![Page 1: NEW ENGINEERING & SCIENCE BUILDING · Provide Submittals for long lead items February 2015 Start Construction March 2015 (weather permitting) Complete Construction January 2017 Sally](https://reader034.vdocument.in/reader034/viewer/2022050523/5fa65fa2c74d4b46351a42a9/html5/thumbnails/1.jpg)
PLANNING, ARCHITECTURAL & ENGINEERING SERVICES
NEW ENGINEERING &
SCIENCE BUILDING
May 30, 2014
31 Ledoyt Rd Storrs, CT 06269 Phone: (860)486-2776 Fax: (860)486-3117 www.paes.uconn.edu
![Page 2: NEW ENGINEERING & SCIENCE BUILDING · Provide Submittals for long lead items February 2015 Start Construction March 2015 (weather permitting) Complete Construction January 2017 Sally](https://reader034.vdocument.in/reader034/viewer/2022050523/5fa65fa2c74d4b46351a42a9/html5/thumbnails/2.jpg)
INTRODUCTION
UConn PAES
John Robitaille, Design Project Manager
Sally Beaudet, Construction Project Manager
Leggat McCall Properties, LLC
Miriam Tuchman, Design Program Manager
Dan Boyd, Design Program Manager
Fusco Corporation
Darren Antolini, Project Manager
Manafort Construction
Jesse Garuti
Pio Monsini
Project Team
Haley & Aldrich
Tim Crowl
Meeting Objective
![Page 3: NEW ENGINEERING & SCIENCE BUILDING · Provide Submittals for long lead items February 2015 Start Construction March 2015 (weather permitting) Complete Construction January 2017 Sally](https://reader034.vdocument.in/reader034/viewer/2022050523/5fa65fa2c74d4b46351a42a9/html5/thumbnails/3.jpg)
PROJECT OVERVIEW
Site Plan
Dan Boyd, Leggat McCall
![Page 4: NEW ENGINEERING & SCIENCE BUILDING · Provide Submittals for long lead items February 2015 Start Construction March 2015 (weather permitting) Complete Construction January 2017 Sally](https://reader034.vdocument.in/reader034/viewer/2022050523/5fa65fa2c74d4b46351a42a9/html5/thumbnails/4.jpg)
PROJECT OVERVIEW
Exterior
Building
Elevation
Dan Boyd, Leggat McCall
![Page 5: NEW ENGINEERING & SCIENCE BUILDING · Provide Submittals for long lead items February 2015 Start Construction March 2015 (weather permitting) Complete Construction January 2017 Sally](https://reader034.vdocument.in/reader034/viewer/2022050523/5fa65fa2c74d4b46351a42a9/html5/thumbnails/5.jpg)
PROJECT OVERVIEW
Floor 1
Dan Boyd, Leggat McCall
![Page 6: NEW ENGINEERING & SCIENCE BUILDING · Provide Submittals for long lead items February 2015 Start Construction March 2015 (weather permitting) Complete Construction January 2017 Sally](https://reader034.vdocument.in/reader034/viewer/2022050523/5fa65fa2c74d4b46351a42a9/html5/thumbnails/6.jpg)
PROJECT OVERVIEW
Floors 2, 3, 4
Dan Boyd, Leggat McCall
![Page 7: NEW ENGINEERING & SCIENCE BUILDING · Provide Submittals for long lead items February 2015 Start Construction March 2015 (weather permitting) Complete Construction January 2017 Sally](https://reader034.vdocument.in/reader034/viewer/2022050523/5fa65fa2c74d4b46351a42a9/html5/thumbnails/7.jpg)
PROJECT OVERVIEW
Floor 5
Dan Boyd, Leggat McCall
![Page 8: NEW ENGINEERING & SCIENCE BUILDING · Provide Submittals for long lead items February 2015 Start Construction March 2015 (weather permitting) Complete Construction January 2017 Sally](https://reader034.vdocument.in/reader034/viewer/2022050523/5fa65fa2c74d4b46351a42a9/html5/thumbnails/8.jpg)
OVERALL SCHEDULE
Abatement & Demolition of Old Central Warehouse June – August 2014
Enlarge Service Road to Central Utility Plant Fall 2014
Complete Construction Documents December 2014
Bid & Award to Subcontractors January 2015
Provide Submittals for long lead items February 2015
Start Construction March 2015 (weather permitting)
Complete Construction January 2017
Sally Beaudet, UConn PAES
![Page 9: NEW ENGINEERING & SCIENCE BUILDING · Provide Submittals for long lead items February 2015 Start Construction March 2015 (weather permitting) Complete Construction January 2017 Sally](https://reader034.vdocument.in/reader034/viewer/2022050523/5fa65fa2c74d4b46351a42a9/html5/thumbnails/9.jpg)
DEMOLITION SCHEDULE
Mobilize, create construction roadway and fencing June 6 - June 13 2014
Abatement June 6 – July 3 2014
Disconnect electrical • Jorgensen • Wood Hall • Storrs Hall • Student Health Services
Shutdown scheduled for June 21 2014
Demolition July 7 – July 30 2014
Clean up and Closeout August 15 – August 26 2014
Sally Beaudet, UConn PAES
![Page 10: NEW ENGINEERING & SCIENCE BUILDING · Provide Submittals for long lead items February 2015 Start Construction March 2015 (weather permitting) Complete Construction January 2017 Sally](https://reader034.vdocument.in/reader034/viewer/2022050523/5fa65fa2c74d4b46351a42a9/html5/thumbnails/10.jpg)
LOGISTICS PLAN Darren Antolini, Fusco Corporation
![Page 11: NEW ENGINEERING & SCIENCE BUILDING · Provide Submittals for long lead items February 2015 Start Construction March 2015 (weather permitting) Complete Construction January 2017 Sally](https://reader034.vdocument.in/reader034/viewer/2022050523/5fa65fa2c74d4b46351a42a9/html5/thumbnails/11.jpg)
NOISE AND DUST CONTROL Darren Antolini, Fusco Corporation Jesse Garuti, Manafort Construction
![Page 12: NEW ENGINEERING & SCIENCE BUILDING · Provide Submittals for long lead items February 2015 Start Construction March 2015 (weather permitting) Complete Construction January 2017 Sally](https://reader034.vdocument.in/reader034/viewer/2022050523/5fa65fa2c74d4b46351a42a9/html5/thumbnails/12.jpg)
VIBRATION MONITORING Tim Crowl, Haley & Aldrich
Due diligence and benchmarking
Specification limits
Monitoring
![Page 13: NEW ENGINEERING & SCIENCE BUILDING · Provide Submittals for long lead items February 2015 Start Construction March 2015 (weather permitting) Complete Construction January 2017 Sally](https://reader034.vdocument.in/reader034/viewer/2022050523/5fa65fa2c74d4b46351a42a9/html5/thumbnails/13.jpg)
DEMOLITION EQUIPMENT PHOTOS Sally Beaudet, UConn PAES
Detail of Hitachi 450 Hydraulic excavator with a pulverizer attachment
![Page 14: NEW ENGINEERING & SCIENCE BUILDING · Provide Submittals for long lead items February 2015 Start Construction March 2015 (weather permitting) Complete Construction January 2017 Sally](https://reader034.vdocument.in/reader034/viewer/2022050523/5fa65fa2c74d4b46351a42a9/html5/thumbnails/14.jpg)
DEMOLITION EQUIPMENT PHOTOS Sally Beaudet, UConn PAES
Detail of several hydraulic excavators (Volvo EC-290 and Volvo EC-360) with a hydraulic Hammer and bucket attachments
![Page 15: NEW ENGINEERING & SCIENCE BUILDING · Provide Submittals for long lead items February 2015 Start Construction March 2015 (weather permitting) Complete Construction January 2017 Sally](https://reader034.vdocument.in/reader034/viewer/2022050523/5fa65fa2c74d4b46351a42a9/html5/thumbnails/15.jpg)
AVERY POINT STUDENT UNION DEMOLITION Sally Beaudet, UConn PAES
Before demolition
After demolition
![Page 16: NEW ENGINEERING & SCIENCE BUILDING · Provide Submittals for long lead items February 2015 Start Construction March 2015 (weather permitting) Complete Construction January 2017 Sally](https://reader034.vdocument.in/reader034/viewer/2022050523/5fa65fa2c74d4b46351a42a9/html5/thumbnails/16.jpg)
PLANNING, ARCHITECTURAL & ENGINEERING SERVICES
Questions & Answers
May 30, 2014