Page 1: Narrow Pavement Widening

Narrow widening projects Kory Keller

Allen Keller Company

Page 2: Narrow Pavement Widening

Intro

• Ranch Road, and Farm to Market experience.

• Parameters• Constructability• Efficiency• Construction Safety

Page 3: Narrow Pavement Widening

Topics

• Safety Slopes

• Flex Base vs. HMAC

• Aggregate Prime

• Widening vs. Rehabilitation

Page 4: Narrow Pavement Widening

Safety slopes – the enemy

• Work that is not gainful to the progress of the project.

• Quality Control issues

• Permeates Runoff

Page 5: Narrow Pavement Widening

Slopes (cont)

• While safety slopes are an obvious and necessary hazard abatement, the elimination of the hazard is even better.

Page 6: Narrow Pavement Widening

How can we avoid the safety slope hazard?

• Avoid the use of multiple layers in pavement design

• Multilayer Example: 6 in flex base, prime, and 2”hmac

Page 7: Narrow Pavement Widening

How can we avoid the safety slope hazard (cont)?

• Consider using a single layer, or “monolithic” approach.

• Monolithic example, 6 or 8” of flex base over subgrade, or 4-8’’ of hmac that fills to final surface.

• The need for the safety slope is eliminated.

Page 8: Narrow Pavement Widening

Flex base vs. hot mix

• Flex base is considerably cheaper, especially as we move farther away from the hmac plants.

• HMAC is seasonal

• Unsuitable subgrade risk

Page 9: Narrow Pavement Widening

Benefits of aggregate prime

• Quick and reliable protective cover

• Finished base under Traffic

• Adheres very well to base course

• Low maintenance under traffic in comparison

• Protects ride quality on finished base

Page 10: Narrow Pavement Widening

Benefits of aggregate prime (cont)

• Traffic uses the widened road immediately

• Cheap base slope protection • All season application

Page 11: Narrow Pavement Widening

Aggregate prime recommendations

• RC-250 with Grade 5 aggregate

• 0.2-0.23 g/sy

• Grade 5-Grade 6 • dry screened• Non-coated

Page 12: Narrow Pavement Widening

Widening vs. Rehabilitation

• Benefit/Cost Ratio

• Labor• Equipment • Project Duration

is comparable between widening and Rehabilitation

Page 13: Narrow Pavement Widening

Widening vs. Rehabilitation

• Major components of increase

• Cement

• extra base

• second full width chip seal

Page 14: Narrow Pavement Widening

RM 336 Real

Page 15: Narrow Pavement Widening

Completed Project RM 783 Gillespie

Page 16: Narrow Pavement Widening

Rehabilitation Project US 83 Kerr

Page 17: Narrow Pavement Widening

Widening RM 336 –Post Agg. Prime

Page 18: Narrow Pavement Widening

Widening RM 336 –Post Agg. Prime

Page 19: Narrow Pavement Widening

Widening RM 335 –Before Agg. Prime

Page 20: Narrow Pavement Widening

Typical Milling Machine

Page 21: Narrow Pavement Widening

Finishing Base RM335 Real