PROJECT RISK / MITIGATION - INDEX
CCC International
Wide Geographical Area
Type of Projects
Forms of Contract
Types of Risks
Conclusions / Recommendations
2
![Page 3: PROJECT RISK / MITIGATION - INDEXecrisponsor.org › Npresentations › 2-2Ath.pdf · Turnkey EPC Packages Reimbursable Contracts Convertible to Lump Sum Turnkey Contracts (CLSTK)](https://reader030.vdocument.in/reader030/viewer/2022041116/5f29361d9141c158e93957d5/html5/thumbnails/3.jpg)
OUR CCC FAMILY
Consolidated Contractors Company (CCC) a private company, was originally formed in 1952 in Lebanon and has been 63 years in the Construction Industry
CCC, with it’s managing office based in Athens - Greece, currently employs approximately 140,000 people in its worldwide operations
CCC is predominately a major construction company, providing project management, engineering, procurement and construction services to the industry worldwide and ranked 22nd in ENR Top International Contractors (2015)
CCC turnover 5 Billion
Operations in 50 Countries
Projects in hand - 150 worldwide
Total manpower – 140,000
3
![Page 4: PROJECT RISK / MITIGATION - INDEXecrisponsor.org › Npresentations › 2-2Ath.pdf · Turnkey EPC Packages Reimbursable Contracts Convertible to Lump Sum Turnkey Contracts (CLSTK)](https://reader030.vdocument.in/reader030/viewer/2022041116/5f29361d9141c158e93957d5/html5/thumbnails/4.jpg)
WIDE GEOGRAPHICAL AREA
4
![Page 5: PROJECT RISK / MITIGATION - INDEXecrisponsor.org › Npresentations › 2-2Ath.pdf · Turnkey EPC Packages Reimbursable Contracts Convertible to Lump Sum Turnkey Contracts (CLSTK)](https://reader030.vdocument.in/reader030/viewer/2022041116/5f29361d9141c158e93957d5/html5/thumbnails/5.jpg)
TYPE OF PROJECTS
Oil & Gas
Refineries & Petrochemical
Power & Desalination
Mines & Smelters
Pipelines
Water & Sewage Treatment
Airport & Seaports
Heavy, Civil, Dams, Reservoirs & Distribution Systems
Road Networks
Skyscrapers
Environmental Projects
5
![Page 6: PROJECT RISK / MITIGATION - INDEXecrisponsor.org › Npresentations › 2-2Ath.pdf · Turnkey EPC Packages Reimbursable Contracts Convertible to Lump Sum Turnkey Contracts (CLSTK)](https://reader030.vdocument.in/reader030/viewer/2022041116/5f29361d9141c158e93957d5/html5/thumbnails/6.jpg)
FORMS OF CONTRACT
Turnkey EPC Packages
Reimbursable Contracts Convertible to
Lump Sum Turnkey Contracts (CLSTK)
Build / Own / Operate / Transfer (BOO /
BOT / BOOT)
Design / Build with Guaranteed Maximum
Price
Re-measurable
6
![Page 7: PROJECT RISK / MITIGATION - INDEXecrisponsor.org › Npresentations › 2-2Ath.pdf · Turnkey EPC Packages Reimbursable Contracts Convertible to Lump Sum Turnkey Contracts (CLSTK)](https://reader030.vdocument.in/reader030/viewer/2022041116/5f29361d9141c158e93957d5/html5/thumbnails/7.jpg)
TYPE OF RISKS
Country Risks
Client / Partner Risks
Contractual / Commercial Risks
Technical Risks
CCC Internal Executive Risks
7
![Page 8: PROJECT RISK / MITIGATION - INDEXecrisponsor.org › Npresentations › 2-2Ath.pdf · Turnkey EPC Packages Reimbursable Contracts Convertible to Lump Sum Turnkey Contracts (CLSTK)](https://reader030.vdocument.in/reader030/viewer/2022041116/5f29361d9141c158e93957d5/html5/thumbnails/8.jpg)
COUNTRY RISKS
Political instability / Security
Currency exchange
Cannot import labor/staff
Onerous local content requirements
Lack of reliable Suppliers and Subcontractors
Climate conditions
8
![Page 9: PROJECT RISK / MITIGATION - INDEXecrisponsor.org › Npresentations › 2-2Ath.pdf · Turnkey EPC Packages Reimbursable Contracts Convertible to Lump Sum Turnkey Contracts (CLSTK)](https://reader030.vdocument.in/reader030/viewer/2022041116/5f29361d9141c158e93957d5/html5/thumbnails/9.jpg)
CLIENT/PARTNER RISKS
Ability of Client to pay on time
Quality of E&P deliverables
CCC’s ability to influence E&P deliverables
Delays by client on approvals or responses
Teamwork (Client/Partner)
9
![Page 10: PROJECT RISK / MITIGATION - INDEXecrisponsor.org › Npresentations › 2-2Ath.pdf · Turnkey EPC Packages Reimbursable Contracts Convertible to Lump Sum Turnkey Contracts (CLSTK)](https://reader030.vdocument.in/reader030/viewer/2022041116/5f29361d9141c158e93957d5/html5/thumbnails/10.jpg)
CONTRACTUAL/COMMERCIAL RISKS
Ambiguous, contradicting or onerous contract
terms and conditions
Scope or split of responsibility is not well defined
Non clarity of the Intermediate and/or Completion
milestones pre-requisites to obtain the Client
acceptance certificates
Contract conditions highly unfavorable
Negative cash flow
Dispute resolution mechanism
High LD’s
10
![Page 11: PROJECT RISK / MITIGATION - INDEXecrisponsor.org › Npresentations › 2-2Ath.pdf · Turnkey EPC Packages Reimbursable Contracts Convertible to Lump Sum Turnkey Contracts (CLSTK)](https://reader030.vdocument.in/reader030/viewer/2022041116/5f29361d9141c158e93957d5/html5/thumbnails/11.jpg)
TECHNICAL RISKS
Poorly prepared FEED package/ immature design
from the Client in EPC & D/B contracts
Unrealistic schedule
Lack of scope definition
Undefined and/or difficult handing-over
requirements
Uncertainty in soil/underground conditions
Limited time allocated for comprehensive bidding
11
![Page 12: PROJECT RISK / MITIGATION - INDEXecrisponsor.org › Npresentations › 2-2Ath.pdf · Turnkey EPC Packages Reimbursable Contracts Convertible to Lump Sum Turnkey Contracts (CLSTK)](https://reader030.vdocument.in/reader030/viewer/2022041116/5f29361d9141c158e93957d5/html5/thumbnails/12.jpg)
CCC INTERNAL EXECUTIVE RISKS
Unavailability of capable sub-contractors
Low labor productivity of Local Workforce
Timely availability of Project Team on site
Growth in Construction Management
12
![Page 13: PROJECT RISK / MITIGATION - INDEXecrisponsor.org › Npresentations › 2-2Ath.pdf · Turnkey EPC Packages Reimbursable Contracts Convertible to Lump Sum Turnkey Contracts (CLSTK)](https://reader030.vdocument.in/reader030/viewer/2022041116/5f29361d9141c158e93957d5/html5/thumbnails/13.jpg)
CONCLUSIONS / RECOMMENDATIONS
Early engagement with Client / Partner
Risk allocation to the party that can best manage /
mitigate the Risk
Spend enough time & money on Tender to identify
the Risk
Continuous monitoring of Risk at Project execution
Do not be afraid to walk away from Tenders
13