TXDOT PROJECT COSTING –PEOPLESOFT PROJECT SETUPSFinancial Management Division
06/07/2018
06/07/2018
Table of contents
2
5-6
7-13
14-17
18-24
25-27
3-4
28
Flow Charts
Key Terms
Project Setups – General Information
Project Setups – Funds Distribution
Queries & Reports
Additional Activities & Error Messages
Contact Emails and Training Modules
11
22
33
44
55
66
77
06/07/2018
Partial Multi System Flow Chart
3
FAFOS
Site Manager FAID
FHWA FMIS
Automatic Interface Between Systems/Modules
Manual Load Between Systems
DCIS – Design Construction Information SystemFAFOS – Federal Aid Funding Obligation SystemFHWA FMIS – Fiscal Management Information SystemFAID – Finance Accounting Inactive Projects Database
DCIS
FPAA and MPA(s) Processed
FPAA – Federal Project Authorization and AgreementEstablishes initial obligation amounts for phase(s) of work
MPA – Modified Project AgreementSubmitted to increase or decrease the federal obligation due to actual low bid, cost overruns or cost underruns, and final closeout
PeopleSoft Project Costing
PeopleSoft Accounts Payable
PeopleSoft Customer Contracts
PeopleSoft Billing
PeopleSoft Accounts
Receivable
06/07/2018
Project Set Up Overview
4
06/07/2018
Key Terms
5
Key Term Definition
Project Costing Business Unit (PCBU)
A business unit in Project Costing is defined as an operational subset of the organization. Ex: 60172, 60173, etc.
CSJ Control Section Job
Project AKA “Project ID”
Project is the core project costing Chartfield that captures information for project accounting. DD + CSJ in 60172,60173, & 60176. Ex: 02160101031
(Source) Activity Project component used to capture and collect costs for a specific phase of work
Distributional Activity Determines how expenditures are funded for a given transaction. Ex: Federal, State, Local, or/and Bond
Source Analysis Type Assigned to individual transactions to identify where thetransaction is coming from. For example: Transactions with an ACT are coming from the accounts payable module, transactions with GLE are coming from General Ledger, etc.
Distributional Analysis Type
Distinguishes the funding as federal, state, local, or bond. Ex: FDF, FDS, FDL, or FDB
06/07/2018
Key Terms
6
Key Term Definition
Funds Distribution Funds Distribution is the process of distributing funding by applying Funds Distribution rules to incoming transactions and assigning costs accordingly.
Fund Source AKA “Resource Category”
It enables you to know how the costs are being funded, whether federal, state, bond, or local. Ex: 0006, M001*The “Fund” field used to complete chartfields is a different field, but is often confused in conversation.
Demo ID AKA “Resource Subcategory”
The Demo ID is a subcategory of a funding source that is classified as earmarked. Ex: TX123
Threshold Amount AKA “Obligation Amount”
Funding limit dollar amount for a specific line or sequence of funding
AFA Advanced Funding Agreement
06/07/2018
Business Unit Overview
7
Project setups in these business units are handled by the FIN Project Ledgers team
06/07/2018
How Projects are Set-Up in PeopleSoft Project Costing
The majority of projects are extracted from DCIS
– State Letting Projects, Non-Letting Projects, and Local Letting Projects
Usually setup in two phases
– PE phase
• CSJ to PeopleSoft should only be requested when it’s ready for design work
– Once a project ID is set up it cannot be reused
• Push to PeopleSoft is indicated by a date on the PE DCIS (P11) screen
– Construction and CE phase
• Push to PeopleSoft indicated by an actual let date on the Project Info DCIS Screen(P01)
• State Letting projects, set up process begins after monthly Letting
– Projects are made active in PeopleSoft after Award by Commission
DCIS funding information directly impacts how projects are set up in PS and how expenditures are distributed
*Missing/incorrect DCIS information may delay project set up*
8
06/07/2018
DCIS Inbound Interface
9
Creates and updates Projects and Activities
The Inbound interface from DCIS:
Creates and updates Project Attributes
Creates and updates Fund Distribution Rules
Creates and updates Customer Contracts
Initiated by Letting Management Uses information from P01, P02, P2C, P2D, P03, P04, P05, P11 Three day/two night process
06/07/2018
DCIS P11 Screen – PE Phase
10
PE push to PeopleSoft is initiated by the Letting Management coordinator assigned to that district Letting coordinator enters the date into the “PE Date” field and the interface
process will begin that night
06/07/2018
DCIS P01 Screen
11
06/07/2018
Project Attributes Page
DCIS is the source for all projects in PCBU 60176
– Project ID
• In PS, the project ID consists of the district/division followed by the CSJ (Ex: 02160101031)
– P01 SCREEN: Project Class, Authority Description, Highway Number, County, TxDOTproject number
– P02 SCREEN: Low-Bid Amount, Sub-receipt/Vendor field
– P03 SCREEN: Urban/Rural Code
– P05: Primary CSJ
12
06/07/2018
Project Attributes Page
Some fields are derived from fields in DCIS and then programming within the interface is used to populate the fields in PeopleSoft.
– Site Manager Contract No.
– Primary CSJ
– CE Percentage
– Prorate Flag(Derived from P05)
13
06/07/2018
DCIS Interface- Funds Distribution
“Waterfall” based on the P02 and P2C screens
Funding from P02 screen will be used on activities in the following order:
1) CNST
2) CNSTF
3) CE
P02 screen MUST have an open line of funding
PSFT does not track Cat or Work program
14
06/07/2018
Funds Distribution
Contains funding rules & controls how projects pay out
“Waterfall” funding is set up in Funds Distribution –through the use of Sequences
Expenditures : Once sequence 1 is fully exhausted the remaining flows through to sequence 2. Once sequence 2 is fully exhausted all remaining expenses will flow through to catch sequence 3.
15
Catch sequence indicated by twelve 9’s
06/07/2018
PSFT Total Project Cost – Calculating Threshold Amounts
For all construction CSJs that are let through Site Manager, Finance has additive percentages that are added onto the low bid to come up with a more accurate estimate of what the project will cost.
Rates based on project class, derived from historical data
Contingency (CONT%) – Estimated amount of changes to bid items or work that fall below the threshold for creating a change order
Potential Change Order (PCO%) – Estimated amount of changes orders that will likely be approved and applied to the CSJ
Construction Engineering (ENG%) – Estimated costs for engineering and time charged by TxDOT during the construction phase
16
06/07/2018
Summary of Project Setups
DCIS houses important information on numerous screens that is used to setup projects in Project Costing
– Project attributes come from the P01, P02, P04, & P05 screens
– Project fund distribution rules come from the P02 & P2C screens
It is crucial for the information in DCIS to be accurate in order for the project to be setup correctly
17
06/07/2018
Running Queries
Main Menu>Reporting Tools>Query>Query Viewer
Must have at least PROJECT COSTING (PC) READ ONLY user rights – Call 512-266-6328 or submit a TxDOTNOW ticket if you need this access
18
06/07/2018
Running Queries
To search for a specific query, enter all or part of the query name and click Search
– Click ‘HTML’ link to view in a web browser or ‘Excel’ to pull it up in a spreadsheet
19
06/07/2018
Running Queries
Multiple parameter combinations may be used to run the X_PC_EXP_BY_PROJECT_DETAIL query.
Business Unit and Project ID were used here.
Click View Results
20
06/07/2018
Query: X_PC_EXP_BY_PROJECT_DETAIL
Rate % for each sequence adds up to 100%
Each activity has a “catch” sequence
Analysis Types
To re-distribute any expenditures a PeopleSoft adjustment is needed
21
Catch sequence for activity CNST
Analysis Types
Sequence adds up to 100%
06/07/2018
Common Analysis Types
22
Analysis Type Description Description of Use
FDF Federal Distribution Federal expenditures after funds distribution processing
FDA Advanced Construction Advanced construction expenditures after funds distribution processing, expenditures with this analysis type cannot be billed to the federal government
FDS State Distribution State expenditures after funds distribution processing
FDB Bond Distribution Bond expenditures after funds distribution processing
FDL Local Distribution Local expenditures after funds distribution processing
TDC TDC Distribution Transportation development credits used as the match and billed to FHWA. This occurs after funds distribution processing
SPO Sponsor ReimbursementDistribution
To account for the non-cash match for the local participants
INK In‐Kind Distribution In kind contribution expenditures after funds distribution processing
L- - Last Distribution/Catch Sequence
When federal funds are involved, it allows borrowing within the same fund source and same federal project number
Complete list can be found under the PeopleSoft References link on the FIN TN page
06/07/2018
Common Queries & Reports
23
Query/Report Name Description
X_PC_EXP_BY_PROJECT_DETAIL Funding & LTD expenditures at the project ID, federal project, TxDOT project number or SiteManager level.
X_PC_PRIMARY_SECONDARY_CSJ Provides all projects ID within a SiteManagercontract number. Lists the CE% and pro-rate flag
X_PC_AH_DIST_PROJ_LTD Life to date expenditure details such as account, voucher number and supplier ID
X_PC_FED_PROJ_RESOURCE_DETAIL Pulls entire Project Resource table transactions for a project ID, federal project number, TxDOTproject number, or SiteManager Contract No.
X_PC_RECV_SUMM_QUERY Provides receivables summary details for local entities
5202 Report General project expenditure details based on various search criteria
06/07/2018
Common Navigations Queries & Reports
24
X_PC_EXP_BY_PROJECT_DETAIL Instructions:
Common navigations:
Expenditure 5202 Report Instructions:
PDF File
Microsoft Word Document
PDF File
06/07/2018
Additional Activities
PE-ADM
– Used for TxDOT time charges while funding agreements are created
– 100% state funded
– Currently only for off-system bridge projects
CNSTF-AAH
– Submit Abatement/Asbestos Removal Request Form (resource type 225)
• Request form is on the TNtoday FIN Page under FIN Applications tab
• Notifies Ledgers and Letting Management
– Any work that is done before the FPAA is authorized would not be eligible for federal reimbursement
CE-C
– Redesign of plans Consultant Engineering Coordinated with PEPS
– Can only be setup if the project has gone through letting
– Will be funded the same as PE
25
06/07/2018
Check that the correct PCBU, Project ID and source activity are being used
Contact a FIN Project Ledger’s employee for assistance-Justin Lawson-Sarah Bohuslav
For PE activity, please contact your Project Coordinator in Letting Management
Error Messages
06/07/2018
Error Messages
Budget related error messages
“SRCACT No Budget Exists”
– the combination of activity and source type is not valid in the system
“ORG No Budget Exists”
– the Budget Chartfield string that you are attempting to charge to is not yet set up in the system
“APPROP No Budget Exists”
– the Appropriation (Class) being used for charges does not exist or does not have enough budget for the payment
"Chartfield combination CLASS_FLD ACCOUNT_CNTRT; Invalid Chartfield combination“
– combination within your chartfield string is incorrect
FIN Budget Analyst should be contacted to assist with error
06/07/2018
Contact Emails & Training
Contact Emails
For questions please contact the below mailboxes:
Initial project setups - FIN_PROJECT_LEDGERS
Local participation - FIN_Local-Participation
Federal inactive projects – FIN_UrgentReviewOfFHWAInactiveProjects
Project status changes – FIN_PSFT_Status_Changes
Training
From the ELM homepage, look for this training:
– DEV505 – PSFT Third Party Funding
From this link: http://crossroads/org/erp/ERP_KnowledgeCenter.html, look for this training:
– DEV334 – Maintain Projects
– DEV343 – Managing Contracts