Name of project Falu Energi & Vatten
Location Falun, Sweden
Equipment Supplied PST Spiral Conveyors
Material Dry Sawdust, Pellets
Capacity 40-80m³/h
Number of conveyors 24
Commissioned 2013
[email protected] www.pst.se Plåt & Spiralteknik I Torsås AB
Pellet plant
This top-of-the-line, fully automated plant produces approx.
45 000 tons/ year. The installation consists of 24 conveyors.
The use of PST vertical systems saved valuable floor space
and helped in the design of the plant´s compact layout. The
conveyors met the strict demand for a clean plant with zero
acceptance of dust or leakage.
The pellet plant is designed to use logging residue and hard-
wood as raw material for the pellets. The plant is also capable
of producing consumer grade pellets, by the use of sawdust
only.