Download - Project Management - Foundation
![Page 1: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/1.jpg)
Project Management — Foundation
Project ManagementAn Interactive Session
Facilitated by:
Shabbeer Zafar
![Page 2: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/2.jpg)
You don’t have to see the whole
staircase, just take the first step.
-Martin Luther King Jr. 01
![Page 3: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/3.jpg)
How the Customer
explained it
How the PM
understood it
How the Analyst
designed it
How the Developer
wrote it
How the Sales
explained it
How the project was
documented
What Operations
installed
How the Customer
was billed
How it was
supported
What the Customer
really needed
Assumption is the mother of all screw-ups.-Wethern’s Law of Suspended Judgement
![Page 4: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/4.jpg)
4 44
• Only 64% of projects meet their goals
• High-performing organizations complete 89% of projects
• Low performing organization complete only 36%
• Low performing organizations waste nearly 12 times more resources than high-performing organizations
Stats: Project Surveys
![Page 5: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/5.jpg)
5 44
• 1 in 6 (17%) IT projects have an average cost overrun of 200% and a schedule overrun of 70% (both inclusive)
• 17% of large IT projects go so badly that they threaten the existence of the company
• Across all software projects (2014-15):
– Average cost overrun – 59%
– Average time overrun – 74%
Stats: Project Surveys
![Page 6: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/6.jpg)
6 44
Reasons of Failure % Reasons of Failure %
Changing priorities within organization
40% Inaccurate task time estimate 27%
Inaccurate requirements 38% Resource dependency 25%
Change in project objectives 35% Poor change management 25%
Undefined risks/opportunities 30% Inadequate resource forecasting
23%
Poor communication 30% Inexperienced project manager
20%
Undefined project goals 30% Limited resources 20%
Inadequate sponsor support 29% Procrastination within team 13%
Inaccurate cost estimates 29% Task dependency 11%
Meta Source: https://www.wrike.com/blog/complete-collection-project-management-statistics-2015
Stats: Causes of Project Failure
![Page 7: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/7.jpg)
No matter how good the team or how
efficient the methodology, if we’re not
solving the right problem, the project fails.
-Woody Williams02
![Page 8: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/8.jpg)
8 44
• To introduce the concept and need of software project management
• To discuss the crucial role of project manager in the success and failure of a project
• Laying down the foundation for further trainings in project management area
Session Objectives
![Page 9: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/9.jpg)
9 44
• What is Project?
• What is Project Management?
• Objectives of Project Management
• Introducing PMBOK
• Project Management Process
• Project Management Framework
• Project Process Interactions
• Why do we need a Project Manager?
• Project Management Activities
Agenda
• Project Manager’s Skill Set
• Components of a Successful Project Management System
• Measuring Success of a Project
• 7 Habits of Highly Effective Project Manager
• Journey ahead…
![Page 10: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/10.jpg)
10 44
Origin: projectum (Latin verb proicere)
– pro: before
– icere: to do
– proicere = before an action
What is Project?
![Page 11: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/11.jpg)
11 44
Project is a temporary endeavour undertaken to create a unique product, service or result.
What is Project?
• Temporary – definite beginning and end
• Unique – different in some distinguishing characteristic
• Progressively elaborated
![Page 12: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/12.jpg)
12 44
• Developing a new product or service
• Effecting a change in structure, staffing, or style of an organization
• Designing a new transportation vehicle
• Constructing a building or facility
• Running an election campaign
• Implementing a new business procedure or process
Examples of Project
![Page 13: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/13.jpg)
13 44
Projects Operations• Temporary • On-going
• Unique • Repetitive
• Closes after attaining the objectives
• Objective is to sustain the business
• Prototyping a new car model • Assembly line production
Projects Vs. Operations
![Page 14: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/14.jpg)
14 44
• Programs
– Collection of strategically related projects
– Collective benefits are realized
– Projects share resources and depends on the outcomes of other projects
– Governed by a common mission statement
• Portfolios
– Collection of programs and projects
– Projects/programs meet specific goals or objectives
– Ensures efficient use of resources
– Governed by a vision statement
• PMO (Project Management Office)
– Centralized units to oversee projects and programs within the organization
– Establishes and maintains the standards of project management methodologies
– Supports managers in planning, estimating, risk management and trainings
– Custodian of Organization Process Assets (OPA)
Project, Program & Portfolio
![Page 15: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/15.jpg)
Operations keeps the lights on. Strategy
provides a light at the end of the tunnel. But,
Project management is the train engine that moves the organization forward.
-Joy Gumz03
![Page 16: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/16.jpg)
16 44
1. Project activities
2. Knowledge and skills
3. Tools and techniques
4. Project activities
5. Stakeholder needs and expectations (client relation challenges)
– Meet or Exceed
Project Management?
Project management is the application of knowledge, skills, tools, and techniques to project activities in order to meet or exceed
stakeholder needs and expectations from a project.
![Page 17: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/17.jpg)
17 44
• Scope
• Cost
• Time
• Quality
Via
bili
ty
Performance
Effort
Co
mp
etitiveness
Project management
process and controls
Project Management
Process and Controls
Scope
Cost
Quality
Time
The Core Elements
![Page 18: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/18.jpg)
18 44
Objectives: Project Management
S• Specific: What, who, when? Details of what needs to be done.
M• Measureable: How much, how many? Defined milestones. Matrices.
A• Achievable: Agreed and accepted by all stakeholders. Results matter.
R• Realistic: Challenging yet possible to attain with the given resources.
T• Time bound: By when? Timeline clearly defined.
![Page 19: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/19.jpg)
19 44
PMBOK
PMBOK – Project Management Body of Knowledge
• General Management:– Planning, Organising, Staffing– Executing, Operations
• Application Area:– Estimation– Fin. forecasting– Budgeting– Org. behaviour
• Interpersonal Skills:– Communication– Team building, Delegation– Decision making, Collaboration– Leadership, Mentoring
• Project Environment:– Org. Culture/Structure– Social, Technological
Interpersonal
Skills
General Management
Knowledge and PracticesApplication Area
Knowledge & Skills
Understanding the
Project Environment
PMBOK
Generally Accepted
Project Management
Knowledge and Practices
![Page 20: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/20.jpg)
If you can’t describe what you are doing as
a process, you don’t know what you’re
doing.-W. Edwards Deming04
![Page 21: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/21.jpg)
21 44
Project Management Process
• Initiate
• Plan
• Execute
• Monitor & Control
• Close
• Process: – Linear?
– Iterative?
– Cyclic?
Initiate Plan
Monitor & Control
Execute
Close
![Page 22: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/22.jpg)
22 44
• Initiating – Authorizes the project
• Planning – Plan the course of action to achieve the objectives
• Executing – Uses the resources to carry out project tasks
• Monitoring and Controlling – Measures progress to identify variances. Take preventive and corrective actions
• Closing – Ensures structured project closure
Project Management Process
![Page 23: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/23.jpg)
23 44
• Work Performance Data
– The raw observations and measurements:
• Start and finish dates of scheduled tasks/activities
• Number of change requests
• Number of defects
• Actual cost
• Actual duration
• Work Performance Information
– The performance data collected from various controlling processes:
• Status of deliverables
• Implementation status of change requests
• ETC forecast
• Work Performance Reports
– The physical or electronic representation, compiled in project reports/documents:
• PSR
• Dashboards
• Memos
• Justifications
• Information notes
Project Information Flow
![Page 24: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/24.jpg)
24 44
Project Management FrameworkK
no
wle
dge
Are
as
Pro
cess
Gro
up
s
47
PROCESESS
Integration Management
Scope Management
Time Management
Cost Management
Quality Management
HR Management
Communication Management
Risk Management
Procurement Management
Stakeholder Management
Initiating
Planning
Executing
Monitoring & Controlling
Closing
![Page 25: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/25.jpg)
25 33
![Page 26: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/26.jpg)
26 44
Inputs
• Scope Management Plan
• Requirements Management Plan
• Stakeholder Management Plan
• Project Charter
• Stakeholder Register
Tools & Techniques
• Interviews
• Focus Groups
• Facilitated Workshops
• Group Creativity Techniques
• Group Decision Making Techniques
• Questionnaires and Surveys
• Observations
• Prototypes
• Benchmarking
• Context Diagram
• Document Analysis
Output
• Requirements Documentation
• Requirements Traceability Matrix
Process: An Example
Process: Collect Requirements
![Page 27: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/27.jpg)
27 44
Process Interactions
Process Groups
Init
iati
ng
Pla
nn
ing
Exec
uti
ng
Mo
nit
ori
ng
&
Co
ntr
olli
ng
Clo
sin
g
Kn
ow
led
ge A
reas
Integration
Scope
Time
Cost
Quality
Human Resources
Communication
Risk
Procurement
Stakeholder
![Page 28: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/28.jpg)
28 44
Process Overlap
Level of Process
Interaction
Start FinishTime
Initiating Planning Executing Monitoring & Controlling Closing
Initiating Planning Executing Monitoring & Controlling Closing
Processes 4% 51% 17% 23% 4%
Time span Short End-to-End Long End-to-End Short
![Page 29: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/29.jpg)
29 44
Project Activities
Deciding – Planning & Defining Doing – Implementing & Controlling
Initiate Work
Monitor & Track Progress
Compare Actual vs. Planned
Analyze Impact of Changes
Adjust Plan as Needed
Complete the Project
Assess Outcomes
Project Goals and Objectives
Work Requirements
Quantity of Work
Quality of Work
Required Resources
Team Structure
Scheduling and Task Sequencing
Budgeting
Deciding & Doing
![Page 30: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/30.jpg)
![Page 31: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/31.jpg)
Project managers function as bandleaders
who pull together their players each a
specialist with individual score and internal
rhythm. Under the leader’s direction, they all
respond to the same beat.
-L.R. Sayles
05
![Page 32: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/32.jpg)
32 44
• To focus on the responsibility, authority, and scheduling of the project in order to meet the defined goals.
– Defining clear work descriptions
– Assigning individual/team responsibilities
– Decision making
– Minimize surprises and conflicts
– Reducing the need for continuous reporting
– Measuring progress against the plan
Do We Really Need a PM?
![Page 33: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/33.jpg)
33 44
• Knowledge
– What s/he knows about project management
• Performance
– What the PM is able to do or accomplish while applying project management knowledge
• Personal
– Attitude
– Core personality characteristics
– Leadership
• The ability to guide the project team while achieving objectives and balancing the project constraints
Project Manager’s Skill Set
![Page 34: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/34.jpg)
34 44
Management Skills Interpersonal Skills
• Presentation • Negotiation
• Team building • Motivation
• Business Writing • Verbal Communication
• Public Speaking • Convincing and Influencing
• Decision Making • Political and Cultural Awareness
Project Manager’s Skill Set
![Page 35: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/35.jpg)
Project Managers are the most creative
persons in the world; they have to figure out
everything that could go wrong, before it does.
-Fredrik Haren06
![Page 36: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/36.jpg)
36 44
Balancing Act
Risks
The Project
ClientExpectations
Business Objectives
Risks
Client Expectations
Low High
Business Objectives
Low OKCustomer wants more than the organization intends to provide
HighBusiness needs more from the
project than the customerOK
![Page 37: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/37.jpg)
37 44
Project Management Equation
Project Management
Expectations Management
RiskManagement
![Page 38: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/38.jpg)
All things are created twice; first mentally; then
physically. The key to creativity is to begin
with the end in mind, with a vision and a
blueprint of the desired result.
-Stephen Covey07
![Page 39: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/39.jpg)
39 44
1. Be Proactive
2. Begin with the “End in Mind”
3. Put First Things First
4. Think Win/Win
5. Seek First to Understand, Then to be Understood
6. Synergize
7. Sharpen the Saw
7 Habits of Highly Effective PM
![Page 40: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/40.jpg)
40 44
• Human Factors
• Methods
• Culture
• Organization
• Planning
• Information
• Control
Components of a Successful Project Management System
• Leadership• Negotiation• Team building• Motivation• Communication• Decision making
![Page 41: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/41.jpg)
41 44
• Stakeholder satisfaction
• Meeting business case objectives
• End-user adoption
• Quality of delivery
• Meeting governance criteria
• Benefits realization (ROI)
Measuring Project Success
![Page 42: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/42.jpg)
42 44
• A project is a problem scheduled for solution
• If the problem is not defined correctly, you may find the right solution to the wrong problem
• Focus on desired outcomes
• Regularly measure the progress to know when you achieve them
• The people who must execute the plan should participate in preparing it
• If you have no plan, you have no control
The Bottom Line
![Page 43: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/43.jpg)
A project is complete when it starts working for
you, rather than you working for it.
-Scott Allen08
![Page 44: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/44.jpg)
44 44
• Session to cover each Knowledge Area (2-3 hrs./session)
• Practice Workshops:
– Creating WBS
– Estimation Techniques
– Planning and Scheduling
– Earn Value Analysis
– Requirements Writing
• Suggestions welcome!
• Volunteers?
Journey Ahead…
![Page 45: Project Management - Foundation](https://reader031.vdocument.in/reader031/viewer/2022022415/5a66ed1d7f8b9a91298b4ac3/html5/thumbnails/45.jpg)
The art of asking good questions is often the most
important element of managerial tasks.
-Parte Bose
THANK YOU!