Chapter 8PERT, CPM, Resource Allocation and GERT
On-line MS Project Tutorialshttp://webcampus.stthomas.edu/s3c/Software/Project/ProjectEC_1a.html
![Page 2: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/2.jpg)
Team Alternative
• Form teams of five or fewer– Identify the task of each team member– Rate the contribution of each member
Teams 2,3,and 4
Team 1
![Page 3: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/3.jpg)
Real World Considerations
• Other concurrent projects (size of total commitments)
• Coordinating with other companies (structure)• Have you ever built a TV Tower? (technology)• What is the basis for the estimators estimate?
– Is company experience still valid?– Is 15% for contingencies still appropriate?
Thankfully this is not the real world.Thankfully this is not the real world.Size
Stru
ctur
e Technology
![Page 4: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/4.jpg)
Tasks with MS ProjectTeam One • Manage the other teams • Do a post mortem
– Identify the benefits of a team approach
– Identify the issues encountered– Characterize your team
Team Two - At normal rate• In how many days can the job be
completed?• What bid will yield a 10% pre tax profit?• To reduce risk, what are the key tasks to
watch?
Team Three - At the fastest time:• In how many days can the job be
completed• What bid will yield a 10% pre tax
profit?• To reduce risk, what are the key tasks
to watch?
Team four - • If cost is not a consideration, what
else can be done to shorten the project?
• Address real world issues
![Page 5: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/5.jpg)
Deliverablesshort written reposts
• Team One - Reality of managing this project • Teams Two and Three - MS Project based appropriate network
diagrams for each time scenario identifying: – Key events – Dependencies – Cost estimates for each time scenario
• Team Four– Using team one and two's analysis, provide a list of alternatives for:
• Shortening the project if cost is not an object• Further reducing costs
– Address the real world issues
![Page 6: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/6.jpg)
FAQs
• Yes, you will work in teams• Yes, this is a project within a project• • • Others?
![Page 7: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/7.jpg)
Petersen General ContractorsCase 8-1
the book answer
![Page 8: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/8.jpg)
At a Normal Rate
• Time– The critical path, a a-f-h-i-v-k-cc-ee = 224 days– Next longest path is a-b-c-l-n-m-p-q-r-s-u-ee = 200 days
![Page 9: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/9.jpg)
At a Normal Rate
Costs– Total direct costs = $364,050
• Direct labor = $206,280 • Direct material = $157,770
– + Indirect costs @ 65% of direct cost = $600,682.50– + Contingency @ 15% of direct plus indirect cost =
$690,784.87– + Bid with 10% profit = $759,863.35
$500Direct cost are 50%
![Page 10: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/10.jpg)
Shortest Possible Timesame path new time
• Time– The critical path, a a-f-h-i-v-k-cc-ee = 191 days– Second critical path is a-b-c-l-n-m-p-q-r-s-u-ee = 191 days
25
29
30 14
25 434
![Page 11: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/11.jpg)
Shortest Possible Timesame path new time, new cost
Costs– Total direct costs = $383,813.20
• Direct labor = $226,043.20– Activities on the critical path increase = $16,320– Activities on the second critical path = $3443.20
• Direct material = $157,770 – + Indirect costs and contingency = $728,285.54 – + Bid with 10% profit = $801,114.10
(plus $41,250.25 for 35 days)
Time is money
![Page 12: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/12.jpg)
What to Supervise More Carefully
• Near critical paths• Areas of new technology or technique• New staff• High risk items• Any “high visibility” items• Others
Glass, china and reputation are easily brokenAnd never well mended. Ben Franklin
![Page 13: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/13.jpg)
If “Shortest” is Still Too Long
• Sub contract sub assemblies• Buy a tower and transport it• Others?
Think out of the box
Some Leading Authors
![Page 14: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/14.jpg)
Idea-Based Leadership
• Ensure the presence and respect for idea practitioners
• Set forth an idea strategy in a idea-friendly culture
• Be open to ideas and the people who suggest them
• Reward the practitioners• Signal the importance of ideas
Yes No
How does your organization rate and whySource: What’s the Bid IdeaThomas Davenport, and Laurence Prusak with H. James Wilson
![Page 15: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/15.jpg)
Breaking Through to Innovation• Technology = arrangement of objects, ideas and people to accomplish a goal• Technology brokering = exploiting existing technologies to create new ones• Innovation is not breaking free of the past; it is harnessing the past in new
ways
Source:How Breakthroughs HappenAndrew Hargadon
Your perspective
and knowledge
Othersperspective
and knowledge
![Page 16: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/16.jpg)
The Balancing Act
ActionableDogma
Jack of all tradesMaster of none
"Knowledge" is both the raw material for innovation and "comfort" that inhibit seeking new opportunities outside of your comfort zone.
Inside Outside
Dee
pSh
allo
w
Breath
Dep
th
Networking
New Ideas
Source:How Breakthroughs HappenAndrew Hargadon
![Page 17: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/17.jpg)
The Rules
• Never forget the future is already here. • Analogy trumps invention• Find your discomfort zone• Divided we innovate.• Bridge to your strengths • Build to your weakness • Build teams • As goes the individual, so goes the organization• Rip, mix and burn Source:
How Breakthroughs HappenAndrew Hargadon
![Page 18: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/18.jpg)
Efficiency – Innovation Dichotomy
Efficiency InnovationStay inBusiness
Today’s BusinessClimate
Source:Creating the Innovation CultureFrances Hribe
![Page 19: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/19.jpg)
Honoring the Dissenters Foster Innovation
• Dissenters offer new ideas• Force others to challenge their assumptions• Dissent can:
– Kill wrong or out of date ideas– Tap into peoples tacit (gut) knowledge– Break you out of a think rut SOW
Source:Creating the Innovation CultureFrances Hribe
![Page 20: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/20.jpg)
How to Kill Dissent (Innovation) Without Really Trying
• Best practices – make the status quo better• Treat everybody equally – no one is a
valuable resource who's ideas count• Hire a mini me – all run down the same
train of thought• Design a process for innovation –
oxymoronic?Source:Creating the Innovation CultureFrances Hribe
![Page 21: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/21.jpg)
How to Foster Innovation
• Speak last in meetings• Seek out dissenter’s view• Protect the dissenter• Help dissenter be heard • Challenge the Status Quo
Minorit
y Rep
ots ar
e
a go
od th
ing
Source:Creating the Innovation CultureFrances Hribe
![Page 22: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/22.jpg)
80 /20 and You19th Century – Vilfredo Pareto
• A small minority (20%) account for a majority (80%) of the wealth
20th Century – Joseph Juran
• Solving quality problems depends on differentiation the vital few cause from the trivial many.
Every job should leverage your 20% genius 80% of the timeSource:Richard Koch80/20 Individual
![Page 23: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/23.jpg)
Out of the Box Thinking
•Budgets and Schedules•Self Interest
•Silos and Turf•Good Enough
Problems Looking for a Solution•If resources were no object•Walk in the others shoes
Solutions Looking for a Problem•Where else would it fit•Do it the opposite way
Source:Why NotBary Nalebuff and Ian Ayres
![Page 24: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/24.jpg)
Selling your Ideas
• Elevator pitch• KISS – keep is similar silly• Know to whom to pitch• Make it their idea
Source:Why NotBary Nalebuff and Ian Ayres
![Page 25: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/25.jpg)
The Capability to Innovate
• Process• People• Strategy and Customers• Technology• Measures and Performance
Source: 24/7 InnovationStephen M. Shapiro
![Page 26: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/26.jpg)
ProcessThe “re’s”
• Rethink• Reconfigure• Re-sequence• Relocate• Reduce• Reassign• Retool
![Page 27: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/27.jpg)
Phrase Problems in Ways They Can Be Solved…
• How to…………. (H2)• How might……….. (HM)• In what ways might…….(IWWM)• What might………….(WM)
Source: Dave LabnoInnovation Consultant
Do it globallyDo it globally
![Page 28: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/28.jpg)
Slides not Used
![Page 29: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/29.jpg)
What would you do if you
weren’t afraid?
Source:Spencer JohnsonWho Moved My Cheese
Who Moved My Cheese
![Page 30: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/30.jpg)
We all approach EC Change Differently
• Sniff – Sniffs out the situation and sees early
• Scurry – Goes into action immediately• Hem – Does not want to deal with change
and stays in familiar territory• Haw - Sees what he is doing is wrong,
laughs at himself, and finally changes
![Page 31: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/31.jpg)
Haw’s Writing on the Wall
• Change happens, they keep moving the cheese• Anticipate change – get ready for the cheese to
move• Monitor change – smell the cheese often• Adapt to change quickly• Enjoy change – savor the adventure• Be ready to change quickly and enjoy it again.
They keep moving the cheese
![Page 32: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/32.jpg)
The Johari Window
Hidden
BlindUnknown
Open
Kno
w to
Sel
f
Known to Others
Unk
now
n
Unknown
Kno
wn
Known
TellA
sk
![Page 33: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/33.jpg)
Pareto – Yesterday and Today
• Corporations created wealth• Jobs are repetitive & labor
intensive• Managers – Theory X• Shareholders consume wealth
• Capital is king• Centralized planning yields
strategic goals• Economies of scale and mass
production• Mangers are focus of power
• Individuals create wealth• Few employees &creative
imagination• Coaches - Theory Y and Z• Venture capitalist and
entrepreneurs share the wealth• Creativity is critical element• Agility & contractual relationships • Mass customization
• Companies reunite ownership and control
Managerial Capitalism Individualism
Source:Richard Koch80/20 Individual
![Page 34: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/34.jpg)
Customer Strategies
• Add more value• Listen• Serve• Hire
![Page 35: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/35.jpg)
Creating a Culture of Innovation
• Envision• Enable• Explode• “EmpowerTool”
![Page 36: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/36.jpg)
Technology and Innovation
• Create a virtual enterprise• Change the rules of the game• Collaborate across the value chain• Increase the knowledge of employees• Launch new businesses
![Page 37: Petersen General Contractors Case 8-1](https://reader035.vdocument.in/reader035/viewer/2022070423/568167d1550346895ddd238d/html5/thumbnails/37.jpg)
Getting There
• Alliance Based• Capability Bases• Process Dominated• Process Driven• Process Sensitive• Functionally Bound
Stag
es