Use of Microsoft Project in Construction
26th March 2019
Paul DolanAthlone Institute of Technology
[email protected](086)3801140
![Page 2: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/2.jpg)
Stage 1
• Sequence
Stage 2
• Establish
Stage 3
• Estimate
Stage 4
• Programme
4 Stage“Thought Process3”
![Page 3: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/3.jpg)
Stage 1
• Sequence
Stage 2
• Establish
Stage 3
• Estimate
Stage 4
• Programme
Stage 1Sequence the Operations
1. Look at significant elements or stages of construction.
2. Based on the project documentation (BIM Model, Drawings, Bill of Quantities, Specifications) identify the main activities and think about a rough schedule.
![Page 4: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/4.jpg)
Stage 1
• Sequence
Stage 2
• Establish
Stage 3
• Estimate
Stage 4
• Programme
Stage 1Sequence the Operations
![Page 5: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/5.jpg)
Stage 1
• Sequence
Stage 2
• Establish
Stage 3
• Estimate
Stage 4
• Programme
3. Prepare a phasing diagram where appropriate.
Understand the link between the sequences of operations to be undertaken and the practicalities on site.
4. Do not have too many activities to begin with - 20 or 30 max.
5. Do not worry about minor details at this stage.
Stage 1Sequence the Operations
Block A
Block C
Block B
![Page 6: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/6.jpg)
Establish methods of work, choice of plant, determine quantities involved, assess risk.• Temporary works• Cranage• Material handling• Hoisting and access equipment• Scaffolding• Risk and uncertainty
Stage 1
• Sequence
Stage 2
• Establish
Stage 3
• Estimate
Stage 4
• Programme
Stage 2Establish Methods of
Work
Image courtesy of www.nce.co.uk
![Page 7: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/7.jpg)
Stage 1
• Sequence
Stage 2
• Establish
Stage 3
• Estimate
Stage 4
• Programme
Stage 2Establish Methods of
Work
![Page 8: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/8.jpg)
Stage 1
• Sequence
Stage 2
• Establish
Stage 3
• Estimate
Stage 4
• Programme
Stage 3Estimate Activity
Durations
• Resource availability• Plant • Labour• Supervision
i. Top-Down Estimating Analogous Estimates
ii. Bottom-Up Estimating Parametric Estimates
iii. Three Point Estimating Program Evaluation Review Technique (PERT)
=�� + 4�� +��
6
![Page 9: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/9.jpg)
Stage 1
• Sequence
Stage 2
• Establish
Stage 3
• Estimate
Stage 4
• Programme
1. List activities
2. Enter durations
3. Link activities with logic
• Mandatory dependencies. Hard Logic
• Discretionary dependencies. Soft Logic
• External dependencies.
Finish to Start Start to Start Finish to Finish Start to Finish
Stage 4Programme
![Page 10: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/10.jpg)
Stage 1
• Sequence
Stage 2
• Establish
Stage 3
• Estimate
Stage 4
• Programme
1. List activities
2. Enter durations
3. Link activities with logic
• Mandatory dependencies. Hard Logic
• Discretionary dependencies. Soft Logic
• External dependencies.
Finish to Start Start to Start Finish to Finish Start to Finish
Stage 4Programme
![Page 11: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/11.jpg)
Stage 1
• Sequence
Stage 2
• Establish
Stage 3
• Estimate
Stage 4
• Programme
1. List activities
2. Enter durations
3. Link activities with logic
• Mandatory dependencies. Hard Logic
• Discretionary dependencies. Soft Logic
• External dependencies.
Finish to Start
Start to Start Finish to Finish Start to Finish
Stage 4Programme
![Page 12: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/12.jpg)
Stage 1
• Sequence
Stage 2
• Establish
Stage 3
• Estimate
Stage 4
• Programme
1. List activities
2. Enter durations
3. Link activities with logic
• Mandatory dependencies. Hard Logic
• Discretionary dependencies. Soft Logic
• External dependencies.
Finish to Start Start to Start
Finish to Finish Start to Finish
Stage 4Programme
![Page 13: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/13.jpg)
Stage 1
• Sequence
Stage 2
• Establish
Stage 3
• Estimate
Stage 4
• Programme
1. List activities
2. Enter durations
3. Link activities with logic
• Mandatory dependencies. Hard Logic
• Discretionary dependencies. Soft Logic
• External dependencies.
Finish to Start Start to Start Finish to Finish
Start to Finish
Stage 4Programme
![Page 14: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/14.jpg)
Stage 1
• Sequence
Stage 2
• Establish
Stage 3
• Estimate
Stage 4
• Programme
1. List activities
2. Enter durations
3. Link activities with logic
• Mandatory dependencies. Hard Logic
• Discretionary dependencies. Soft Logic
• External dependencies. • Applying Lags and Leads can
modify the relationship between activities.
Stage 4Programme
![Page 15: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/15.jpg)
Stage 1
• Sequence
Stage 2
• Establish
Stage 3
• Estimate
Stage 4
• Programme
1. List activities
2. Enter durations
3. Link activities with logic
• Mandatory dependencies. Hard Logic
• Discretionary dependencies. Soft Logic
• External dependencies. • Applying Lags and Leads can
modify the relationship between activities.
Stage 4Programme
![Page 16: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/16.jpg)
Stage 1
• Sequence
Stage 2
• Establish
Stage 3
• Estimate
Stage 4
• Programme
1. List activities
2. Enter durations
3. Link activities with logic
• Mandatory dependencies Hard Logic
• Discretionary dependencies Soft Logic
• External dependencies. • Applying Lags and Leads can
modify the relationship between activities.
4. Use summary activities as headings to structure the schedule model
Stage 4Programme
![Page 17: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/17.jpg)
Stage 1
• Sequence
Stage 2
• Establish
Stage 3
• Estimate
Stage 4
• Programme
1. List activities
2. Enter durations
3. Link activities with logic
• Mandatory dependencies Hard Logic
• Discretionary dependencies Soft Logic
• External dependencies. • Applying Lags and Leads can
modify the relationship between activities.
4. Use summary activities as headings to structure the schedule model
Don't mistake the schedule model for reality!
Stage 4Programme
![Page 18: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/18.jpg)
Stage 1
• Sequence
Stage 2
• Establish
Stage 3
• Estimate
Stage 4
• Programme
Don't mistake the schedule model for reality!
Stage 4Programme
![Page 19: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/19.jpg)
Baselined Schedule
![Page 20: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/20.jpg)
Baselined Schedule
![Page 21: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/21.jpg)
Baselined Schedule with Progress Line
![Page 22: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/22.jpg)
Filter – Late Tasks
![Page 23: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/23.jpg)
Filter - Milestones
![Page 24: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/24.jpg)
![Page 25: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/25.jpg)
![Page 26: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/26.jpg)
![Page 27: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/27.jpg)
Bibliography
i. Architects' and Builders' Price Book, SPONS's - 2018
ii. Project Management Body of Knowledge, PMI - 6ed.
iii. Construction Planning, Programming and Control, Cooke and Williams - 2008
Stage 1
Stage 2
Stage 3
Stage 4
Thank You
![Page 28: Presentation - Use of Microsoft Project in Construction - 260319 · 2020. 5. 18. · Use of Microsoft Project in Construction 26th March 2019 Paul Dolan Athlone Institute of Technology](https://reader034.vdocument.in/reader034/viewer/2022052012/602804093f9b4a436a061197/html5/thumbnails/28.jpg)
Stage 1
• Sequence
Stage 2
• Establish
Stage 3
• Estimate
Stage 4
• Programme
Paul DolanAthlone Institute of Technology