PROJECT MANAGEMENT3RD YEAR UNDERGRADUATE UNIT
U13451 PRMAN DL
Tutor: Kathy Parker
WEEK FIVEAdapted from slides by Dr Philip J. Scott MSc PhD FBCS
CITPUniversity of Portsmouth
Adapted by Kathy Parker
![Page 2: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/2.jpg)
Contents
Learning outcomes Lecture: Project planning (part 2) Exercise
Slide 2 of 8
![Page 3: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/3.jpg)
Learning outcomes
Demonstrate how to construct a project plan using Microsoft Project
Use bespoke resource calendars, task dependencies and timescale options
Explain costing and reporting options
Slide 3 of 8
![Page 4: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/4.jpg)
Lecture: Using Microsoft Project MS Project is the de facto standard There are commercial alternatives and
free/shareware products, or use Excel Viewing software freely available to
read .MPPs MS Project comes as standalone or Enterprise
server Maintaining it can become an industry! This lecture is mostly demonstration Tutorial will give you an opportunity to applySlide 4 of 8
![Page 5: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/5.jpg)
Lecture: Using Microsoft Project Introduction to Microsoft Project – walk
through an existing plan Key concepts:
Tasks (summary/detail) Dependencies Resources Calendars Timescale views
Not covering resource levelling
Slide 5 of 8
![Page 6: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/6.jpg)
Lecture: Using Microsoft Project Example of building a new plan
Define project information (start date, calendar options)
Enter tasks, indent/outdent to demote/promote Enter task durations and dependencies Adjust timescale view as necessary Get print format right Allocate resources and their calendars and costs Update % completion Compare alternative views (PERT, resource
sheet)Slide 6 of 8
![Page 7: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/7.jpg)
MS Project: Start Up
This is what you get when you open MS Project.If you don’t get the Project Guide (a sort of a wizard tool) on the left hand side of the display and you want to use it then you will need to follow the instructions on the next slide.Otherwise go to slide 9.
![Page 8: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/8.jpg)
MS Project: Getting to Project Guide
On the top menu Click on Tools then Options Then click on the Interface tab and tick the Display Project Guide Box
![Page 9: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/9.jpg)
MS Project: Define project information
Project -> Project InformationGives this pop-up.Enter the project start date.Leave the Schedule from: Project start Date as it is (helps with initial scheduling)If you need to put in time frame constraints later then fine
![Page 10: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/10.jpg)
MS Project: Define project calendar
Tools - > Change working time gives this screen.From here you can define the project working days and hours.If the project will use work the days and weeks as per the ‘Standard’ calendar then use it. Otherwise Create a New Calendar, give it a name and make it a copy of the Standard
![Page 11: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/11.jpg)
MS Project: Define Working times
From here you can set default working times for specified days of the week.E.g. I have set working times for Monday to Thursday as 09:00 to 12:30 and 13:30 to 17:00 and from 09:00 to 12:00 and 13:00 to 16:00 on a Friday
![Page 12: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/12.jpg)
MS Project: Define Non-Working times
From the Exceptions tab I have defined an exception of Christmas from 20/12 to 3/1/11 as non-working time
![Page 13: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/13.jpg)
MS Project: Assign Calendar to Project
Back to Project -> Project Information and select your calendar from the drop down menu to assign the calendar to your project
![Page 14: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/14.jpg)
MS Project: Enter your tasks
Enter the tasksBefore doing this you should have done the PBS and PFD as per week 4
![Page 15: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/15.jpg)
MS Project: Indent/outdent tasks
I have entered higher level tasks: Project Initiation and Determine requirements
![Page 16: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/16.jpg)
MS Project: Indent/outdent tasks
I now highlight the sub tasks for each and click on the indent arrow
![Page 17: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/17.jpg)
MS Project: Indent/outdent tasks
When I put in a new task it will go in as a sub task under the Determine Requirements unless I outdent
![Page 18: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/18.jpg)
MS Project: Enter Task Durations
Under Duration enter the time it will take to complete the task. Only enter the times for the low level tasks.The summary level tasks are calculatedTasks with a time of zero are indicated as milestones
![Page 19: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/19.jpg)
MS Project: Enter Task Dependencies
This can be done in one of 3 ways:1.Highlight the two tasks e.g. Cannot get PID approved until PID is produced•Then click on the Link tasks icon•The chart shows the tasks linked
![Page 20: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/20.jpg)
MS Project: Enter Task Dependencies 2a
2. Double click on a task to get the Task information windowSelect the Predecessors tab, click on the down arrow under Task Name and select the task(s) that must precede (be done before) this task.e.g. PID approved milestone cannot happen until the Get PID approved is complete. Click OK
![Page 21: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/21.jpg)
MS Project: Enter Task Dependencies 2b
2. This method is also useful for specifying link type that are not the standard Finish-to-Start and these can be selected under TypeA lag can also be specified
![Page 22: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/22.jpg)
MS Project: Enter Task Dependencies 2c
2. Which creates this->
![Page 23: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/23.jpg)
MS Project: Enter Task Dependencies 3
3. Using drag and drop technique.Hover over the predecessor task until you see and a task box appearThen drag to the successor task. A box labelled Finish-to-Start Link will appearComplete the link
![Page 24: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/24.jpg)
MS Project: Changing the GANTT view timescales
We now cannot all our project so we may wish to change the timescale at the topSet the middle tier – here we are changing it from Weeks to MonthsAnd the bottom tier from Days to weeks
![Page 25: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/25.jpg)
MS Project: Changing the GANTT view timescales
Which gives us ->
![Page 26: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/26.jpg)
Lecture: Using Microsoft Project Keep it manageable:
Limit number of tasks per plan (500?) Split or create sub-plans or super-plans if
necessary Only add the crucial dependencies Break down work to sensible level for
monitoring Strict version control: baseline, progress,
what-ifs Don’t try to make it an accounting tool
Slide 26 of 8
![Page 27: PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP](https://reader036.vdocument.in/reader036/viewer/2022062409/56649ed55503460f94be603f/html5/thumbnails/27.jpg)
Tutorial walk-through
Slide 27 of 8