![Page 1: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design](https://reader034.vdocument.in/reader034/viewer/2022042216/5ebdb1f3e3e1612af12d72d5/html5/thumbnails/1.jpg)
NCC Infrastructure
NCC Wind PowerFinland
![Page 2: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design](https://reader034.vdocument.in/reader034/viewer/2022042216/5ebdb1f3e3e1612af12d72d5/html5/thumbnails/2.jpg)
Content1. NCC services2. Contract model3. References in Finland4. Contacts
NCC Infrastructure
![Page 3: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design](https://reader034.vdocument.in/reader034/viewer/2022042216/5ebdb1f3e3e1612af12d72d5/html5/thumbnails/3.jpg)
NCC Infrastructure
We provide wide range of services for wind parks• Assistance in permitting sites• Site surveys• Design• Civil engineering• Electrical engineering
NCC´s Wind Power Services
![Page 4: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design](https://reader034.vdocument.in/reader034/viewer/2022042216/5ebdb1f3e3e1612af12d72d5/html5/thumbnails/4.jpg)
NCC Infrastructure
• Access roads, platforms and assembly areas ‒ Geotechnical investigations ‒ Design and construction
• Foundations‒ Geotechnical investigations and design ‒ Design and construction of foundations‒ Assembly of anchor cages, cable ducts etc.
• Electrical and data network‒ Design, acquisition and construction of substation, main
transformer, cables and accessories‒ Investigation, testing and energization of electrical system
• Assisting in building permitting processes
NCC’s scope as wind farm contractor
![Page 5: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design](https://reader034.vdocument.in/reader034/viewer/2022042216/5ebdb1f3e3e1612af12d72d5/html5/thumbnails/5.jpg)
ReferencesWind Power Projects in Finland
NCC Infrastructure
![Page 6: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design](https://reader034.vdocument.in/reader034/viewer/2022042216/5ebdb1f3e3e1612af12d72d5/html5/thumbnails/6.jpg)
NCC Infrastructure
• 6 wind turbines, Vestas• Customer Empower Oy• Construction time 6–11/2011• NCC’s scope‒ Construction of access roads and assembly areas ‒ Road design
Tuuliwatti, Simo Wind Farm
![Page 7: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design](https://reader034.vdocument.in/reader034/viewer/2022042216/5ebdb1f3e3e1612af12d72d5/html5/thumbnails/7.jpg)
NCC Infrastructure
• 9 turbines, Nordex N117• Construction time 11/2012–6/2013• NCC’s scope‒ Foundation ground works design and construction ‒ Foundation design and construction‒ Substation, electrical and data network design and construction‒ Main contractor liability during the Nordex works
Taaleritehdas, Honkajoki Wind Farm
![Page 8: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design](https://reader034.vdocument.in/reader034/viewer/2022042216/5ebdb1f3e3e1612af12d72d5/html5/thumbnails/8.jpg)
NCC Infrastructure
• 8 turbines, Nordex N117• Construction time 07/2013-07/2014• NCC’s scope‒ Access roads, platforms and assembly areas
• Geotechnical investigations• Design and construction
‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.
‒ Substation, electrical and data network design and construction‒ Main contractor liability during the Nordex works
Taaleritehdas, Nyby Wind Farm
![Page 9: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design](https://reader034.vdocument.in/reader034/viewer/2022042216/5ebdb1f3e3e1612af12d72d5/html5/thumbnails/9.jpg)
NCC Infrastructure
• 19 turbines, Nordex N117• Construction time 2/2014–5/2015• NCC’s scope‒ Access roads, platforms and assembly areas
• Geotechnical investigations• Design and construction
‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.
‒ Electrical and data network design and construction‒ Main contractor liability during the Nordex works
Taaleritehdas,Myllykangas Wind Farm
![Page 10: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design](https://reader034.vdocument.in/reader034/viewer/2022042216/5ebdb1f3e3e1612af12d72d5/html5/thumbnails/10.jpg)
NCC Infrastructure
• 9 turbines, Nordex N131• Construction time 1–10/2015• NCC’s scope‒ Access roads, platforms and assembly areas
• Geotechnical investigations• Design and construction
‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.
‒ Substation, electrical and data network design and construction‒ Main contractor liability during the Nordex works
Taaleritehdas, Kooninkallio Wind Farm
![Page 11: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design](https://reader034.vdocument.in/reader034/viewer/2022042216/5ebdb1f3e3e1612af12d72d5/html5/thumbnails/11.jpg)
NCC Infrastructure
• 6 turbines, Vestas V126• Construction time 1–9/2015• NCC’s scope‒ Access roads, platforms and assembly areas
• Design and construction
‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.
‒ Substation, electrical and data network design and construction
Taaleritehdas, Kytölä Wind Farm
![Page 12: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design](https://reader034.vdocument.in/reader034/viewer/2022042216/5ebdb1f3e3e1612af12d72d5/html5/thumbnails/12.jpg)
NCC Infrastructure
• 2 turbines Nordex N131 and 1 N117• Construction time 3–10/2015• NCC’s scope‒ Access roads, platforms and assembly areas
• Geotechnical investigations• Design and construction
‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.
‒ Electrical and data network design and construction‒ Main contractor liability during the Nordex works
Taaleritehdas, Myllykangas II Wind Farm
![Page 13: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design](https://reader034.vdocument.in/reader034/viewer/2022042216/5ebdb1f3e3e1612af12d72d5/html5/thumbnails/13.jpg)
NCC Infrastructure
• 13 turbines, Nordex N131• Construction time 12/2015–9/2016• NCC’s scope‒ Access roads, platforms and assembly areas
• Geotechnical investigations• Design and construction
‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.
‒ Substation, electrical and data network design and construction
Taaleritehdas, KiPe Wind Farm (Step 1)
![Page 14: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design](https://reader034.vdocument.in/reader034/viewer/2022042216/5ebdb1f3e3e1612af12d72d5/html5/thumbnails/14.jpg)
NCC Infrastructure
• 20 turbines, Nordex N131• Construction time 1/2016–8/2017• NCC’s scope‒ Access roads, platforms and assembly areas
• Geotechnical investigations• Design and construction
‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.
‒ Electrical and data network design and construction
Taaleritehdas, KiPe Wind Farm(Steps 2A and 2B)
![Page 15: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design](https://reader034.vdocument.in/reader034/viewer/2022042216/5ebdb1f3e3e1612af12d72d5/html5/thumbnails/15.jpg)
NCC Infrastructure
• 9 turbines, Nordex N131• Construction time 12/2015–9/2016• NCC’s scope‒ Access roads, platforms and assembly areas
• Geotechnical investigations• Design and construction
‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.
‒ Substation, electrical and data network design and construction
Taaleritehdas, Kantti Wind Farm
![Page 16: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design](https://reader034.vdocument.in/reader034/viewer/2022042216/5ebdb1f3e3e1612af12d72d5/html5/thumbnails/16.jpg)
NCC Infrastructure
• 9 turbines, Nordex N131• Construction time 12/2015–9/2016• NCC’s scope‒ Access roads, platforms and assembly areas
• Geotechnical investigations• Design and construction
‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.
‒ Substation, electrical and data network design and construction
Taaleritehdas, Limakko Wind Farm
![Page 17: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design](https://reader034.vdocument.in/reader034/viewer/2022042216/5ebdb1f3e3e1612af12d72d5/html5/thumbnails/17.jpg)
NCC Infrastructure
• Joint project with NCC Infrastructure in Sweden• 179 turbines, GE Turbine• Construction time 2017–2019• NCC’s scope‒ Access roads, platforms and assembly areas
• Geotechnical investigations• Design and construction
‒ Foundations• Geotechnical investigations and design • Design and construction of foundations• Assembly of anchor cages, cable ducts etc.
‒ Electrical and data network design and construction
Markbygden Wind Farm Piteå, Sweden
![Page 18: NCC Wind Power Finland · • 9 turbines, Nordex N117 • Construction time 11/2012– 6/2013 • NCC’s scope ‒Foundation ground works design and construction ‒Foundation design](https://reader034.vdocument.in/reader034/viewer/2022042216/5ebdb1f3e3e1612af12d72d5/html5/thumbnails/18.jpg)
Mikko NiinimaaGeneral Construction ManagerProject Manager, Wind Power ConstructionTel. +358 50 3100 454, [email protected]
NCC Infrastructure
Contact
Tuomas MäkiläBusiness Manager, Electrical Power Engineering Project Manager, Wind Power ConstructionTel. +358 43 8501 424, [email protected]