Optimisation of Allocation and Scheduling

in The Blasting Halls Team: CHUA Xin Qian, FAN Siyu, GAN Wei Ming, SHAO Xuna and ZHENG Qingyu

Supervising Professors: Dr. TEO Kwong Meng and Dr. Michel-Alexandre CARDIN

Industry Supervisors: Mr. Daryl LIM and Mr. Andy NG

Objectives

1) Leverage on Excel VBA to Optimize Planning

Process

2) Provide Feasible Planning Scheme

Scope Block Painting Process in Blasting Halls

Allocation Process Map On-site Observations of Process

Interviews with Painting Supervisors

Heuristic Approach

Experience-based Technique

Feasible solution obtained in minimal time

Operation Platform

Excel Visual Basic for Applications (VBA) platform

User-friendly

Compatible with existing planning process

Automate Planning Process

Future Direction

Use as a prototype for future development

Explore other approaches to achieve improved solution

Improve planning accuracy as planning lead time increases

Phase I: Problem & Objective

Phase II: Methodology

Phase III: Implementation

Phase IV: Future Direction

Poka-yoke Features (Mistake-Proofing)

A Japanese concept oriented to finding and correcting problems as close to the source as possible.

User Functions User Interface

Planning Input and Output

Department of Industrial and Systems Engineering System Design Project

1. Manual Process 2. Qualitative 3. Uncertainty 4. No tracking of

Performance Indicators

1. Automated Process 2. Qualitative & Quantitative 3. Account for Uncertainty 4. Tracking of Performance

Indicators

Where we are

Where we want to be

Efficiency

Effectiveness

Problem

Manual planning and scheduling of blocks into blasting halls

Design

Construction

Painting in Blasting Halls

Erection

Handover Date

Required Date

Production Process

Identify Suitable

Halls

Start Allocation

Identify Project &

Block Type

Compare Required Date(RD)

with ESD

Check Handover

Date (HOD)

Hall Available on HOD?

Identify Hall with Earliest Start

Date (ESD)

Will Block meet RD?

Schedule Block into

Hall on ESD

RD earlier than scheduled

block?

Schedule New Block into

Hall on HOD

Request for Additional Manpower

Yes

No

Yes

No

No

Yes

Allocation Ends

Meet Requirements 1. Start after Handover Date 2. Go into Suitable Hall 3. Finish before Required Date

Reduce: Hall Idling Time Increase: Average Difference between Finished Date and Required Date Simplify: Allocation and Scheduling Process

Make necessary modification 1. Manual Allocation 2. Modification of Duration or Required Date

If fail Feasibility Check

Improvement

Feasibility Check

Model Analysis

Planning criteria and constraints

summarised in the Allocation Process Map

Objectives 1) Leverage on Excel

VBA to Optimize Planning Process

2) Provide Feasible Planning Scheme

Contributions 1) Increase in Planning Efficiency and Accuracy

2) Reduction in Planning Lead Time

3) Simplification of the Planning Process

Additional Data Tracking and Report Function Generating Process

:

Modes of Validation

Remarks Results

Test Cases Inputted specific test cases to check for the accuracy of specific outputs

What-if Analysis Carried out what-if analysis to test the robustness of the program

Comparison with Historical Data

Inputted historical data to compare the level of consistency

Feedback from Company

Continuous communication with industry supervisors for feedback

Program Result Analysis

Inputted historical data to analyse the amount of improvement from past schedules

Validation

Include controls/features e.g. dropdown lists and alerts to prevent or diminish error occurrence

Simple and inexpensive inspection at the end of each successive operation to determine or correct defects at the source