![Page 1: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/1.jpg)
Pedestrian Trail and Bridge
Volga, IA
Ryan McDonough
Nathan Gjersvik
Ryan Kowalsky
Spencer McDermott
May 5, 2020
KGMM Engineering
![Page 2: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/2.jpg)
Design Team
KGMM Engineering
Nathan Gjersvik
Substructure Design
Hydrologic Design
Ryan McDonough
Project Manager
Structural Design
Bridge Design
Trail Design
Water Resources
Ryan Kowalsky Spencer McDermott
Structural Design
Bridge Design
![Page 3: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/3.jpg)
Outline
KGMM Engineering
![Page 4: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/4.jpg)
Project Statement & Goals
KGMM Engineering
Existing Trail
New Trail
New Bridge
Existing Trail
Existing Bridge
New Trail
New Bridge
![Page 5: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/5.jpg)
Stub Abutments
Cross Section
KGMM Engineering
![Page 6: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/6.jpg)
Stub Abutments
Plan View
KGMM Engineering
![Page 7: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/7.jpg)
Stub Abutments
Profile View
KGMM Engineering
![Page 8: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/8.jpg)
Pile-founded Pier
Cross Section
KGMM Engineering
![Page 9: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/9.jpg)
Pile-founded Pier
Plan View
KGMM Engineering
![Page 10: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/10.jpg)
Pile-founded Pier
Profile View
KGMM Engineering
![Page 11: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/11.jpg)
Pile-founded Pier
Pile Cap Plan View
Symmetrical pile layout
KGMM Engineering
![Page 12: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/12.jpg)
Bridge Deck
KGMM Engineering
3’-6”
![Page 13: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/13.jpg)
Bridge Truss
KGMM Engineering
150’267’
116’
![Page 14: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/14.jpg)
Trail Design
KGMM Engineering
West Trail
East Trail
Pedestrian Bridge
![Page 15: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/15.jpg)
Scour Protection
Riprap10’ upstream and downstream at each abutment
2’-3' thick
10’ in all directions around pier3’ thick
Engineering fabric under all riprap
Class E revetment stone with 1.0’ median diameter (IADOT BDM)
KGMM Engineering
![Page 16: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/16.jpg)
Scour Protection
KGMM Engineering
![Page 17: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/17.jpg)
Outline
KGMM Engineering
![Page 18: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/18.jpg)
Bridge Cost Estimate - $979,790.00
KGMM Engineering
Item Unit Quantity Price/Unit TotalSteel Truss EA 4 $219,000.00 $876,000.00
Bridge Deck PCC CY 60 $200.00 $12,000.00
Subgrade Stabilization Material SY 260 $3.00 $780.00
Scour Protection CY 173 $40.00 $6,925.00
Cast-In-Place PCC CY 91 $280.00 $25,500.00
#4 Reinforcement Bar TON 0.25 $695.00 $175.00
#9 Reinforcement Bar TON 3.1 $800.00 $2,500.00
#11 Reinforcement Bar TON 0.49 $835.00 $410.00
H-Pile LF 780 $71.00 $55,500.00
Total Bridge Cost $979,790.00
![Page 19: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/19.jpg)
Trail Cost Estimate - $47,340.00
KGMM Engineering
Item Unit Quantity $ Price/Unit Total
Recreational Trail, PCC 6" SY 710 $34.98 $24,900.00
Backfill CY 567.57 $ 21.13 $11,900
Corrugated Metal Culvert (12”) LF 14 $ 21.50 $300.00
Temporary Erosion Control EA 2 $500.00 $1,000.00
Granular Subbase SY 710 $8.20 $5,825.00
Aluminum, Reflective Trail Signs EA 5 $25.00 $125.00
Wood Posts for Trail Signs (4x4) EA 5 $16.98 $85.00
Seeding and Fertilizing ACRE 0.1304 $2,027.37 $265.00
Clearing and Grubbing ACRE 0.3260 $1,757.56 $575.00
Special Compaction of Subgrade
for Recreational TrailSTA 6.39 $365.65 $2,350.00
Total Trail Cost $47,340.00
![Page 20: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/20.jpg)
Total Project Cost - $1,494,000.00
KGMM Engineering
Bridge (Superstructure and Substructure)
Item Unit Quantity $ Price/Unit Total
Steel Truss EA 4 $ 219,000.00 $ 876,000.00
Deck(267x12x.5) CY 60 $ 200.00 $ 12,000.00
Subgrade Stabilization Material SY 260 $ 3.00 $ 780.00
Scour Protection CY 173 $ 40.00 $ 6,925.00
Cast-In-Place Portland Cement Concrete CY 91 $ 280.00 $ 25,500.00
#4 Reinforcement Bar TON 0.25 $ 695.00 $ 175.00
#9 Reinforcement Bar TON 3.1 $ 800.00 $ 2,500.00
#11 Reinforcement Bar TON 0.49 $ 835.00 $ 410.00
H-Pile installation LF 780 $ 71.00 $ 55,500.00
Total Bridge Cost $ 979,790.00
Trail
Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00
Backfill CY 562.79 $ 21.13 $ 11,900.00
Corrugated Metal Culvert (12”) LF 14 $ 21.50 $ 300.00
Seeding and Fertilizing ACRE 0.1304 $ 2,027.37 $ 265.00
Clearing and Grubbing ACRE 0.3260 $ 1,757.56 $ 575.00
Granular Subbase SY 710 $ 8.20 $ 5,825.00
Special Compaction of Subgrade for Recreational Trail STA 6.39 $ 365.65 $ 2,350.00
Temporary Erosion Control EA 2 $ 500.00 $ 1,000.00
Aluminum, Reflective Trail Signs EA 5 $ 25.00 $ 125.00
Wood Posts for Trail Signs (4x4) EA 5 $ 16.98 $ 85.00
Total Trail Cost $ 47,340.00
Bridge Removal
Bridge Removal (350x68) SF 23800 $ 7.00 $ 167,000.00
Total Removal Cost $ 167,000.00
Phase 1 Construction $ 1,027,500.00
Phase 2 Construction $ 167,000.00
Total Construction Cost $ 1,194,500.00
Easements
10% Contingencies $ 120,000.00
15% Engineering and
Administration $ 179,500.00
Total Project Cost $ 1,494,000.00
![Page 21: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/21.jpg)
Phase 1 – Construction
Bridge Construction $ 980,000.00
Construction of Trail $ 47,340.00
Contingencies $ 103,000.00
Engineering/Admin $ 154,000.00
Estimated Total Cost $1,284,000.00
KGMM Engineering
![Page 22: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/22.jpg)
Removal of Cass Street Bridge $167,000.00
Contingencies $ 16,700.00
Engineering/Admin $ 25,050.00
Estimated Total Cost $209,000.00
KGMM Engineering
Phase 2 – Demolition
![Page 23: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/23.jpg)
Outline
KGMM Engineering
![Page 24: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/24.jpg)
Project Overview
KGMM Engineering
Existing Trail
Existing Bridge
New Trail
New Bridge
![Page 25: Pedestrian Trail and Bridge Volga, IA · H-Pile installation LF 780 $ 71.00 $ 55,500.00 Total Bridge Cost $ 979,790.00 Trail Recreational Trail, PCC 6" SY 710 $ 34.98 $ 24,900.00](https://reader033.vdocument.in/reader033/viewer/2022043003/5f8144a258c9f15001382f6d/html5/thumbnails/25.jpg)
KGMM Engineering
KGMM Engineering
3100 Seamans Center for the
Engineering Arts and Sciences
(563) 258-1685
engineering.uiowa.edu
facebook.com/UIowaEngineering
twitter.com/UIowaEngr
Questions?