PAR 1085 – SOUTH SECONDARY IMPROVEMENTS PROJECT
A 4D GIANT
Eric M. WetzelCarollo Engineers, Inc.
Bentley Be Inspired AwardsNovember 13, 2012
• PAR 1085 South Secondary Improvements Project• What is 4D?• Building the 4D Model• 4D Visualization• The Benefits• Summary• Questions
South Secondary Improvements Project
Outline
South Secondary Improvements Project
Metro Wastewater Reclamation District Robert W. Hite Treatment Facility
(The District)
DAF & Centrate Modifications
Ammonia Facility
Stage 5, RAS Pump Stations, Secondary Clarifier Modifications
South Aeration Complex (SAC)
• $136 million w/ potential $1.8 million bonus for early completion
• Meets new wastewater discharge criteria and adds capacity
• Very tight schedule to meet permit compliance
South Secondary Improvements Project
Carollo Engineers’ Role
• Design Engineer & Owner’s Representative during construction
• Review Contractor’s construction schedule to verify compliance with the Contract
• Responsible for 3D and 4D models
What is 4D?
South Secondary Improvements Project
What is 4D?
• 4D is a tool that links a 3D CAD model with a construction schedule
• The resulting 4D model allows visualization of the planned construction sequence
3D Model + Schedule = 4D Visualization
Building the 4D Model
South Secondary Improvements Project
3D Model• Software Used
Bentley Microstation V8 XM Bentley Architecture V8 XM Bentley Structural V8 XM PlantSpace Design Series V8 XM InRoads XM ProjectWise V8i ProjectWise InterPlot Navigator V8i
• 65 Total Models Anything above 2” pipe was modeled
• 99 Reference Files• Completed during the design phase• Finalist – Be Inspired Awards 2011
3D Model Elements
• To achieve a 4D visualization, the 3D model must be designed into constructible elements Construction Joints Pipe Joints
• 3D model must match the depth of the construction schedule
Construction Schedule
• Software: Primavera P6 v7.0
• Extremely detailed consisting of 12,143 activities
Structural Drawings vs. Construction Schedule
Linking the Model and Schedule
• Import accepted Primavera P6 Schedule into Bentley Navigator V8i
• Link activities in Schedule to Item Sets in the Model Drop and Drag
• After Linking is complete: Close Navigator V8i and Open linked
model in Microstation Use Animation Producer in
Microstation to create image frames Set time frame (May ‘11 – June ‘13) Set frame duration (daily, weekly, etc.)
Import frames to Camtasia for .AVI development
Visualizing the Visualization
• While watching the 4D visualization• Every start activity will turn
the item set within the model green
• Every finish activity will turn it to the model color. Yellow in this example
Example: Concrete – Rebar, Form, Pour, Cure
4D Model – South West Blower Building
PAR 1085 South Secondary Improvements Project
The BenefitsHow does this help?
South Secondary Improvements Project
4D Benefits
• Tool for Risk Mitigation• 4D analysis validated Contractor’s realistic ability
to obtain full bonus ($1.8 million)• Detailed review and identification of issues in the
schedule
Example 1: Concrete Pour Sequence Compliance
Schedule Bust: Wall and Slab are poured concurrently. A single bust = Potentially 14 calendar days.Schedule Bust: Wall is being poured prior to Slab
Example 2: Missing Activities/Links or Inappropriate Logic
“A” – Schedule did not reflect updated CJs.
“B” – Threshold of two facilities. Not accounted for in schedule
A
B
Missing Activities/Links
Upon completion of linking the schedule to the model, linked items can be turned off to show only model items not linked to an activity
Example 3: Visual Assessment of Actual vs. Planned
10/2/2012
4D Benefits – Cont.
• An updated 3D model for Owner’s use
• Public Outreach• Identification of non-
conformance with Contract
• Ability to look-ahead and plan for future Work activities
Summary
South Secondary Improvements Project
Summary
• 4D tool mitigated significant risk associated with a complex and accelerated schedule
• Minimize logic loops, missing activities, non-conformance, etc, to account & save significant time in the schedule. Estimated at 60 working days to date
• A tool to engage stakeholders without a tangible connection to the project• An updated 3D model that can be used for facility maintenance or
modifications• Versatile Bentley software was utilized in all facets of 3D and 4D
development No hardware or software costs incurred to produce 4D
Questions?