Project Status• The project is progressing well with both grading aspects
and building components. • The mason has erected many walls to “scaffold high”
and starting to take the walls in Gym/Cafeteria wing to bearing height.
• The steel frame in 2-3 wing is 98% complete and began on the K-1 wing on 10/4/10.
• Part of Gym/Cafeteria wing steel frame has been started. • Slab On Grade in 4-5 wing has been poured and the
mason has the interior walls up to scaffold height. • The plumber has finished the underground rough-in in K-
1 wing and 2-3 wing; the kitchen is the next area for installation.
• The electrician has continued with rough-in.• Project is 26% completed.
Aerial Photo taken from Northern Elevation---Picture taken on 9/13/10
Gym
Cafeteria
4-5 wing2-3 wing
K-1 wing
K-1 Wing Masonry in Fore Ground; 2-3 Wing Steel Frame on Right
Picture taken from Church Parking Lot viewing 2-3 wing Steel Frame
Slab on Grade poured in 4-5 wing. Steel for 2-3 wing.
Givens Street Extension Completed prior to Children returning to School on 8/25/10
Project in relation to the existing school; Picture taken from North Elevation