PROJECT MANAGEMENT
IN
Submitted byBanaja pattanayak
MBA IInd year
A Project Report on
Welcome to Construction World
Top 10 Construction Companies
AFCONS began its operation as a civil construction firm way back in 1959. The Company was then a partnership between RODIO FOUNDATION ENGINEERING LIMITED, SWITZERLAND AND HAZARAT AND COMPANY, INDIA
, AFCONS has emerged as the leader in its business field by continuously delivering its world class services in the areas of Marine Works, Highways, Bridges, Metro Works, Power Houses, Tunnels, Oil & Gas, LNG Tanks and other general Civil Engineering Projects
Line Of Business
Power Project Transportation Marine Drive
Buildings & Industrial Structure Oil & Gas Special Foundation
Financial Highlights
Mission•To be a prominent transnational infrastructure company recognized for business innovation, focused on total satisfaction and enhanced value creation for all its stakeholders.
Goal •It aims to be a billion dollar company by 2011-12.
PROJECT MANAGEMENT
Project Management is a well-established approach to managing and controlling the introduction of new initiatives or organizational changes.
Tools of Project Management
Estimating Time Risk Impact Scheduling Simple Projects Critical Path Analysis Planning Large Project Stake Holders Analysis Stake Holders Planning &management
Project-1
Owner : New Delhi Municipal Council
Client : Engineers India Limited on behalf of NDMC
Contractor : M/s AFCONS –Sterling & Wilson Consortium
PROJECT TEAM
1. Projects consists of Construction of service Corridor at Middle Circle and laying of the Service of Connaught Place,
2. Total Contract Value : 236.70 Crores
3. AFCONS Scope : 180.42 Crores
4. Revised AFCONS Scope : 198.39 Crores *
5. S & W Scope : 56.30 Crores.
6. Duration of Project : 18 Months.
7. Date of Issue of letter of acceptance : 04th Nov 2009
8. Date of completion of Project. : 03 May 2011
9. Defect Liability Period of Project. : 12 Months from the
date of issue of completion certificate.
PROJECT DETAIL
Design and Construction of Cut & Cover Tunnel Including
Switchover Ramps and One Underground Station in Airport
AreaAMEL – C3 Project
Project-2
Client : Delhi Metro Rail Corporation
Limited
Consultant : Airport Line Consultants
Contractor : Afcons Infrastructure Limited
Total Length - 3630 RM
Excavation - 791250 Cum
Piling - 2900 RM
Reinforcement - 12500 MT
Concrete - 95000 Cum
Structural Steel- 5000 MT (Temp.
works)
Major items of Work