Download - Pacific Team

Transcript
Page 1: Pacific Team

Pacific Team For tomorrow may rain, so I’ll follow the sun.

Page 2: Pacific Team

A E C P a c i f i c T e a m 2006

Ajaya MallaUW Madison

Jeremy Tillman

StanfordKatie Walker

Stanford

Magnus Hellsten

KTH

Joannie Rios

UPR

Josh Odelson

Stanford

Construction Managers

ArchitectStructural Engineers

Owner

Erik Kneer

Page 3: Pacific Team

A E C P a c i f i c T e a m 2006

Page 4: Pacific Team

A E C P a c i f i c T e a m 2006

Team Vision

Page 5: Pacific Team

A E C P a c i f i c T e a m 2006

Team ProcessOwner

Construction Managers

ArchitectsEngineers

Solution

O

A

E

C

Page 6: Pacific Team

A E C P a c i f i c T e a m 2006

Site Information Project Details:

• University Building • Use: - Engineering School for Innovative Design

• Location: - San Francisco State University

• Construction in 2015

• $6.5 million Donation

N

Page 7: Pacific Team

A E C P a c i f i c T e a m 2006

Site Location

NEXT TO LAKE MERCED

NNN

Page 8: Pacific Team

A E C P a c i f i c T e a m 2006

Site Climate Information Mild Local Climate

Average Temp: - Mid- 40 deg

Precipitation: - 23 in rain/year

Page 9: Pacific Team

A E C P a c i f i c T e a m 2006

Site Conditions • 18 degree Slope

Hazards:

• Earthquakes – Zone 4 ~ 1-2 miles away from San Andreas Fault• Landslides• Liquefaction

Lake Merced

BLVD.MAP OF

LIQUIFACTION & LANDSLIDE POTENITIAL

SITE SLOPE

N

Page 10: Pacific Team

A E C P a c i f i c T e a m 2006

Site Master Plan

• Reflection Pond

• Bridge Building Entrance • Running/walking path to Lake - Platforms - Ramps - Stairs • Swale

• Natural Vegetation

N

Page 11: Pacific Team

A E C P a c i f i c T e a m 2006

Innovative Financing

University Foundation•$6.5 million to use•Meet current needs

Build Parking Garage•Alleviates university parking problems•Parking fees back Revenue Bonds•Return rate of 6%

$8,415,000

Page 12: Pacific Team

A E C P a c i f i c T e a m 2006

Schedule

Labs FinishedApril 30, 2016

Project Finish July 12, 2016

Site

Foundation

Interior Framing

Roof

MEP/Interior Finishes

Page 13: Pacific Team

A E C P a c i f i c T e a m 2006

Site Access

SITE

Street improvement for South access

Re-route runningpath

BUS STOPS

N

Page 14: Pacific Team

A E C P a c i f i c T e a m 2006

Site Layout

Material StorageSite officesSecurityWater/ElectricityWCParkingWaste containerEquipmentRecyle areaWorkshopWheel wash

N

Page 15: Pacific Team

A E C P a c i f i c T e a m 2006

Slope Stability Solutions Control:

1. Ground water pressure

- Horizontal Drains

2. Storm-water run-off

- Swales3. Slope erosion

- Re-vegetation- Gabions

SWALE

GABIONS

CROSS-SECTION

Page 16: Pacific Team

A E C P a c i f i c T e a m 2006

17 Base Isolators

19

’-4

19

’-4

1

9’-

4”

1

9’-

2”

1

9’-

2”

1

9’-

2”

19’-4” 19’-4” 19’-4” 19’-2” 19’-2” 19’-2”

Foundation Options:

1. Base Isolation2. Foundation

On-Grade

Trade Off Analysis:

Base IsolationDesign RequirementsCost of Structure = $2,155,000

SAVE $580,000

Foundation On-GradeDesign RequirementsCost of Structure = $1,575,000

REQUIRES:

1. Higher Building Design Forces

- Larger Structural Members

- Ductile Connections

58’-0”

REQUIRES:

1. Second Basement

2. Flexible Utility Connections

58’-0”

N

Page 17: Pacific Team

A E C P a c i f i c T e a m 2006

Foundation Solution Design:

• 12” Diameter Bored Pile• Concrete Grade Beams • 4” Concrete Slab On- Grade• Display Graphic for pile design

PILE CAP DETAIL

12 in

~ 40 ft

4 in

Pile Comparison:

• Bored - Cost = $9100/pile

• Driven - Cost = $6300/pile

Page 18: Pacific Team

A E C P a c i f i c T e a m 2006

Basement Floor Instructional Lab

Computer Lab

Seminar Rooms

Auditorium

Restroom

Storage

Balcony

116’-0”

116’-0”

N

Page 19: Pacific Team

A E C P a c i f i c T e a m 2006

Basement• MEP Room

19

’-4

19

’-4

1

9’-

4”

1

9’-

2”

1

9’-

2”

1

9’-

2”

19’-4” 19’-4” 19’-4” 19’-2” 19’-2” 19’-2”

• Gravity System:

- Steel Columns and Beams - Retaining Walls

• Lateral System:

Moment Frame - Column: HSS 16x16 - Beam: W12x120

Shear Wall - Concrete - 12” wide

Shear Wall Core - Concrete - 12” wide

1

9’-

4”

19

’-4

1

9’-

4”

1

9’-

2”

1

9’-

2”

1

9’-

2”

19’-4” 19’-4” 19’-4” 19’-2” 19’-2” 19’-2”

N

Page 20: Pacific Team

A E C P a c i f i c T e a m 2006

First Floor Small Classrooms

Large Classrooms

Administration

Storage

Restrooms

125’-0”

125’-0”

N

Page 21: Pacific Team

A E C P a c i f i c T e a m 2006

First Floor

Wall Truss:

• Span Auditorium

• Transfer Load

• Architectural requirement1

9’-

4”

19

’-4

1

9’-

4”

19

’-2

1

9’-

2”

19

’-2

”19’-4” 19’-4” 19’-4” 19’-2” 19’-2” 19’-2”

N

Page 22: Pacific Team

A E C P a c i f i c T e a m 2006

Wall Truss - Connection

Connection Detail:

• Gusset Plate• Pin Connection

19’-2”

12’-6”

58’-0”

Page 23: Pacific Team

A E C P a c i f i c T e a m 2006

Wall Truss: Load Path

58’-0”

Page 24: Pacific Team

A E C P a c i f i c T e a m 2006

Second FloorStudent offices

Faculty offices

Faculty Lounge

Restrooms

128’-0”

128’-0”

N

Page 25: Pacific Team

A E C P a c i f i c T e a m 2006

Special Features:

1. Link Bridge2. Lateral System3. Core-wall Interface

Second Floor

13

’-6

1

9’-

4”

1

9’-

4”

1

9’-

4”

1

9’-

2”

1

9’-

2”

1

9’-

2”

19’-4” 19’-4” 19’-4” 19’-2” 19’-2” 19’-2” 13’-6

N

Page 26: Pacific Team

A E C P a c i f i c T e a m 2006

Moment Frame Connection

Moment Frame •Double Moment Connection•Biaxial Bending•Use of HSS square tubular section•Pre-North Ridge approved connection

Full Penetration WeldShear

Tab

Bolt

Page 27: Pacific Team

A E C P a c i f i c T e a m 2006

Second Floor

Link Bridge:

• Provides Diaphragm Action• Transfers Lateral Load to Shear Core• Shear Tab Connection to Girder

Page 28: Pacific Team

A E C P a c i f i c T e a m 2006

Lateral System Load Path

Moment Frame

Link Bridge

Shear Wall Core

Load Transfer Girder

N

Page 29: Pacific Team

A E C P a c i f i c T e a m 2006

Roof

128’-0”

128’-0”

Corrugated Metal

Glass

Solar Panels

Louvers

N

Page 30: Pacific Team

A E C P a c i f i c T e a m 2006

Building Section

Interior Spaces

Open Space

Outside Space

128’-0”

Page 31: Pacific Team

A E C P a c i f i c T e a m 2006

HVAC - Evolution

MECHANICAL SYSTEM

HYBRID SYSTEM

Supply

Return

Page 32: Pacific Team

A E C P a c i f i c T e a m 2006

Roof Evolution

Page 33: Pacific Team

A E C P a c i f i c T e a m 2006

Roof Evolution

Page 34: Pacific Team

A E C P a c i f i c T e a m 2006

Roof Structural Evolution

58 ft

30 ft

Efficient Load Path

Shallow Depth

Page 35: Pacific Team

A E C P a c i f i c T e a m 2006

ELLIPTICAL ROOF

(END TRUSS)

Roof Structural Evolution

ARCH TRUSS (WITH COLUMNS)

ELLIPTICAL TRUSS (VARIABLE DEPTH)

Page 36: Pacific Team

A E C P a c i f i c T e a m 2006

Trade Off Analysis

Arch Beam(Option-1)

Curved Truss(Option-2) Comparison

Architecture

Shallow structure Column free spaceSmaller section

Open space highly desired (Option-2)

Structure Efficient Lateral load resisting mechanism

Deep truss required for stiffness

Arch is more efficient

Costing Weight – 20 kip/TrussMore bending More handling

Weight – 21.5 kip/TrussMore welding

Negligible difference

Page 37: Pacific Team

A E C P a c i f i c T e a m 2006

Final Structural Design Key Structure

TOP CHORD (8.625 x 0.5 HSS)BOTTOM CHORD (8.625 x 0.375 HSS)DIAGONALS(7.5 x 0.375 HSS)GIRDER(W6x9 @ 6ft c/c)

58 ft

27 ft

3 ft

5.5 ft

Material Specification

Hollow SectionsASTM A500

Rolled open sectionASTM 529 (Gr 50 Steel)

Bolts & FastenersASTM A490

N

Page 38: Pacific Team

A E C P a c i f i c T e a m 2006

Load Carrying Mechanism

Gravity Load

(Dead / Live)

58 ft

30 ft

97 ft

Dead Load – 35 psf

Live Load - 20 psf

DL – 2.2 in. (L/331)

LL – 0.97 in. (L/725)

------------------------

(DL+LL)= 3.1 in.(L/225)

Page 39: Pacific Team

A E C P a c i f i c T e a m 2006

Load Carrying Mechanism

Lateral Load

(Seismic / Wind)

Wind – 20psf

Seismic – 20% DL

30 ft

58 ft

97 ft

Lateral Drift (max)

1.5 in ( H / 240)

Page 40: Pacific Team

A E C P a c i f i c T e a m 2006

Transverse Direction Bracing Lateral Load: - 0.5” Dia. Bracing rod.

CONNECTION DETAIL

12.5 k

Page 41: Pacific Team

A E C P a c i f i c T e a m 2006

Roof Connections - Conceptual TRUSS BASE

CONNECTION

-CONNECTS TO WIDE

FLANGE COLUMN

-PIN-TYPE DETAIL

3 ft

5.5 ft

Page 42: Pacific Team

A E C P a c i f i c T e a m 2006

Truss Construction (temporary) PREFABRICATED

C-CLAMP

BOLTS

SLOTTED ANGLE WELDED TO COLUMN

ADJUSTABLE COLUMN WITH ANGLED CUT

End Truss with Temporary Supports

Page 43: Pacific Team

A E C P a c i f i c T e a m 2006

2nd Floor Beam Completion

End Truss with Temporary Supports

Roof Construction

Center Truss Installation

TRUSS CHORD SPLICE (Detail

Below)

8.625 x 0.375” HSS

8.625 x 0.375” HSS

0.5” Round End Capping Plate

3/8” Single “V” Butt-Weld

TRUSS CHORD – SPLICE DETAIL

Page 44: Pacific Team

A E C P a c i f i c T e a m 2006

Roof ConnectionsDiagonal Truss Connection

8.625 x 0.5 HSS

(Diagonal truss chord)

0.5” thk capping plate

8.625 x 0.375 HSS (Parallel Truss chord)

3 nos. ½ in. dia (A490 bolts)

4”

0.75” thk end plate Welded to HSS

Page 45: Pacific Team

A E C P a c i f i c T e a m 2006

4D Construction

Page 46: Pacific Team

A E C P a c i f i c T e a m 2006

Cost Comparison

Winter Concept

SUBSTRUCTURE1%

EXTERIOR CLOSURE22%

FOUNDATION7%SITEWORK

6%

EQUIPMENT0%

ELECTRICAL13%

ROOFING & WATERPROOFING

2%

CONVEYING SYSTEM

1% INTERIOR CONSTRUCTION

12%

SUPERSTRUCTURE17%

MECHANICAL19%

Spring Concept

EXTERIOR CLOSURE18%

SUBSTRUCTURE2%

FOUNDATION3%SITEWORK

6%

EQUIPMENT0%

ELECTRICAL16%

ROOFING & WATERPROOFING

2%

CONVEYING SYSTEM

1%

INTERIOR CONSTRUCTION

13%

SUPERSTRUCTURE24%

MECHANICAL15%

Cost Changes

•Superstructure + Increased Truss Steel

• Exterior Closure – Changed from glass to corrugated metal

• Mechanical costs + Under-estimated cost Natural ventilation

•Foundation – Overdesigned piles

• Overall building cost Lowered by $515,000

Finish July 12, 2016

$8,630,000

$8,115,000

$SSU Global Teamwork Center DATED 2/10/2005

ARCHITECT: Joannie Rios

TECHNOLOGY CONCEPT - COLUMNS Building Gross Square Footage 30,000 GSF

Item Description Quantity Unit Unit Price Sub Total Cost/Sf Comments

00 DEMOLITION N/A N/A Building Demolition n/a

01 FOUNDATION $277,250 $9.24

Concrete Piers 23 EA 11,000.00$ 253,000.00$ 8.43$ Piles, 200kip load

Pile Caps 5 CY 250.00$ 1,250.00$ 0.04$ Grade Beams 92 CY 250.00$ 23,000.00$ 0.77$ Structural Excavation Caps/ Grade Beams 110 CY 20.00$ 2,200.00$ 0.07$

02 SUBSTRUCTURE $110,600 $3.69Mass Excavation 1,490 CY 20.00$ 29,800.00$ 0.99$

Retaining Wall 2,600 SF 25.00$ 65,000.00$ 2.17$ 13' high wall,

pumpedSlab on Grade 9,600 SF 4.75$ 45,600.00$ 1.52$ 4" reinforced

03 SUPERSTRUCTURE $1,713,150 $57.11Structural Steel - Standard 235 TONS 4,000.00$ 940,000.00$ 31.33$ Structural Steel - Curved 107 TONS 4,500.00$ 481,500.00$ 16.05$ Concrete Fill over Metal Deck 24,100 SF 4.50$ 108,450.00$ 3.62$ Metal Deck 24,100 SF 2.00$ 48,200.00$ 1.61$ Fireproofing 300 TONS 200.00$ 60,000.00$ 2.00$ Misc. Steel & Metal Stair 1 LS 75,000.00$ 75,000.00$ 2.50$

04 EXTERIOR CLOSURE $1,477,000 $49.23Curved Curtainwall 20,100 SF 70.00$ 1,407,000.00$ 46.90$ Flat End Windows 1,000 SF 45.00$ 45,000.00$ 1.50$ Louvers 1,000 SF 25.00$ 25,000.00$ 0.83$

05 ROOFING & WATERPROOFING $120,000 $4.00Waterproofing 30,000 SF 1.00$ 30,000.00$ 1.00$ Flashing & Sheet Metal 30,000 SF 2.00$ 60,000.00$ 2.00$ Sealants and Caulking 30,000 SF 1.00$ 30,000.00$ 1.00$

06 INTERIOR CONSTRUCTION $954,000 $31.80Doors, Frames & Hardware 70 EA 1,500.00$ 105,000.00$ 3.50$ Wall, Floor, Ceiling Finishes 30,000 SF 25.00$ 750,000.00$ 25.00$ Atrium 1 EA 50,000.00$ 50,000.00$ 1.67$ Building Insulation 30,000 SF 0.50$ 15,000.00$ 0.50$ Miscellaneous Specialties 1 LS 15,000.00$ 15,000.00$ 0.50$ Toilet and Bath Accessories 9 EA 1,000.00$ 9,000.00$ 0.30$ Main Entrance Doors 1 ea 10,000.00$ 10,000.00$ 0.33$

07 CONVEYING SYSTEM $100,000 $3.33Elevators 1 EA 100,000.00$ 100,000.00$ 3.33$

08 MECHANICAL $1,206,000 $40.20Fire Protection 30,000 SF 2.50$ 75,000.00$ 2.50$ Plumbing 18 FIX 4,500.00$ 81,000.00$ 2.70$ HVAC 30,000 SF 35.00$ 1,050,000.00$ 35.00$

09 ELECTRICAL $1,050,000 $35.00Electrical 30,000 SF 35.00$ 1,050,000.00$ 35.00$

11 EQUIPMENT $15,000 $0.50Trash Chute and Compactor 1 LS 15,000.00$ 15,000.00$ 0.50$

12 SITEWORK $420,000 $14.00

Site Preparation 1 Allow 50,000.00$ 50,000.00$ 1.67$ Site Concrete 1 Allow 50,000.00$ 50,000.00$ 1.67$ Site Improvements, AC Paving 1 Allow 100,000.00$ 100,000.00$ 3.33$ Landscape & Irrigation 1 Allow 50,000.00$ 50,000.00$ 1.67$ Site Utilities 1 Alllow 100,000.00$ 100,000.00$ 3.33$ Gabions, horizontal drains 1 Alllow 50,000.00$ 50,000.00$ 1.67$ Pedestrain Trail Alteration 1 Allow 20,000.00$ 20,000.00$ 0.67$ INDIRECT COST 7,055,000.00$ $7,023,000 $220.10 General Conditions 15% $1,058,250 $1,058,250 $35.28Fee 5% $352,750 $352,750 $11.76Contingency 5% $352,750 $352,750 $11.76TOTAL COST $8,818,750 $8,786,750 $292.89

Page 47: Pacific Team

A E C P a c i f i c T e a m 2006

LEED - SustainabilityLEED-NC Version 2.2 Registered Project Checklist

Yes ? No

7 2 6 Sustainable Sites 14 Points

Prereq 1 Construction Activity Pollution Prevention Required

Credit 1 Site Selection 1

Credit 2 Development Density & Community Connectivity 1

Credit 3 Brownfield Redevelopment 1

Credit 4.1 Alternative Transportation, Public Transportation Access 1

Credit 4.2 Alternative Transportation, Bicycle Storage & Changing Rooms 1

Credit 4.3 Alternative Transportation, Low-Emitting and Fuel-Efficient Vehicles 1

Credit 4.4 Alternative Transportation, Parking Capacity 1

Credit 5.1 Site Development, Protect of Restore Habitat 1

Credit 5.2 Site Development, Maximize Open Space 1

Credit 6.1 Stormwater Design, Quantity Control 1

Credit 6.2 Stormwater Design, Quality Control 1

Credit 7.1 Heat Island Effect, Non-Roof 1

Credit 7.2 Heat Island Effect, Roof 1

Credit 8 Light Pollution Reduction 1

Yes ? No

4 1 Water Efficiency 5 Points

Credit 1.1 Water Efficient Landscaping, Reduce by 50% 1

Credit 1.2 Water Efficient Landscaping, No Potable Use or No Irrigation 1

Credit 2 Innovative Wastewater Technologies 1

Credit 3.1 Water Use Reduction, 20% Reduction 1

Credit 3.2 Water Use Reduction, 30% Reduction 1

Yes ? No

5 3 1 Energy & Atmosphere 17 Points

Prereq 1 Fundamental Commissioning of the Building Energy Systems Required

Prereq 2 Minimum Energy Performance Required

Prereq 3 Fundamental Refrigerant Management Required

Credit 1 Optimize Energy Performance 1 to 10

Credit 2 On-Site Renewable Energy 1 to 3

Credit 3 Enhanced Commissioning 1

Credit 4 Enhanced Refrigerant Management 1

Credit 5 Measurement & Verification 1

Credit 6 Green Power 1

continued…

Yes ? No

2 10 1 Materials & Resources 13 Points

Prereq 1 Storage & Collection of Recyclables Required

Credit 1.1 Building Reuse, Maintain 75% of Existing Walls, Floors & Roof 1

Credit 1.2 Building Reuse, Maintain 100% of Existing Walls, Floors & Roof 1

Credit 1.3 Building Reuse, Maintain 50% of Interior Non-Structural Elements 1

Credit 2.1 Construction Waste Management, Divert 50% from Disposal 1

Credit 2.2 Construction Waste Management, Divert 75% from Disposal 1

Credit 3.1 Materials Reuse, 5% 1

Credit 3.2 Materials Reuse,10% 1

Credit 4.1 Recycled Content, 10% (post-consumer + ½ pre-consumer) 1

Credit 4.2 Recycled Content, 20% (post-consumer + ½ pre-consumer) 1

Credit 5.1 Regional Materials, 10% Extracted, Processed & Manufactured Regionally 1

Credit 5.2 Regional Materials, 20% Extracted, Processed & Manufactured Regionally 1

Credit 6 Rapidly Renewable Materials 1

Credit 7 Certified Wood 1

Yes ? No

11 6 Indoor Environmental Quality 15 Points

TechnologySan Francisco State University

Prereq 1 Minimum IAQ Performance RequiredPrereq 2 Environmental Tobacco Smoke (ETS) Control RequiredCredit 1 Outdoor Air Delivery Monitoring 1Credit 2 Increased Ventilation 1Credit 3.1 Construction IAQ Management Plan, During Construction 1Credit 3.2 Construction IAQ Management Plan, Before Occupancy 1Credit 4.1 Low-Emitting Materials, Adhesives & Sealants 1Credit 4.2 Low-Emitting Materials, Paints & Coatings 1Credit 4.3 Low-Emitting Materials, Carpet Systems 1Credit 4.4 Low-Emitting Materials, Composite Wood & Agrifiber Products 1Credit 5 Indoor Chemical & Pollutant Source Control 1Credit 6.1 Controllability of Systems, Lighting 1Credit 6.2 Controllability of Systems, Thermal Comfort 1Credit 7.1 Thermal Comfort, Design 1Credit 7.2 Thermal Comfort, Verification 1Credit 8.1 Daylight & Views, Daylight 75% of Spaces 1Credit 8.2 Daylight & Views, Views for 90% of Spaces 1

Yes ? No

5 Innovation & Design Process 5 Points

Credit 1.1 Innovation in Design: Provide Specific Title 1

Credit 1.2 Innovation in Design: Provide Specific Title 1

Credit 1.3 Innovation in Design: Provide Specific Title 1

Credit 1.4 Innovation in Design: Provide Specific Title 1

Credit 2 LEED® Accredited Professional 1

Yes ? No

29 26 9 Project Totals (pre-certification estimates) 69 Points

Certified 26-32 points Silver 33-38 points Gold 39-51 points Platinum 52-69 points

29 Points

LEED Certification

• Rain water collection

• PV Cells

• Natural ventilation

• Sustainable material

• Sustainable construction

Page 48: Pacific Team

A E C P a c i f i c T e a m 2006

Page 49: Pacific Team

A E C P a c i f i c T e a m 2006


Top Related