg)
6. Transmission Outage Reporting and ModelingMMU Summary
• The MMU supports SPP’s current efforts to improve planned outage reporting and suggests adding flexibility to outage inclusion criteria for ARR and TCR modeling.
MWG Action/Response
• MWG approved in October a change to add transmission outages with a “Proposed” status to the list of current outage types accepted in the models for the TCR Market
18
![Page 19: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/19.jpg)
7. TCR Bidding at Electrically Equivalent Settlement LocationsMMU Summary
• A systematic block of TCR bidding at electrically equivalent settlement locations should be implemented to prevent ongoing tariff violations.
MWG Action/Response
• MWG directed SPP Staff to complete the following in 2016:
– Research ERCOT’s “dead bus logic”
– Create Impact Analysis for the systematic block/validation
• In the meantime, SPP Staff will continue its current approach, which is described as follows:
– Post a list of prohibited settlement location pairs
– Inform AOs when prohibited bids are submitted
– Manually remove prohibited bids from ARR Allocations and TCR Auctions
19
![Page 20: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/20.jpg)
8. Allocation of Over-Collected Losses
MMU Summary
• SPP should remove the Bilateral Settlement Schedule transactions from the over-collected losses distribution calculation and consider over-collected losses (OCL) distributions to exports relative to interface transaction profit margins to assess potential distortion of market incentives.
MWG Action/Response
• FERC Order ER15-763 stated disagreement with MMU and Xcel Energy proposed removal of BSSs from the OCL distribution
– It appears that the idea of removing BSSs from OCL distribution is not necessarily final upon further review of the Order
– Discussion and consideration at MWG in Q1-2016
20
![Page 21: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/21.jpg)
9. Market Power Mitigation Conduct Thresholds
MMU Summary
• The MMU supports a modest increase in offer conduct thresholds for start-up offers, regulation offers, and for energy offers for Frequently Constrained Areas.
MWG Action/Response
• MWG will await submission of RRs by MMU for consideration and possible approval
– MMU will submit a Revision Request for the FCA threshold change
– MMU will continue to do research and analysis on the threshold changes for start-up and regulation offers, and submit a Revision Request in 2016
21
![Page 22: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/22.jpg)
CONSENT AGENDA: MARKETPLACE PROTOCOL REVISION REQUESTS (RRS)
22
![Page 23: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/23.jpg)
RR32_MPRR218 – Market Registration Naming Conventions• SPP’s Registration process does not require consistent
naming convention for Market assets
• Establishing consistent naming convention will
– Ensure names for all Market assets are consistent
– Provide ease in asset identification in all SPP Reliability and Market models, and systems
• Naming conventions will only apply to market assets after June 1, 2016 forward
23
![Page 24: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/24.jpg)
RR32_MPRR218 – Market Registration Naming Conventions
• Working Group Voting Results
– MWG approved 11/17/2015
One abstention
One Opposition
– RTWG approved 12/17/2015
• MWG recommends MOPC approve RR32_MPRR218
24
![Page 25: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/25.jpg)
RR115 – Resource Retirement Timeline
• SPP does not have established requirements for MPs to provide notice of intent to deactivate, retire or mothball a Resource
• This revision request will:
– Require a 6-month notice prior to a Resource being deactivated, retired or mothballed.
– Provide sufficient time to study and mitigate potential reliability and economic impacts
25
![Page 26: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/26.jpg)
RR115 – Resource Retirement Timeline
• Working Group Voting Results
– MWG approved 10/20/2015
One abstention
– ORWG unanimously approved 11/5/2015
– RTWG unanimously approved 11/19/2015
• MWG recommends MOPC approve RR115
26
![Page 27: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/27.jpg)
RR124 – Rejection of Incomplete Market Registration Documentation
• RR124 provides consistency between the Tariff and Market Protocols
• RR124 adds language from the Tariff to the Market Protocols supporting SPP’s ability to reject incomplete Market Registration applications
• Working Group Voting Results
– MWG approved 10/20/2015
Two abstentions
– RTWG unanimously approved 11/19/2015
• MWG recommends MOPC approve RR124
27
![Page 28: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/28.jpg)
RR127 – JOU Combined Option – Aggregate Energy Offer Curve
• Background:
– Current design of Combined Resource Option for JOUs, an Asset Owner could potentially game Energy Offer Curve of MWP
– Potential gaming opportunity is achieved by putting in a larger than normal Energy Offer Curve and getting dispatched to minimum
– Since entire JOU plant is committed or none at all, Asset Owner with higher than normal Energy Offer Curve is made whole to that curve
28
![Page 29: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/29.jpg)
RR127 – JOU Combined Option – Aggregate Energy Offer Curve
• RR127 eliminates potential gaming opportunity:
– All shares of Combined JOU Option will start at zero for first price point
– SPP will aggregate all price points into one new Energy Offer curve
– Commitment of JOU remains all or none at all
– Shares will only be dispatched off of zero if those share(s) are economical
– Each JOU share is eligible for recovery of Start-Up Offer and No-Load Offer costs when committed
29
![Page 30: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/30.jpg)
RR127 – JOU Combined Option – Aggregate Energy Offer Curve
• Impact Analysis
– Estimated cost $148k, 6 months to complete
• Benefit realized
– Eliminates potential gaming opportunity
30
![Page 31: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/31.jpg)
RR127 – JOU Combined Option – Aggregate Energy Offer Curve• Working Group Voting Results
– MWG approved 11/17/2015
Seven abstentions
– ORWG approved 12/3/2015
One abstention
– RTWG approved 12/17/2015
Three abstentions
• MWG recommends MOPC approve RR127
31
![Page 32: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/32.jpg)
RR128 – Clarification to the Start-Up Eligibility Rules
• Rules for Start-Up eligibility for Day-Ahead and RUC MWP has circular references and could be confusing when read
• RR128 will clarify language for rules on Start-Up eligibility for Day-Ahead and RUC MWP
• Circular reference is removed and format of the language is changed to allow a better read
32
![Page 33: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/33.jpg)
RR128 – Clarification to the Start-Up Eligibility Rules• Working Group Voting Results
– MWG unanimously approved 11/17/2015
– RTWG approved with modifications 12/17/2015
One abstention
• MWG recommends MOPC approve RR128 pending MWG approval of RTWG’s minor modifications
33
![Page 34: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/34.jpg)
RR129 – Settlements Clean-Up
• RR129 was drafted to include various Settlement clean up items that were found in the Protocols:
– Deleting attributes
– Adding a hashtag in front of billing determinates
– Cleaning up various definitions in the variable table
– Adding 5min to Real-Time Flags
– Adding language to the Protocols to match ER16-130 Tariff Clean-Up filing
34
![Page 35: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/35.jpg)
RR129 – Settlements Clean-Up
• Working Group Voting Results
– MWG unanimously approved 11/17/2015
– RTWG unanimously approved 12/17/2015
• MWG recommends MOPC approve RR129
35
![Page 36: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/36.jpg)
RR130 – Commitment Notification Enhancement
• Timestamp of receipt log is maintained by SPP in order to provide assurance that a MP received all SPP Resource commitment start-up and shut-down notifications
• There is a gap in current process where a MP’s system provides a timestamp of receipt, however the operator does not receive commitment instruction
• RR130 requires a manual acknowledgement to confirm the notifications were received
36
![Page 37: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/37.jpg)
RR130 – Commitment Notification Enhancement
• Working Group Voting Results
– MWG approved 11/17/2015
One abstention
One opposition
– ORWG approved with modifications 12/3/2015
Three abstentions
– RTWG unanimously approved 12/17/2015
– RCWG approved 12/21/2015
One abstention
• MWG recommends MOPC approve RR130 pending MWG’s approval of ORWG’s modifications
37
![Page 38: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/38.jpg)
RR138 – Revisions to Attachment AF, Addendum 1 Frequently Constrained Areas
• SPP Market Monitor has completed annual Frequently Constrained Area (FCA) study as required by Attachment AF, Section 3.1.1 to the Tariff
• Changes to Attachment AF, Addendum 1 reflect the recommended updates to the tariff.
38
![Page 39: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/39.jpg)
RR138 – Revisions to Attachment AF, Addendum 1 Frequently Constrained Areas
• Working Group Voting Results
– MWG approved 12/15/2015
One abstention
– RTWG unanimously approved 12/17/2015
• MWG recommends MOPC approve RR138 pending
39
![Page 40: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/40.jpg)
APPENDIX - MARKETPLACE REVISION REQUEST ESTIMATED COST SUMMARY
40
![Page 41: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/41.jpg)
Marketplace Revision Request Estimated Cost Summary
41
Approved and Pending requests with system changes addressing enhancements/defects
RRs Estimated Cost MWG Approval Date Estimated Implementation
RR1_101 9,200,000.00$ 9/17/2013 Qtr 1, 2017
RR6_MPRR151 29,341.00$ 7/22/2014 Qtr 1, 2016
RR16_MPRR190 4,000.00$ 8/19/2014 Qtr 1, 2016
RR18_MPRR196 51,131.00$ 10/21/2014 Qtr 1, 2016
RR25_MPRR211 4,400.00$ 2/10/2015 Qtr 1, 2016
RR46_MPRR233 33,044.00$ 2/10/2015 Qtr 4, 2015
RR77 21,369.00$ 4/21/2015 Qtr 1, 2016
RR82 52,000.00$ 8/18/2015 Qtr 1, 2017
RR91 113,810.00$ 9/15/2015 Qtr 1, 2016
RR99 334,542.00$ 6/16/2015 Qtr 2, 2016
RR100 1,510,590.00$ 6/16/2015 Qtr 3, 2016
RR106 9,000.00$ 7/21/2015 Qtr 1, 2017
RR116 200,000.00$ 9/15/2015 TBD
RR127 148,050.00$ 11/17/2015 TBD
11,711,277.00$ Total
![Page 42: MWG Report to the MOPC - RTO Insider · MWG postponed moving RR125 forward to the MOPC on 12/15/15 until the group had further discussion on Physical Withholding – MMU submitted](https://reader033.vdocument.in/reader033/viewer/2022050214/5f600b1375e9035c015172e8/html5/thumbnails/42.jpg)