PPP International Best Practice and Regional Application
Overview of Public Private Partnerships (PPPs)
23-25 April, 2008Tegucigalpa, Honduras
Filip DrapakWorld Bank Institute
![Page 2: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/2.jpg)
Why PPP
• Large infrastructure gap in both developed as well as developing countries
• Risk management
• Project management skill
• Lack of public funding available for infrastructure
• Procurement efficiency
![Page 3: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/3.jpg)
How is PPP defined?
• Long term contract
• Between Private and Public body
• Contract contains risks that are withhold by private sector
![Page 4: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/4.jpg)
Roles of Partners
Successful project
Public partnerPrivate partner
Rules of the game set up by public sector:
- Legislation and regulation- Institutions- Procedures- Procurement
Project inputs set up by private partner:
- Design- Construction schedule and content- Maintenance schedule- Subcontractors
![Page 5: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/5.jpg)
Types of PPP
1. Who is paying? 2. Who has a demand risk?
Concession type PFI type
• User pays principle• Demand risk with private partner
• Public body pays on behalf of users• Demand risk with public partner
Hybrid type
• Shared payments between Public and User• Demand risk with private partner, public partner or shared
![Page 6: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/6.jpg)
Contractual types of PPPs
• M&O ?– long term operation and maintenance contract
• DB ?– Design Build• BBO ?– Buy Build Operate• BOT – Build Operate Transfer• BOO – Build Own Operate• BOOT – Build Own Operate Transfer• DBFO- Design Build Finance Operate• Concession
![Page 7: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/7.jpg)
How to make it a success?
Project
Public partner
Private partner
Finance providersUsers
Meet objectives of all stakeholders
![Page 8: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/8.jpg)
Public sector objective
• Output based delivery of infrastructure and service
• Value for Money• Procurement according to regulation• Risk transfer to Private partner
![Page 9: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/9.jpg)
Private partner objective
• Profit• Lowest possible procurement risks• Reference• Long term use of own capacity• Risks transferred to subcontractors• Projects pipeline
![Page 10: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/10.jpg)
Financier objective
• Save return of loan• Profit margin reflecting the risk• Risks not with borrower (transferred to
public sector or to subcontractors)
![Page 11: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/11.jpg)
Users objective
• Low or no user fees• Transparency of tariffs and procurement• Quality of infrastructure and services
![Page 12: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/12.jpg)
Is there a Best practise?
Rules of game
Capacity
Political will Market capability
![Page 13: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/13.jpg)
Political will
• Demonstrated political will
• Ideally not dependent on election terms
• Political rationale
![Page 14: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/14.jpg)
Rules of game
• Clear procedures of project management
• Public procurement legislation
• Policy and regulation
• Law and legislation optimisation
• Standardised contacts
• Clear tolls of avaluation
![Page 15: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/15.jpg)
Market capacity
• Availability of Experienced sponsors
• Availability of reliable subcontractors
• Availability of long term finance at a given risk profile
• Availability of risk mitigating instrument
![Page 16: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/16.jpg)
Capacity
• Capacity (public) on national level
• Capacity (public) on executive level
• Institutional capacity, memory and experience
• Capacity with private sector – Advisory– Project Sponsors– Financiers
![Page 17: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/17.jpg)
What is different in PPP?
• Extra costs:– For preparation and procurement– Cost of capital – Expensive debt
• Benefits– Life time costing– Risk transfer– Innovation
![Page 18: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/18.jpg)
Fiscal space
• The Extent to which fiscal decisions can be made by a public body– Fiscal space is a key driver for PPPs– Successful PPPs tend to enlarge fiscal space– Fiscal space can be jeopardised by “bad”
PPPs
![Page 19: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/19.jpg)
Project Finance and PPP
• Financing infrastructure using Public Debt is in terms of financing most cheapest ways, however each new debt can affect overall rating and make all debts more expensive
• Project finance is most expensive way of financing projects, however its influence on overall rating and fiscal space can be limited
• To accept all risks and use Project finance is the worst solution for a Government
![Page 20: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/20.jpg)
Project Finance - Risk Analyses
Force major risks
Risk mitigation and credit enhancement
Sovereign risks
On-project risks
![Page 21: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/21.jpg)
Construction risk
• Key risk in PPP/PFI
• Difficult to measure
• Fully transferred to Subcontractors
• Some issues:– site conditions, potential delays, credit rating
and track record of Subcontractor, new or existing project, vulnerability of project, risks of currency and inflation, planning risks
![Page 22: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/22.jpg)
Demand risk
• Key risk in projects that apply user fees
• Difficult to predict
• Difficult to mitigate
• Some issues:– Users willingness to pay, level of fees,
alternatives, who is responsible if there is not demand….
![Page 23: PPP International Best Practice and Regional Application Overview of Public Private Partnerships (PPPs) 23-25 April, 2008 Tegucigalpa, Honduras Filip Drapak](https://reader034.vdocument.in/reader034/viewer/2022042822/56649eb75503460f94bc0986/html5/thumbnails/23.jpg)
What can jeopardise PPP
– Tender is not competitive or transparent– Project risks are not well defined and
contractually transferred– Risks are to high and can’t be mitigated– Change in political will