S T A N D A R D P R O C U R E M E N T D O C U M E N T
Prequalification Document forProcurement of Works
and
Users Guide
The World Bank
August 2006revised May 2007 and September 2010
-
8/3/2019 Prequal en 09 Sep 10
2/86
ii
September 2010 Revision
This revision dated September 2010 is, inter alia, to modify the Eligibility and Fraud andCorruption clauses to align their text with that of the May 2010 corrigendum to the ProcurementGuidelines, reflecting the changes related to Fraud and Corruption as per the Agreement for
Mutual Enforcement of Debarment Decisions between the Multilateral Development Banks, towhich the World Bank Group is a signatory. This Standard Bidding Document is applicable toPrequalification for Procurement of Works funded under IBRD- or IDA- financed projectswhose Legal Agreement makes reference to (a) the Guidelines for Procurement under IBRDLoans and IDA Credits, dated May 2004, revised October 2006, or (b) the Guidelines forProcurement under IBRD Loans and IDA Credits, dated May 2004, revised October 2006 andMay 2010.
May 2007 Revision
This revision dated May 2007 is to modify Sub-Clauses 3.1, and 4.6 of Section I, Instructions toApplicants to align their text with that of the corrigenda of the Procurement Guidelines, issued inOctober, 2006, to reflect the changes related to Fraud and Corruption as per the World BanksSanctions Reform package approved by the Board of Directors in August, 2006
August 2006 Revision
This revision dated August 2006 changed the provision in ITA 18.1, Late Applications, andadded a corresponding entry in the PDS, to offer the Employer the option to choose between two
alternate treatments for applications received past the deadline for submission of applications.
-
8/3/2019 Prequal en 09 Sep 10
3/86
iii
ForewordThis Standard Procurement Document Prequalification Document for Procurement of Works andUsers Guide has been prepared by the World Bank and is based on the Master ProcurementDocument Prequalification Document for Procurement of Works and Users Guide prepared by
the Multilateral Development Banks and International Financing Institutions. This documentreflects the majority view of these institutions and is to be used when a prequalification processtakes place prior to the bidding process for procurement of works through International CompetitiveBidding (ICB) in projects that are financed in whole or in part by the World Bank.
This document is organized into two (2) main components:
The Prequalification Document for Procurement of Works; and
A Users Guide for the Prequalification Document for Procurement of Works.
Those wishing to submit comments or questions on these documents or to obtain additionalinformation on procurement under World Bank-financed projects are encouraged to contact:
Procurement Policy and Services GroupOperations Policy and Country Services Vice Presidency
The World Bank1818 H Street, NW
Washington, D.C. 20433 [email protected]
http://www.worldbank.org/procure
mailto:[email protected]://www.worldbank.org/procuremailto:[email protected]://www.worldbank.org/procure -
8/3/2019 Prequal en 09 Sep 10
4/86
Summary Description
This Standard Procurement Document (SPD) consists of the Prequalification Procedures for
Procurement of Works and its Users Guide. A brief description of this document is givenbelow.
Prequalification Document for Procurement of Works
PART 1 PREQUALIFICATION PROCEDURES
Section I. Instructions to Applicants (ITA)
This Section specifies the procedures to be followed by Applicants in the preparation and submission of their Applications for Prequalification (AFPs).Information is also provided on opening and evaluation of AFPs. Section I containsprovisions that are to be used without modification.
Section II. Prequalification Data Sheet (PDS)
This Section consists of provisions that are specific to each prequalification andsupplement the information or requirements included in Section I, Instructions to
Applicants.
Section III. Qualification Criteria and Requirements
This Section contains the methods, criteria, and requirements to be used todetermine how Applicants shall be prequalified and later invited to bid.
Section IV. Application Forms
This Section contains the forms for the Application Submission Form and all theforms required to be submitted with the Application.
Section V. Eligible Countries
This Section states the country eligibility policy of the Bank, and provides lists ofineligible countries
-
8/3/2019 Prequal en 09 Sep 10
5/86
v
PART 2. WORKS REQUIREMENTS
Section VI. Scope of Works
This Section includes a summary description, delivery and completion schedules,technical specifications and drawings of the Works subject of this prequalification.
Users Guide for the Prequalification Document for Procurement of Works
This Guide to the Standard Prequalification Document contains detailedexplanations and recommendations to Employers on how to prepare aPrequalification Document for a specific procurement of Works and evaluateapplications. The Guide is not a part of the Prequalification Document.
-
8/3/2019 Prequal en 09 Sep 10
6/86
vi
PROCUREMENT DOCUMENTS
Prequalification Document for
Procurement of
[Insert Title of the Works]
Issued on: [insert date]
Invitation for Prequalification No.: [insert number]
ICB No.: [insert number]
Employer: [insert full legal name of Employer]
Country: [insert Country]
-
8/3/2019 Prequal en 09 Sep 10
7/86
vii
Preface
This Prequalification Document (an update of the September 1999 document) for Procurement ofWorks (PQD) has been prepared by the World Banks Procurement Policy and Services Group and
is based on the Standard Procurement Document Prequalification Document for Procurement ofWorks issued by the World Bank, dated September 1999, revised March 2000. This PQD reflectsthe structure and the provisions of the Master Procurement Document Prequalification Documentfor Procurement of Works issued by the Multilateral Development Banks and InternationalFinancial Institutions, except where specific considerations of the procurement policies of theWorld Bank have required a change. This PQD incorporates the new features of the May 2004Procurement Guidelines.
-
8/3/2019 Prequal en 09 Sep 10
8/86
viii
Contents
PART 1 Prequalification Procedures........................................................................................1
Section I. Instructions to Applicants................................................................................................2
Section II. Prequalification Data Sheet..........................................................................................14
Section III. Qualification Criteria and Requirements....................................................................18
1-35 Section III. Qualification Criteria and Requirements............................................................20
Section IV. Application Forms......................................................................................................23
1-35 Section IV. Application Forms..............................................................................................36
Section V. Eligible Countries........................................................................................................38
PART 2 Works Requirements...................................................................................................1
Section VI. Scope of Works............................................................................................................2
2-35 Section VI. Scope of Works....................................................................................................4
Users Guide...................................................................................................................................1
35 Users Guide Introduction..........................................................................................................2
35 Users Guide Why Prequalification............................................................................................8
35 Users Guide The Prequalification Process..............................................................................10
35 Users Guide Section II. Prequalification Data Sheet (PDS)...................................................14
35 Users Guide Section III. Qualification Criteria and Requirements.........................................16
35 Users Guide Section III. Qualification Criteria and Requirements.........................................22
35 Users Guide s...........................................................................................................................24
35 Users Guide ............................................................................................................................26
35 Users Guide ............................................................................................................................28
35 Users Guide ............................................................................................................................34
-
8/3/2019 Prequal en 09 Sep 10
9/86
1-1
PART 1 Prequalification Procedures
-
8/3/2019 Prequal en 09 Sep 10
10/86
1-2 Section I. Instructions to Applicants
Section I. Instructions to Applicants
Table of ClausesA. General ........................................................................................................................................ 4
1. Scope of Application ............................................................................................................ 42. Source of Funds .................................................................................................................... 43. Fraud and Corruption ............................................................................................................44. Eligible Applicants ............................................................................................................... 65. Eligible Goods and Related Services .................................................................................... 8
B. Contents of the Prequalification Document ................................................................................ 8
6. Sections of Prequalifica tion Document ................................................................................ 87. Clarification of Prequali fication Document ...........................................................................9
8. Amendment of Prequalifica tion Document .......................................................................... 9C. Preparation of Applications ........................................................................................................ 9
9. Cost of Applications ............................................................................................................. 910. Language of Application .................................................................................................... 911. Documents Comprising the Application ............................................................................ 912. Application Submission Form ...........................................................................................1013. Documents Establishing the Eligibility of the Applicant .................................................. 1014. Documents Establishing the Qualifications of the Applicant ............................................ 1015. Signing of the Application and Number of Copies ...........................................................10
D. Submission of Applications ...................................................................................................... 10
16. Sealing and Identification of Applications ........................................................................ 1017. Deadline for Submission of Applications ..........................................................................1118. Late Applications ...............................................................................................................1119. Opening of Applications ....................................................................................................11
E. Procedures for Evaluation of Applications ...............................................................................11
20. Confidential ity ...................................................................................................................1121. Clarification of Applications .............................................................................................1122. Responsive ness of Applications ........................................................................................ 1223. Domestic Bidder Price Preference ..................................................................................... 1224. Subcontrac tors ................................................................................................................... 12
F. Evaluation of Applications and Prequalification of Applicants ................................................12
25. Evaluation of Applications ................................................................................................ 1226. Employers Right to Accept or Reject Applications .........................................................1227. Prequalifica tion of Applicants ...........................................................................................1328. Notification of Prequalifica tion ......................................................................................... 1329. Invitation to Bid .................................................................................................................1330. Changes in Qualifications of Applicants ........................................................................... 13
-
8/3/2019 Prequal en 09 Sep 10
11/86
Section I. Instructions to Applicants 1-3
-
8/3/2019 Prequal en 09 Sep 10
12/86
1-4 Section I. Instructions to Applicants
Section I. Instructions to Applicants
A. General
1. Scope ofApplication
1.1 In connection with the Invitation for Prequalification indicated inSection II, Prequalification Data Sheet (PDS), the Employer, asdefined in the PDS, issues this Prequalification Document (PQD) toapplicants interested in bidding for the works described in Section VI,Scope of Works. The number of contracts and the name andidentification of each contract, and the International CompetitiveBidding (ICB) number corresponding to this prequalification, areprovided in the PDS.
2. Source of
Funds
2.1 The Borrower or Recipient (hereinafter called Borrower) indicatedin the PDS has applied for or received financing (hereinafter called
funds) from the International Bank for Reconstruction andDevelopment or the International Development Association(hereinafter called the Bank) towards the cost of the project namedin the PDS. The Borrower intends to apply a portion of the funds toeligible payments under the contract(s) resulting from the bidding forwhich this prequalification is conducted.
3. Fraud and
Corruption
3.1 It is the Banks policy to require that Borrowers (including beneficiaries of Bank loans), as well as bidders, suppliers, andcontractors and their agents (whether declared or not), personnel,subcontractors, sub-consultants, service providers and suppliers,under Bank-financed contracts, observe the highest standard of ethics
during the procurement and execution of such contracts.1 Inpursuance of this policy, the Bank:
(a) defines, for the purposes of this provision, the terms set forthbelow as follows:
(i) corrupt practice is the offering, giving, receiving orsoliciting, directly or indirectly, of anything of value toinfluence improperly the actions of another party2;
(ii) fraudulent practice is any act or omission, including amisrepresentation, that knowingly or recklessly misleads,
or attempts to mislead, a party to obtain a financial orother benefit or to avoid an obligation3;
1 In this context, any action taken by a bidder, supplier, contractor, or any of its personnel, agents, sub-consultants, sub-contractors, service providers, suppliers and/or their employees to influence the procurementprocess or contract execution for undue advantage is improper.
2 Another party refers to a public official acting in relation to the procurement process or contractexecution]. In this context, public official includes World Bank staff and employees of other organizationstaking or reviewing procurement decisions.
3 Party refers to a public official; the terms benefit and obligation relate to the procurement process
-
8/3/2019 Prequal en 09 Sep 10
13/86
Section I. Instructions to Applicants 1-5
(iii) collusive practice is an arrangement between two or moreparties4 designed to achieve an improper purpose, includingto influence improperly the actions of another party;
(iv) coercive practice is impairing or harming, or threateningto impair or harm, directly or indirectly, any party5 or the
property of the party to influence improperly the actionsof a party;
(v) "obstructive practice" is
(aa) deliberately destroying, falsifying, altering orconcealing of evidence material to the investigationor making false statements to investigators in orderto materially impede a Bank investigation intoallegations of a corrupt, fraudulent, coercive orcollusive practice; and/or threatening, harassing orintimidating any party to prevent it from disclosing
its knowledge of matters relevant to the investigationor from pursuing the investigation; or
(bb) acts intended to materially impede the exercise ofthe Banks inspection and audit rights provided forunder sub-clause 3.1 (e) below.
(b) will reject a proposal for award if it determines that the bidderrecommended for award has, directly or through an agent,engaged in corrupt, fraudulent, collusive, coercive orobstructive practices in competing for the contract in question;
(c) will cancel the portion of the loan allocated to a contract if it
determines at any time that representatives of the Borrower orof a beneficiary of the loan engaged in corrupt, fraudulent,collusive, or coercive practices during the procurement or theexecution of that contract, without the Borrower having takentimely and appropriate action satisfactory to the Bank to addresssuch practices when they occur;
(d) will sanction a firm or an individual, at any time, in accordancewith prevailing Banks sanctions proceduresa, including by publicly declaring such firm or individual ineligible, eitherindefinitely or for a stated period of time: (i) to be awarded a
or contract execution; and the act or omission is intended to influence the procurement process or contractexecution.
4 Parties refers to participants in the procurement process (including public officials) attempting toestablish bid prices at artificial, non competitive levels.
5 Party refers to a participant in the procurement process or contract execution.a A firm or an individual may be declared ineligible to be awarded a Bank-financed contract upon
completion of the Banks sanctions proceedings as per its sanctions procedures, including inter alia: (i)temporary suspension in connection with an ongoing sanctions proceeding; (ii) cross-debarment as agreed withother International Financial Institutions, including Multilateral Development Banks; and (iii) the World BankGroup corporate administrative procurement sanctions procedures for fraud and corruption.
-
8/3/2019 Prequal en 09 Sep 10
14/86
1-6 Section I. Instructions to Applicants
Bank-financed contract; and (ii) to be a nominatedb sub-contractor, consultant, manufacturer or supplier, or serviceprovider of an otherwise eligible firm being awarded a Bank-financed contract; and
3.2 In further pursuance of this policy, Applicants shall permit the Bank
to inspect any accounts and records and other documents relating tothe Application submission, Bid Submission and contractperformance, and to have them audited by auditors appointed by theBank.
4. Eligible
Applicants
4.1 An Applicant shall be a private, public or government owned legal entity,subject to ITA 4.8, or any combination of them in the form ofassociation(s) including Joint Venture (JV) with the formal intent, asevidenced by a letter of intent), to enter into an agreement or under anexisting agreement. In the case of a JV, unless otherwise specified inthe PDS, (i) all parties shall be jointly and severally liable, and (ii)there shall be no limit on the number of partners.
4.2 The eligibility criteria listed in this Clause 4 shall apply to theApplicant, including the parties constituting the Applicant, i.e., its proposed partners, subcontractors or suppliers for any part of theContract including related services.
4.3 An Applicant may have the nationality of any country, subject to therestrictions pursuant to sub clause 4.11. An Applicant shall bedeemed to have the nationality of a country if the Applicant is a citizen,or is constituted, incorporated or registered and operates in conformitywith the provisions of the laws of that country, as evidenced by its
Articles of Incorporation or Documents of Constitution, and itsRegistration Documents.
4.4 Applicants and all parties constituting the Applicant shall not have aconflict of interest. Applicants shall be considered to have a conflictof interest, if they participated as a consultant in the preparation ofthe design or technical specifications of the Works that are thesubject of this prequalification. Where a firm, or a firm from thesame economic or financial group, in addition to consulting, also hasthe capability to manufacture or supply goods or to construct works, thatfirm, or a firm from the same economic or financial group, cannot
normally be a supplier of goods or works, if it provided consultingservices for the contract corresponding to this prequalification, unless itcan be demonstrated that there is not a significant degree of common
b A nominated sub-contractor, consultant, manufacturer or supplier, or service provider (different names areused depending on the particular bidding document) is one which either has been: (i) included by the bidder inits pre-qualification application or bid because it brings specific and critical experience and know-how that areaccounted for in the evaluation of the bidders pre-qualification application or the bid; or (ii) appointed by theBorrower.
-
8/3/2019 Prequal en 09 Sep 10
15/86
Section I. Instructions to Applicants 1-7
ownership, influence or control.
4.5 An Applicant shall submit only one application in the samePrequalification process, either individually as an Applicant or as apartner of a joint venture. No Applicant can be a subcontractor while
submitting an application individually or as a partner of a joint venturein the same Prequalification process. A Subcontractor in any applicationmay participate in more than one application, but only in that capacity.An Applicant who submits, or participates in, more than one applicationwill cause all the applications in which the Applicant has participated tobe disqualified.
4.6 An Applicant that has been sanctioned by the Bank in accordancewith the above ITB 3.1 (d), or in accordance with the Bank'sGuidelines on Preventing and Combating Corruption in ProjectsFinanced by IBRD Loans and IDA Credits and Grants, shall beineligible to be awarded a Bank-financed contract, or benefit from aBank-financed contract, financially or otherwise, during such periodof time as the Bank shall determine.
4.7 The Bank maintains a list of firms and individuals that have beensanctioned by the Bank pursuant to Sub-Clause 3.1 (d) and are noteligible to participate in procurement financed by the Bank. The list isregularly updated; its address is specified in the PDS.
4.8 Government-owned entities in the Employers Country shall be eligibleonly if they can establish that they are legally and financiallyautonomous, and operate under commercial law, and that they are not
dependent agencies of the Employer.
4.9 Applicants shall not be under execution of a BidSecuring Declarationin the Employers Country.
4.10 Applicants and all parties constituting the Applicant shall provide suchevidence of their continued eligibility satisfactory to the Employer, asthe Employer shall reasonably request.
4.11 Applicants from an eligible country may be excluded if, (a) as a matterof law or official regulations the Borrowers country prohibitscommercial relations with that country, provided that the Bank is
satisfied that such exclusion does not preclude effective competitionfor the supply of goods or the contracting of works required; or (b) byan act of compliance with a decision of the United Nations SecurityCouncil taken under Chapter VII of the Charter of the United Nations,the Borrowers country prohibits any import of goods or contracting ofworks or services from that country, or any payments to persons orentities in that country. Section V, Eligible countries provide lists of
-
8/3/2019 Prequal en 09 Sep 10
16/86
1-8 Section I. Instructions to Applicants
ineligible countries pursuant to this Sub Clause 4.11.
5. Eligible Goods
and Related
Services
5.1 All goods and related services to be supplied under the Contract to befinanced by the Bank shall have as their origin in any country inaccordance with Section V, Eligible Countries.
B. Contents of the Prequalification Document
6. Sections of
Prequalifica-
tion Document
6.1 The document for the prequalification of Applicants (hereinafter -prequalification document) consists of parts 1 and 2 which compriseall the sections indicated below, and should be read in conjunction withany Addendum issued in accordance with ITA 8.
PART 1 Prequalification Procedures
Section I. Instructions to Applicants (ITA)
Section II. Prequalification Data Sheet (PDS)
Section III Qualification Criteria and Requirements
Section IV. Application Forms
Section V. Eligible Countries
PART 2 Works Requirements
Section VI. Scope of Works
6.2 The Invitation for Prequalification Applications issued by theEmployer is not part of the prequalification document. A sample formis provided as an attachment to this Prequalification Document for
information only.
6.3 The Employer accepts no responsibility for the completeness of theprequalification document and its addenda unless they were obtaineddirectly from the Employer.
6.4 The Applicant is expected to examine all instructions, forms, and terms inthe Prequalification Document and to furnish all information ordocumentation required by the Prequalification Document.
-
8/3/2019 Prequal en 09 Sep 10
17/86
Section I. Instructions to Applicants 1-9
7. Clarification
of Prequali-
fication
Document
7.1 A prospective Applicant requiring any clarification of thePrequalification Document shall contact the Employer in writing at theEmployers address indicated in the PDS. The Employer will respondin writing to any request for clarification provided that such request isreceived no later than fourteen (14) days prior to the deadline for
submission of applications. The Employer shall forward copies of itsresponse to all applicants who have acquired the prequalificationdocument directly from the Employer including a description of theinquiry but without identifying its source. Should the Employer deemit necessary to amend the prequalification document as a result of aclarification, it shall do so following the procedure under ITA 8 and inaccordance with the provisions of ITA 17.2.
8. Amendment of
Prequalifica-
tion Document
8.1 At any time prior to the deadline for submission of applications, theEmployer may amend the Prequalification Document by issuingaddenda.
8.2 Any addendum issued shall be part of the Prequalification Documentand shall be communicated in writing to all who have obtained theprequalification document from the Employer.
8.3 To give prospective Applicants reasonable time to take an addenduminto account in preparing their applications, the Employer may, at itsdiscretion, extend the deadline for the submission of applications.
C. Preparation of Applications
9. Cost of
Applications
9.1 The Applicant shall bear all costs associated with the preparation andsubmission of its application. The Employer will in no case beresponsible or liable for those costs, regardless of the conduct or outcomeof the prequalification process.
10. Language of
Application
10.1 The application as well as all correspondence and documents relatingto the prequalification exchanged by the Applicant and the Employer,shall be written in the language specified in the PDS. Supportingdocuments and printed literature that are part of the application may bein another language, provided they are accompanied by an accuratetranslation of the relevant passages in the language specified in thePDS, in which case, for purposes of interpretation of the application,
the translation shall govern.
11. Documents
Comprising
the
Application
11.1 The application shall comprise the following:
(a) Application Submission Form, in accordance with ITA 12;
(b) documentary evidence establishing the Applicants eligibility toprequalify, in accordance with ITA 13;
-
8/3/2019 Prequal en 09 Sep 10
18/86
1-10 Section I. Instructions to Applicants
(c) documentary evidence establishing the Applicantsqualifications, in accordance with ITA 14; and
(d) any other document required as specified in the PDS.
12. Application
SubmissionForm
12.1 The Applicant shall prepare an Application Submission Sheet using
the form furnished in Section IV, Application Forms. This Form mustbe completed without any alteration to its format.
13. Documents
Establishing
the Eligibility
of the
Applicant
13.1 To establish its eligibility in accordance with ITA 4, the Applicantshall complete the eligibility declarations in the ApplicationSubmission Form and Forms ELI (eligibility) 1.1 and 1.2, included inSection IV, Application Forms.
14. Documents
Establishing
the
Qualificationsof the
Applicant
14.1 To establish its qualifications to perform the contract(s) in accordancewith Section III, Qualification Criteria and Requirements, theApplicant shall provide the information requested in the corresponding
Information Sheets included in Section IV, Application Forms.
15. Signing of the
Application
and Number
of Copies
15.1 The Applicant shall prepare one original of the documents comprisingthe application as described in ITA 11 and clearly mark itORIGINAL. The original of the application shall be typed or writtenin indelible ink and shall be signed by a person duly authorized to signon behalf of the Applicant.
15.2 The Applicant shall submit copies of the signed original application, inthe number specified in the PDS, and clearly mark them COPY. In
the event of any discrepancy between the original and the copies, theoriginal shall prevail
D. Submission of Applications
16. Sealing and
Identification
of
Applications
16.1 The Applicant shall enclose the original and the copies of the applicationin a sealed envelope that shall:
(a) bear the name and address of the Applicant;
(b) be addressed to the Employer, in accordance with ITA 17.1; and
(c) bear the specific identification of this prequalification processindicated in the PDS 1.1.
16.2 The Employer will accept no responsibility for not processing anyenvelope that was not identified as required.
-
8/3/2019 Prequal en 09 Sep 10
19/86
Section I. Instructions to Applicants 1-11
17. Deadline for
Submission of
Applications
17.1 Applicants may always submit their applications by mail or by hand.When so specified in the PDS, applicants shall have the option ofsubmitting their applications electronically, in accordance withelectronic application submission procedures specified in the PDS.Applications shall be received by the Employer at the address and no
later than the deadline indicated in the PDS. A receipt will be givenfor all applications submitted.
17.2 The Employer may, at its discretion, extend the deadline for thesubmission of applications by amending the PrequalificationDocument in accordance with ITA 8, in which case all rights andobligations of the Employer and the Applicants subject to the previousdeadline shall thereafter be subject to the deadline as extended.
18. Late
Applications
18.1 Any application received by the Employer after the deadline for submissionof applications prescribed in accordance with ITA 17 will be treated asindicated in the PDS.
19. Opening of
Applications
19.1 Any specific electronic application opening procedures required ifelectronic submission of applications is permitted pursuant to SubClause 17.1 shall be as specified in the PDS. Employer shall preparea record of the opening of applications that shall include, as a minimum,the name of the Applicant. A copy of the record shall be distributedto all Applicants.
E. Procedures for Evaluation of Applications
20. Confidential-
ity
20.1 Information relating to the evaluation of applications, and
recommendation for prequalification, shall not be disclosed toApplicants or any other persons not officially concerned with such process until the notification of prequalification is made to allApplicants.
20.2 From the deadline for submission of applications to the time ofnotification of the results of the prequalification in accordance withITA 28, any Applicant that wishes to contact the Employer on anymatter related to the prequalification process, may do so but only inwriting.
21. Clarification
of
Applications
21.1 To assist in the evaluation of applications, the Employer may, at itsdiscretion, ask any Applicant for a clarification of its applicationwhich shall be submitted within a stated reasonable period of time.Any request for clarification and all clarifications shall be in writing.
21.2 If an Applicant does not provide clarifications of the informationrequested by the date and time set in the Employers request forclarification, its application may be rejected.
-
8/3/2019 Prequal en 09 Sep 10
20/86
1-12 Section I. Instructions to Applicants
22. Responsive-
ness of
Applications
22.1 The Employer may reject any application which is not responsive tothe requirements of the prequalification document.
23. Domestic
Bidder Price
Preference
23.1 Unless otherwise specified in the PDS, a margin of preference fordomestic bidders shall not apply in the bidding processresulting from
this prequalification.
24. Subcontrac-
tors
24.1 Applicants planning to subcontract any of the key activities indicatedin Section III, Qualification Criteria, shall specify the activity(ies) orparts of the works to be subcontracted in the Application SubmissionForm. Applicants shall clearly identify the proposed specialistsubcontractors in Forms ELI-1.2 and EXP (experience)-4.2(b) inSection IV. Such proposed specialist subcontractor(s) shall meet thecorresponding qualification requirements specified in Section III,Qualification Criteria and Requirements.
24.2 At this time, the Employer does not intend to execute certain specific
parts of the Works by subcontractors selected in advance by theEmployer (Nominated Subcontractors) unless otherwise stated in thePDS.
F. Evaluation of Applications and Prequalification of
Applicants
25. Evaluation of
Applications
25.1 The Employer shall use the factors, methods, criteria, andrequirements defined in Section III, Qualification Criteria andRequirements to evaluate the qualifications of the Applicants. The useof other methods, criteria, or requirements shall not be permitted. The
Employer reserves the right to waive minor deviations in thequalification criteria if they do not materially affect the capability of anApplicant to perform the contract.
25.2 Only the qualifications of subcontractors that have been identified inthe application may be considered in the evaluation of an Applicant.However, the general experience and financial resources ofsubcontractors may not be added to those of the Applicant for purposesof prequalification of the Applicant.
25.3 In case of multiple contracts, the Employer shall prequalify each
Applicant for the maximum number and types of contracts for whichthe Applicant meets the appropriate aggregate requirements of suchcontracts, as specified in Section III, Qualification Criteria andRequirements.
26. Employers
Right to
Accept or
Reject
26.1 The Employer reserves the right to accept or reject any application,and to annul the prequalification process and reject all applications atany time, without thereby incurring any liability to Applicants.
-
8/3/2019 Prequal en 09 Sep 10
21/86
Section I. Instructions to Applicants 1-13
Applications
27. Prequalifica-
tion of
Applicants
27.1 All Applicants whose applications have met or exceeded (passed)the specified threshold requirements will, to the exclusion of all others,be prequalified by the Employer.
28. Notification ofPrequalifica-
tion
28.1 Once the Employer has completed the evaluation of the applications itshall notify all Applicants in writing of the names of those applicantswho have been prequalified.
29. Invitation to
Bid
29.1 Promptly after the notification of the results of the prequalification theEmployer shall invite bids from all the Applicants that have beenprequalified.
29.2 Bidders may be required to provide a Bid Security or a Bid SecuringDeclaration acceptable to the Employer in the form and an amount tobe specified in the Bidding Documents, and the successful Bidder shallbe required to provide a Performance Security to be specified in theBidding Documents.
30. Changes in
Qualifications
of Applicants
30.1 Any change in the structure or formation of an Applicant after beingprequalified in accordance with ITA 27 and invited to bid shall besubject to a written approval of the Employer prior to the deadline forsubmission of bids. Such approval shall be denied if as a consequenceof the change the Applicant no longer substantially meets thequalification criteria set forth in Section III, Qualification Criteria andRequirements, or if in the opinion of the Employer, a substantialreduction in competition may result. Any such changes shall besubmitted to the Employer not later than 14 days after the date of the
Invitation for Bids.
-
8/3/2019 Prequal en 09 Sep 10
22/86
1-14
Section II. Prequalification Data Sheet
A. General
ITA 1.1 The Employer is: : [ insert full name, including name of Project Officer, andaddress]
ITA 1.1 The list of contracts is: [insert number, names and identification numbers]
ITA 1.1 ICB name and number are: [insert name and identification number]
ITA 2.1 The name of the Borrower is: [insert name of Borrower ]
ITA 2.1 The name of the Project is: [insert name of Project]
ITA 4.1 (i) The parties in a JV [insert shall or shall not]be jointly and severallyliable.
(ii) Maximum number of partners in the JV shall be: [insert a number or insertnot limited]
ITA 4.7 The electronic address of firms debarred by the Bank is:http://www.worldbank.org/debarr.
B. Contents of the Prequalification Document
http://www.worldbank.org/debarr.http://www.worldbank.org/debarr. -
8/3/2019 Prequal en 09 Sep 10
23/86
Section II. Prequalification Data Sheet 1-15
ITA 7.1 Forclarification purposes, the Employer's address is:
[insert information _or state same as in 1.1 above]
Attention: [insert name and room number of Project Officer]
Address: [insert street name and number]
[insert floor and room number, if applicable]
City: [insert name of city or town]
ZIP Code: [insert postal (ZIP) code, if applicable]
Country: [insert name of country]]
Telephone: [insert telephone number including country and city codes]
Facsimile number: [insert fax number including country and city codes]
Electronic mail address: [insert e-mail address of Project Officer]
C. Preparation of Applications
ITA 10.1 The language of the application as well as of all correspondence is: [InsertEnglish or Spanish or French].
[Note:In Countries that the Bank has agreed with the Borrower that in additionto one internationally used language, applications may be also issued in thelanguage of the Borrower's Country (or the language used nation-wide in theBorrower's Country for commercial transactions), the following text shall be
added]:
In addition to the above indicated language, this Prequalification Documenthas been also issued in [the following language [insert the language of theBorrower's Country or the language used nation-wide in the Borrower'sCountry for commercial transactions].
Applicants are permitted, at their choice, to submit their applications in eitherone of the two languages above indicated. Applicants shall not submitapplications in more than one language.]
ITA 11.1 (d) The Applicant shall submit with its application, the following additional
documents: [insert list of additional documents, if any]
ITA 15.2 In addition to the original, the number of copies to be submitted with theapplication is: [insert number of copies]
D. Submission of Applications
ITA 17.1 Applicants [insert shall or shall not] have the option of submitting their
-
8/3/2019 Prequal en 09 Sep 10
24/86
1-16 Section II. Prequalification Data Sheet
applications electronically.
If electronic submission of applications shall be permitted, the electronicapplication submission procedures shall be: [insert description of theprocedures]
Forapplication submission purposes only, the Employer's address is:
[insert information requested below or insert Employers address is the sameas that indicated in 1.1]
Attention: [insert name and room number of Project Officer]
Address: [insert street name and number]
[insert floor and room number, if applicable]
City: [insert name of city or town]
ZIP Code: [insert postal (ZIP) code, if applicable]
Country: [insert name of country]
Telephone: [insert telephone number including country and city codes]
Facsimile number: [insert fax number including country and city codes]
Electronic mail address: [insert e-mail address of Project Officer]
The deadline for application submission is:
Date: [insert date]
Time: [insert time]
[The time allowed for preparation and submission of the prequalificationdocument should be sufficient for applicants to gather all the informationrequiredpreferably eight weeks, but in any case not less than six weeks afterthe dates when the documents are available for distribution or the date of theadvertisement. This period may be longer for very large projects, where timeshould be allowed for the formation of joint ventures and assembly of thenecessary resources.]
ITA 18.1 [Choose one of the two options below:]
Late applications will be returned unopened to the Applicants.
[or]
The Employer reserves the right to accept or reject late applications.
-
8/3/2019 Prequal en 09 Sep 10
25/86
-
8/3/2019 Prequal en 09 Sep 10
26/86
1-18
Section III. Qualification Criteria and
Requirements
This Section contains all the methods, criteria, and requirements that the Employer shall use toevaluate applications. The information to be provided in relation to each requirement and thedefinitions of the corresponding terms are included in the respective Application Forms.
Contents
1. Eligibility..................................................................................................................................19
2. Historical Contract Non-Performance..................................................................................19
3. Financial Situation...................................................................................................................20
4. Experience................................................................................................................................21
1. Eligibility..................................................................................................................................15
2. Historical Contract Non-Performance..................................................................................16
Number of years should usually be one or two.........................................................................17
3. Financial Situation...................................................................................................................17
The amount stated should normally not be less than twice the estimated annual turnover in
the proposed Works contract (based on a straight-line projection of the Employers
estimated cost, including contingencies, over the contract duration). The multiplier of 2
may be reduced for very large contracts (say, greater than US$200 million equivalent) but
should not be less than 1.5.*........................................................................................................18
The time period is normally five years or more, but may be reduced to not less than three
years (in agreement with the Bank) under special country circumstances, such as to
provide opportunities for a newly privatized construction industry with only a short record
of experience, etc. ........................................................................................................................18
An asterix(*) means that some information on the mater is provided in III.2 Guidance
Notes..............................................................................................................................................18
4. Experience................................................................................................................................18
-
8/3/2019 Prequal en 09 Sep 10
27/86
Section III. Qualification Criteria and Requirements 1-19
Eligibility and Qualification Criteria Compliance Requirements Documentation
No. Subject Requirement Single EntityJoint Venture
Submission
Requirements
All PartiesCombined
Each Partner One Partner
1. Eligibility1.1 Nationality Nationality in accordance
with ITA Sub-Clause 4.2Must meetrequirement
Existing orintended JVmust meet
requirement
Must meetrequirement
N/A Forms ELI 1.1and 1.2, withattachments
1.2 Conflict ofInterest
No conflicts of interest inITA Sub-Clause 4.4
Must meetrequirement
Existing orintended JVmust meetrequirement
Must meetrequirement
N/A ApplicationSubmissionForm
1.3 BankIneligibility
Not having been declaredineligible by the Bank, asdescribed in ITA Sub-Clause 4.7
Must meetrequirement
Existing JVmust meetrequirement
Must meetrequirement
N/A ApplicationSubmissionForm
1.4 GovernmentOwned Entity
Applicant required to meetconditions of ITA Sub-Clause 4.8
Must meetrequirement
Must meetrequirement
Must meetrequirement
N/A Forms ELI 1.1and 1.2, withattachments
1.5 United Nationsresolution orBorrowerscountry law
Not having been excludedas a result of theBorrowers country laws orofficial regulations, or by anact of compliance with UN
Security Council resolution,in accordance with ITA4.11
Must meetrequirement
Must meetrequirement
Must meetrequirement
N/A Forms ELI 1.1and 1.2, withattachments
2. Historical Contract Non-Performance2.1 History of Non-
PerformingContracts
Non-performance of acontract did not occurwithin the last [insertnumber]years prior to thedeadline for applicationsubmission based on allinformation on fully settleddisputes or litigation. A fully
Must meetrequirement byitself or aspartner to pastor existing JV
N/A Must meetrequirement byitself or aspartner to pastor existing JV
N/A Form CON-2
-
8/3/2019 Prequal en 09 Sep 10
28/86
1-20 Section III. Qualification Criteria and Requirements
Eligibility and Qualification Criteria Compliance Requirements Documentation
No. Subject Requirement Single EntityJoint Venture
SubmissionAll PartiesCombined
Each Partner One Partner
settled dispute or litigationis one that has beenresolved in accordancewith the Dispute ResolutionMechanism under the
respective contract andwhere all appeal instancesavailable to the applicanthave been exhausted.
2.2 Failure to SignContract
Not being under executionof a Bid SecuringDeclaration pursuant toSub-Clause 4.9 for[insertnumber]years
Must meetrequirement
Must meetrequirement
Must meetrequirement
N/A ApplicationSubmissionForm
2.3 PendingLitigation
All pending litigation shallin total not represent morethan [insert number]%,[insert percentage inwords]of the Applicantsnet worth and shall betreated as resolved againstthe Applicant
Must meetrequirement byitself or as apartner to pastor existing JV
N/A Must meetrequirement byitself or as apartner to pastor existing JV
N/A Form CON 2
3. Financial Situation3.1 Financial
PerformanceSubmission of auditedbalance sheets or if notrequired by the law of theApplicants country, otherfinancial statementsacceptable to theEmployer, for the last[insert number]years todemonstrate:
Must meetrequirement
N/A Must meetrequirement
N/A Form FIN 3.1withattachments
(a) the current soundnessof the applicants financial
(a) Must meetrequirement
(a) N/A (a) Must meetrequirement
(a) N/A
-
8/3/2019 Prequal en 09 Sep 10
29/86
Section III. Qualification Criteria and Requirements 1-21
Eligibility and Qualification Criteria Compliance Requirements Documentation
No. Subject Requirement Single EntityJoint Venture
SubmissionAll PartiesCombined
Each Partner One Partner
position and its prospectivelong term profitability, and(b) capacity to have a cashflow amount of US$ [insertnumber]equivalent
(b) Must meetrequirement
(b) Must meetrequirement
(b) N/A (b) N/A
3.2 AverageAnnualConstructionTurnover
Minimum average annualconstruction turnover ofUS$ [insert amount in US$equivalent in words andfigures], calculated as totalcertified payments receivedfor contracts in progress orcompleted, within the last[insert number]years,[insert number in words]years
Must meetrequirement
Must meetrequirement
Must meet[insert number]%, [insert
percentage inwords]of therequirement
Must meet[insert number]%, [insert
percentage inwords]of therequirement
Form FIN 3.2
4. Experience4.1 General
ConstructionExperience
Experience underconstruction contracts inthe role of contractor,subcontractor, ormanagement contractor for
at least the last [insertnumber]years prior to theapplication submissiondeadline, and with activityin at least nine (9) monthsin each year.
Must meetrequirement
N/A Must meetrequirement
N/A Form EXP 4.1
4.2(a)
SpecificConstructionExperience
Participation as contractor,management contractor orsubcontractor, in at least[insert number]contractswithin the last [insertnumber]years, each with a
Must meetrequirement
Must meetrequirement
N/A Must meetrequire for onecontract (canbe a specialistsubcontractor
Form EXP4.2(a)
-
8/3/2019 Prequal en 09 Sep 10
30/86
1-22 Section III. Qualification Criteria and Requirements
Eligibility and Qualification Criteria Compliance Requirements Documentation
No. Subject Requirement Single EntityJoint Venture
SubmissionAll PartiesCombined
Each Partner One Partner
value of at least [insertamount], that have beensuccessfully andsubstantially completedand that are similar to the
proposed works. Thesimilarity shall be based onthe physical size,complexity,methods/technology orother characteristics asdescribed in Section VI,Scope of Works
4.2(b)
For the above or othercontracts executed duringthe period stipulated in 4.2(a) above, a minimumconstruction experience inthe following key activities:[list activities]
Must meetrequirements
Must meetrequirements
N/A Must meet thefollowingrequirementsfor the keyactivities listedbelow (can be aspecialistsubcontractor)[list key
activities forthis partner andthecorrespondingminimumrequirements]
Form EXP 4.2(b)
-
8/3/2019 Prequal en 09 Sep 10
31/86
Section IV. Application Forms 1-23
Section IV. Application Forms
Table of Forms
Application Submission Form....................................................................................................24
Applicant Information Form......................................................................................................26
Applicant's Party Information Form.........................................................................................27
Historical Contract Non-Performance......................................................................................28
Financial Situation.......................................................................................................................30
Average Annual Construction Turnover...................................................................................32
General Construction Experience..............................................................................................33
Similar Construction Experience...............................................................................................34
Construction Experience in Key Activities................................................................................36
-
8/3/2019 Prequal en 09 Sep 10
32/86
1-24 Section IV. Application Forms
Application Submission Form
Date: [insert day, month, year]ICB No. and title: [insert ICB number and title]
To: [insert full name of Employer]
We, the undersigned, apply to be prequalified for the referenced ICB and declare that:
(a) we have examined and have no reservations to the Prequalification Documents, includingAddendum(s) No(s)., issued in accordance with Instructions to Applicants (ITA) Clause 8:[insert the number and issuing date of each addendum].
(b) we, including any subcontractors or suppliers for any part of the contract resulting fromthis prequalification process, have nationalities from eligible countries, in accordance with
ITA Sub-Clause 4.2: [insert the nationality of the Applicant, including that of all partnersin case of a Joint Venture, and the nationality of each already identified subcontractor andsupplier of related services, if applicable];
(c) we, including any subcontractors or suppliers for any part of the contract resulting fromthis prequalification, do not have any conflict of interest, in accordance with ITA Sub-Clause 4.4;
(d) we, including any subcontractors or suppliers for any part of the contract resulting from thisprequalification, have not been declared ineligible by the Bank, or under the Employer's countrylaws, official regulations, or under execution of a Bid Securing Declaration in the Employer'sCountry, or by an act of compliance with a decision of the United Nations Security Council, inaccordance with ITA Sub-Clauses 4.7, 4.9 and 4.11;
(e) [insert either "we are not a Government owned entity" or "we are a Government entity,and we meet the requirements of ITA Sub-Clause 4.8];
(f) we, in accordance with ITA Sub-Clause 24.1, plan to subcontract the following keyactivities and/or parts of the works:
[insert any of the key activities identified in Section III- 4.2 (b) which the Applicant intendsto subcontract]
(g) we declare that the following commissions, gratuities, or fees have been paid or are to be
paid with respect to the prequalification process, the corresponding bidding process orexecution of the Contract:
-
8/3/2019 Prequal en 09 Sep 10
33/86
Section IV. Application Forms 1-25
Name of Recipient Address Reason Amount
[insert full name foreach occurrence]
[insert street/number/city/country]
[indicate reason] [specify amount inUS$ equivalent]
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
[If none has been paid or is to be paid, indicate none.]
(h) We understand that you may cancel the prequalification process at any time and that you areneither bound to accept any application that you may receive nor to invite the prequalifiedapplicants to bid for the contract subject of this prequalification, without incurring any liability
to the Applicants, in accordance with ITA Clause 26.
Signed [insert signature(s) of an authorized representative(s) of the Applicant ]
Name [insert full name of person signing the application]
In the Capacity of[insert capacity of person signing the application]
Duly authorized to sign the application for and on behalf of:
Applicants Name [insert full name of Applicant] Address [insert
street number/town or city/country address]
Dated on [insert day number] day of[insert month], [insert year]
-
8/3/2019 Prequal en 09 Sep 10
34/86
1-26 Section IV. Application Forms
Form ELI -1.1
Applicant Information Form
Date: [insert day, month, year]ICB No. and title: [insert ICB number and title]
Page [insert page number] of[insert total number] pages
Applicant's legal name
[insert full legal name]
In case of Joint Venture (JV), legal name of each partner:
[insert full legal name of each partner in JV]
Applicant's Actual or Intended country of constitution:
[indicate country of Constitution]
Applicant's actual or Intended year of constitution:
[indicate year of Constitution]
Applicant's legal address in country of constitution:
[insert street/ number/ town or city/ country]
Applicant's authorized representative information
Name: [insert full legal name]
Address: [insert street/ number/ town or city/ country]
Telephone/Fax numbers: [insert telephone/fax numbers, including country and city codes]
E-mail address: [indicate e-mail address]
Attached are copies of original documents of
Articles of Incorporation or Documents of Constitution, and documents of registration of thelegal entity named above, in accordance with ITA 4.2.
In case of JV, letter of intent to form JV or JV agreement, in accordance with ITA 4.1.
In case of Government owned entity, documents establishing legal and financial autonomy
and compliance with commercial law, in accordance with ITA 4.8.
-
8/3/2019 Prequal en 09 Sep 10
35/86
Section IV. Application Forms 1-27
Form ELI -1.2
Applicant's Party Information Form
[The following form shall be filled in for the Applicant's parties including partner(s) of a joint venture,subcontractors, suppliers and other parties]
Date: [insert day, month, year]ICB No. and title: [insert ICB number and title]
Page [insert page number] of[insert total number]pages
JV applicant legal name:
[insert full legal name]
Applicant's Party legal name:
[insert full legal name of Applicant's Party]
Applicant's Party country of registration:
[indicate country of registration]
Applicant Party's year of constitution:
[indicate year of constitution]
Applicant Party's legal address in country of constitution:
[insert street/ number/ town or city/ country]
Applicant Party's authorized representative information
Name: [insert full legal name]
Address: [insert street/ number/ town or city/ country]
Telephone/Fax numbers: [insert telephone/fax numbers, including country and city codes]
E-mail address: [indicate e-mail address]
Attached are copies of original documents of
Articles of Incorporation or Documents of Constitution, and Registration Documents of the legal entitynamed above, in accordance with ITA 4.2.
In case of a Government owned entity, documents establishing legal and financial autonomy andcompliance with commercial law, in accordance with ITA 4.8.
-
8/3/2019 Prequal en 09 Sep 10
36/86
-
8/3/2019 Prequal en 09 Sep 10
37/86
Section IV. Application Forms 1-29
Year Outcome as
Percentage
of Total
Assets
Contract Identification Total Contract
Amount
(current value,
US$
equivalent)
[insertyear]
[insertpercentage]
Contract Identification: [indicate completecontract name, number, and any otheridentification]Name of Employer: [insert full name]Address of Employer: [insert street/city/country]Matter in dispute: [indicate main issues indispute]
[insert amount]
-
8/3/2019 Prequal en 09 Sep 10
38/86
1-30 Section IV. Application Forms
Form FIN 3.1
Financial Situation
[The following table shall be filled in for the Applicant and for each partner of a Joint Venture]
Applicants Legal Name: [insert full name] Date: [insert day, month, year]Applicants Party Legal Name:[insert full name]ICB No. and title: [insert ICB number and title]
Page [insert page number] of[insert total number]pages
1. Financial data
Financial information in
(US$ equivalent in 000s)
Historic information for previous_[insert number] years,[insert in words]
(US$ equivalent in 000s)
Year 1 Year 2 Year 3 Year Year n
Information from Balance Sheet
Total Assets (TA)
Total Liabilities (TL)
Net Worth (NW)
Current Assets (CA)
Current Liabilities (CL)
Information from Income Statement
Total Revenue (TR)
Profits Before Taxes (PBT)
-
8/3/2019 Prequal en 09 Sep 10
39/86
Section IV. Application Forms 1-31
2. Financial documents
The Applicant and its parties shall provide copies of the balance sheets and/or financial statements for[number] years pursuant Section III, Qualifications Criteria and Requirements, Sub-factor 3.1. Thefinancial statements shall:
(a) reflect the financial situation of the Applicant or partner to a JV, and not sister or parentcompanies.
(b) be audited by a certified accountant.
(c) be complete, including all notes to the financial statements.
(d) correspond to accounting periods already completed and audited (no statements for partialperiods shall be requested or accepted).
Attached are copies of financial statements (balance sheets, including all related notes, and incomestatements) for the [number] years required above; and complying with the requirements
-
8/3/2019 Prequal en 09 Sep 10
40/86
1-32 Section IV. Application Forms
Form FIN - 3.2
Average Annual Construction Turnover
[The following table shall be filled in for the Applicant and for each partner of a Joint Venture]
Applicant's/Joint Venture Partner's Legal Name: [insert full name]Date: [insert day, month, year]
Applicant's Party Legal Name: [insert full name]ICB No. and title: [insert ICB number and title]
Page [insert page number] of[insert total number]pages
Annual turnover data (construction only)
Year Amount and Currency US$ equivalent
[indicate year] [insert amount and indicate currency] [insert amount in US$ equiv.]
AverageAnnual
ConstructionTurnover *
* Average annual construction turnover calculated as total certified payments received for workin progress or completed, divided by the number of years specified in Section III,Qualification Criteria and Requirements, Sub-Factor 3.2.
-
8/3/2019 Prequal en 09 Sep 10
41/86
Section IV. Application Forms 1-33
Form EXP - 4.1
General Construction Experience
[The following table shall be filled in for the Applicant and for each partner of a Joint Venture]
Applicant's/Joint Venture Partner's Legal Name: [insert full name]Date: [insert day, month, year]
Applicant JV Party Legal Name: [insert full name]ICB No. and title: [insert ICB number]
Page [insert page number] of[insert total number]pages
[Identify contracts that demonstrate continuous construction work over the past [number] yearspursuant to Section III, Qualification Criteria and Requirements, Sub-Factor 4.1.List contractschronologically, according to their commencement (starting) dates.]
StartingMonth /
Year
EndingMonth /
Year
Contract Identification Role of Applicant
[indicatemonth/year]
[indicatemonth/year]
Contract name: [insert full name]Brief Description of the Works performed by theApplicant: [describe works performed briefly]Amount of contract: [insert amount in US$equivalent]Name of Employer: [indicate full name]
Address: [indicate street/number/town orcity/country]
[insert"Contractor or
"Subcontractor or"Contract
Manager]
Contract name: [insert full name]Brief Description of the Works performed by theApplicant: [describe works performed briefly]Amount of contract: [insert amount in US$equivalent]Name of Employer: [indicate full name]
Address: [indicate street/number/town orcity/country]
[insert"Contractor or
"Subcontractor or"Contract
Manager]
Contract name: [insert full name]
Brief Description of the Works performed by theApplicant: [describe works performed briefly]Amount of contract: [insert amount in US$equivalent]Name of Employer: [indicate full name]
Address: [indicate street/number/town orcity/country]
[insert
"Contractor or"Subcontractor or
"ContractManager]
-
8/3/2019 Prequal en 09 Sep 10
42/86
1-34 Section IV. Application Forms
Form EXP - 4.2(a)
Similar Construction Experience
[The following table shall be filled in for contracts performed by the Applicant, each partnerof a Joint Venture, and specialist sub contractors]
Applicant's/Joint Venture Partner's Legal Name: [insert full name]Date: [insert day, month, year]
JV Party Name: [insert full name]ICB No. and title: [insert ICB number and title]
Page [insert page number] of[insert total number]pages
Similar Contract No.
[insert number] of[insert numberof similar contracts required]
Information
Contract Identification [insert contract name and number, if applicable]
Award date [insert day, month, year, i. e., 15 June, 2015]
Completion date [insert day, month, year, i.e., 03 October, 2017]
Role in Contract[check the appropriate box]
Contractor
ManagementContractor
Subcontractor
Total Contract Amount [insert total contract amount in localcurrency]
US$ [inserttotal contractamount in US$equivalent]
If partner in a JV, or subcontractor,specify participation in totalcontract amount
[insert apercentageamount]
[insert totalcontract amount inlocal currency]
[insert totalcontract amountin US$equivalent]
Employer's Name: [insert full name]
Address:
Telephone/fax number
E-mail:
[indicate street / number / town or city / country]
[insert telephone/fax numbers, including country andcity area codes]
[insert e-mail address, if available]
-
8/3/2019 Prequal en 09 Sep 10
43/86
Section IV. Application Forms 1-35
Form EXP - 4.2(a) (cont.)
Similar Construction Experience (cont.)
Similar Contract No.
[insert number] of[insert numberof similar contracts required]
Information
Description of the similarity inaccordance with Sub-Factor 4.2(a)of Section III:
1. Amount[insert amount in US$ in words and inFigures]
2. Physical size[insert physical size of activities]
3. Complexity[insert description of complexity]
4. Methods/Technology [insert specific aspects of the methods/technologyinvolved in the contract]
5. Other Characteristics[insert other characteristics as described in Section V,Scope of Works]
-
8/3/2019 Prequal en 09 Sep 10
44/86
1-36 Section IV. Application Forms
Form EXP - 4.2(b)
Construction Experience in Key Activities
Applicant's Legal Name: [insert full name]Date: [insert day, month, year]
Applicant's Party Legal Name: [insert full name]Nominated Subcontractor's Legal Name (as per ITA 24.2): [insert full name]
ICB No. and title: [insert ICB number and title]
Page [insert page number] of[insert total number]pages
All Subcontractors for key activities must complete the information in this form as per ITA 24.2and Section III, Qualification Criteria and Requirements, Sub-Factor 4.2.
1. Key Activity No One: [insert brief description of the Activity, emphasizing itsspecificity]
Information
Contract Identification [insert contract name and number, if applicable]
Award date [insert day, month, year, i. e., 15 June, 2015]
Completion date [insert day, month, year, i.e., 03 October, 2017]
Role in Contract[check the appropriate box]
Contractor
ManagementContractor
Subcontractor
Total Contract Amount[insert total contract amount inlocal currency]
US$ [insert Totalcontract amountin US$equivalent]
If party in a JV, specify participationof total contract amount
[insert apercentage
amount
[insert totalcontract amount
in local currency]
[insert totalcontract amount
in US$
equivalent]
-
8/3/2019 Prequal en 09 Sep 10
45/86
Section IV. Application Forms 1-37
Information
Employers Name: [insert full name]
Address:
Telephone/fax number
E-mail:
[indicate street / number / town or city / country]
[insert telephone/fax numbers, including country andcity area codes]
[insert e-mail address, if available]
2. Activity No Two
3.
Information
Description of the key activities inaccordance with Sub-Factor 4.2(b) ofSection III:
[insert response to inquiry indicated in leftcolumn]
-
8/3/2019 Prequal en 09 Sep 10
46/86
1-38
Section V. Eligible Countries
Eligibility for the Provision of Goods, Works and Services in Bank-Financed
Procurement
1. In accordance with Para 1.8 of the Guidelines: Procurement under IBRD Loans and IDACredits, dated May 2004, the Bank permits firms and individuals from all countries to offer goods,works and services for Bank-financed projects. As an exception, firms of a Country or goodsmanufactured in a Country may be excluded if:
Para 1.8 (a) (i): as a matter of law or official regulation, the Borrowers Country prohibitscommercial relations with that Country, provided that the Bank is satisfied that suchexclusion does not preclude effective competition for the supply of the Goods orWorks required, or
Para 1.8 (a) (ii): by an Act of Compliance with a Decision of the United Nations SecurityCouncil taken under Chapter VII of the Charter of the United Nations, theBorrowers Country prohibits any import of goods from that Country or anypayments to persons or entities in that Country.
2. For the information of borrowers and bidders, at the present time firms, goods and servicesfrom the following countries are excluded from this bidding:
(a) With reference to paragraph 1.8 (a) (i) of the Guidelines:
[insert list of countries prohibited under official regulations of the country]
(b) With reference to paragraph 1.8 (a) (ii) of the Guidelines:
[insert list of countries which are banned under UN Security Council Chapter VII]
-
8/3/2019 Prequal en 09 Sep 10
47/86
2-1
PART 2 Works Requirements
-
8/3/2019 Prequal en 09 Sep 10
48/86
2-2
Section VI. Scope of Works
Contents
1. Description of the Works..........................................................................................................3
2. Construction Period...................................................................................................................4
3. Site and Other Data...................................................................................................................5
-
8/3/2019 Prequal en 09 Sep 10
49/86
Section VI. Scope of Works 2-3
1. Description of the Works
-
8/3/2019 Prequal en 09 Sep 10
50/86
2-4 Section VI. Scope of Works
2. Construction Period
-
8/3/2019 Prequal en 09 Sep 10
51/86
Section VI. Scope of Works 2-5
3. Site and Other Data
-
8/3/2019 Prequal en 09 Sep 10
52/86
1
STANDARD PROCUREMENT DOCUMENTS
Users Guidefor
Prequalification Document
for
Procurement of Works
-
8/3/2019 Prequal en 09 Sep 10
53/86
2 Users Guide Introduction
Introduction
The Standard Prequalification Document for Procurement of Works (SPD) and Users Guide havebeen designed to: (i) simplify the Employers preparation of a specific Prequalification Document
(PQD) for Procurement of Works; (ii) reduce the Applicants preparation time and effort; and (iii)facilitate and simplify the Employers evaluation of applications; and (iv) minimize the Banks timerequired for the prior review of the PQD
The purpose of the Users Guide (the Guide) is to provide guidance to Employers on how to prepareprequalification documents for works based on the standard procurement document. In addition theGuide includes guidance on how to prepare the Invitation for Prequalification (IFP). Theprovisions in Section I, Instructions to Applicants (ITA) of the SPD must be used without anymodification to its text or format. Any data and provisions that this section requires for a specificprequalification shall be included in Section II, Prequalification Data Sheet.
The remaining sections of the SPD, which are also explained in the Guide are: Section III,
Qualification Criteria and Requirements; Section IV, Application Forms; and Section VI,Scope of Works.
At the end of each section of the Guide, Guidance Notes for Users, explain the rationale forcertain clauses of the SPD, and provide guidance to executing agencies and their consultants inpreparing a particular prequalification questionnaire and evaluating the submissions of applicants.The last section of this Guide provides guidance on the evaluation of applications.
Procurement under projects financed by the International Bank for Reconstruction andDevelopment and the International Development Association (hereinafter interchangeably calledthe Bank) is carried out in accordance with policies and procedures laid down in the Banks
Guidelines: Procurement under IBRD Loans and IDA Credits, hereinafter referred to as theGuidelines.
The Standard Prequalification Document in this publication has been prepared for use by theBanks Borrowers and their implementing agencies in the procurement of works primarily throughInternational Competitive Bidding (ICB), but the principles may also be applied if prequalificationis needed under National Competitive Bidding (NCB). The procedures presented are based ongood international practice, and are in compliance with the Banks Guidelines.
When ICB is the appropriate method for procurement, the use of the Banks Standard BiddingDocuments (SBDs) is mandatory. For large Works (customarily regarded as more than US$10million equivalent) or complex Works, prequalification is usually necessary; to be used under a
project, however, prequalification needs to be mandated in the Loan/Credit Agreement.Accordingly, the Banks SBD for the Procurement of Works has been prepared on the basis thatprequalification, in accordance with this document, will have taken place prior to bidding. TheBank has also issued an SBD for smaller contracts (normally less than US$10 million and/orsimple Works), for which prequalification is optional; if, however, prequalification is required, itshould be carried out in accordance with this document.
-
8/3/2019 Prequal en 09 Sep 10
54/86
Introduction Users Guide 3
Contents
Acronyms & Abbreviations..........................................................................................................4
Glossary..........................................................................................................................................5
Why Prequalification?...................................................................................................................7
The Prequalification Process........................................................................................................9
Section I. Instructions to Applicants (ITA)...............................................................................11
Section II. Prequalification Data Sheet (PDS)..........................................................................12
Section III. Qualification Criteria and Requirements..............................................................15
Section IV. Application Forms...................................................................................................23
Section V. Eligible Countries......................................................................................................24
Section VI. Scope of Works.........................................................................................................25
Section VII. Evaluation of Applications....................................................................................26
Invitation for Prequalification....................................................................................................33
-
8/3/2019 Prequal en 09 Sep 10
55/86
4 Users Guide Introduction
Acronyms & Abbreviations
PDS Prequalification Data Sheet
FIDIC Federation Internationale des Ingnieurs-Conseils; an association based in Switzerlandthat produces Conditions of Contract for different classes of works construction.
ICB International Competitive Bidding
IFB Invitation for Bids
IFP Invitation for Prequalification
ITA Instructions to Applicants
JV Joint Venture
NCB National Competitive Bidding
PQ Prequalification
PQD Prequalification Document
SBD Standard Bidding Documents
SPD Standard Prequalification Document
-
8/3/2019 Prequal en 09 Sep 10
56/86
Introduction Users Guide 5
Glossary
Employer One of the two parties to a works contract, the other party being the
Contractor.
Contractor The legal entity that is party to and performs a works contract, the otherparty to the contract being the Employer.
joint venture An ad hoc association of firms that pool their resources and skills toundertake a large or complex contract in the role of Contractor, with allfirms (partners in the JV) being legally liable, jointly and severally, for theexecution of the contract in the event of a partners withdrawal.
managementcontractor
A firm, acting in the role of Contractor, that does not normally usuallyperform contract construction work directly, but manages the work of other
(sub) contractors, while bearing full responsibility and risk for price,quality, and timely performance of the work contract.
constructionmanager
A consultant, acting as agent of the Borrower/Employer, engaged tocoordinate and monitor the timing of preparation, bidding award, andexecution of a number of different contracts comprising a project, but doesnot take on the responsibility for price, quality, or performance of thosecontracts.
nominated A specialist enterprise selected and approved by the Employer to
subcontractor Provide prespecified works included in the Bill of Quantities and
nominated as subcontractor to the main Contractor for such purpose.
postqualification An assessment made by the Employer after the evaluation of bids andimmediately prior to award of contract, to ensure that the lowest-evaluated,responsive, eligible Bidder is qualified to perform the contract inaccordance with previously specified prequalification requirements.
prequalification An assessment made by the Employer before inviting bids, of theappropriate level of experience and capacity of firms expressing interest inundertaking a particular contract, before inviting them to bid.
prime contractor A firm that performs a substantial part of a contract construction workitself and the balance, if any, by subcontractors, while bearing fullresponsibility for the whole contract.
provisional sum A sum included provisionally in the Bill of Quantities of a contract,normally for a specialized part of the Works or for contingencies, whichsum shall be used only on the instructions of the Employer/Engineer forpayments to the contractor and/or to nominated subcontractors.
-
8/3/2019 Prequal en 09 Sep 10
57/86
6 Users Guide Introduction
slice and package A procedure whereby a large homogeneous project is sliced into smallersimilar contracts, which are bid simultaneously so as to attract the interestof both small and large firms; firms offer bids on individual contracts(slices) or on a group of similar contracts (packages), and award is made tothe combination of bids offering the lowest cost to the Employer. Slices
comprising a number of similar construction units together in a small areaare sometimes referred to as lots, which are bid concurrently with othersimilar lots as part of the larger package.
turnover The gross earnings of a firm (in this context, a construction contractor),defined as the billings for contract work in progress and/or completed,normally expressed on an annual basis, and excluding income from othersources.
Works The total work involvement in a construction contract, including thePermanent Works or finished product as specified, and the TemporaryWorks required in by the Contractor for the execution and completion of
the contract.
In writing For the purpose of this document, means authenticated handwritten, typed,or printed; a document prepared in writing can be transmitted by telex,electronic mail, facsimile, with proof of receipt; and in the form requestedby the sender.
-
8/3/2019 Prequal en 09 Sep 10
58/86
-
8/3/2019 Prequal en 09 Sep 10
59/86
8 Users Guide Why Prequalification
the contract and, in the event that only a limited number of applications are received, tomake any necessary adjustments in the procurement process (including, in particular, thespecial conditions of contractsharing of risk, payment terms, liquidated damages, orcompletion times, which may be perceived as onerous by potential bidders);
(d) it helps to expose potential conflicts of interest by identifying contractors who may have abusiness association with consultants to the project;
(e) it reduces the amount of work and time involved by Employers in evaluating bids fromunqualified contractors;
(f) it encourages local firms to form joint ventures with other local or international firms,thereby benefiting from their resources and experience;
(g) it enables the Employer to assess the likelihood of contractors eligibility for domesticbidder price preference in borrowing countries where this is applicable; and
(h) it reduces significantly, if not eliminates, problems of rejection associated with low-priced
bids submitted by bidders of doubtful capability; and.
(i) it gives the Bank some indication of an Employers ability to manage an important, earlyprocurement function.
Disadvantages of Prequalification
5. On the negative side, prequalification has some potential disadvantages:
(a) it may increase procurement lead time, although this can be minimized by goodprocurement scheduling, e.g., undertaking the prequalification process while BiddingDocuments are being prepared;
(b) the Borrower is required to review all prequalification applications, whereaspostqualification requires the review of the qualifications of, normally, only one (thelowest evaluated) bidder;
(c) collusion (and the possibility of price-rigging) is easier among a limited number ofidentified bidders, particularly if they are of the same nationality;
(d) the element of subjective judgment required by evaluators when applying theprequalification criteria to a number of Applicants, and the discretionary rights reservedto the Employer, provide opportunities for externally influenced deviations from theexpected high standards of ethics and impartiality in prequalifying applicants.
6. The Bank, from its own experience, believes that on balance the benefits of prequalificationunder transparent conditions for large Works contracts outweigh by a considerable margin thepotential disadvantages, for both Borrowers and the construction community alike.
-
8/3/2019 Prequal en 09 Sep 10
60/86
Users Guide 9
The Prequalification Process
The prequalification process includes four main phases: (i) Advertising, (ii) Preparation andIssuing of the Prequalification Document, (iii) Application Preparation and Submission, (iv)Application Evaluation, and Prequalification of Applicants.
Advertising (Procurement Guidelines; paras 2.7 and 2.8)
The Employer shall advertise prequalification in the project GPN in UN Development Business 7
on-line (UNDB on line) and in the Development Gateways DG Market. The PrequalificationDocument (PQD) shall not be released to the public earlier than the date of publication of the GPN.
In addition the Employer shall advertise an upcoming prequalification process: .
(a) in at least one newspaper of national circulation in the Borrowers Country and in theofficial gazette, or in an electronic portal wi