RIGGING DEPARTMENT

ANALYZE AND PLANED ACTIVITY FOR LIFTING AND ERECTION

WORK

Page 3: PT. GAKA KARYA ENGINEERING

RIGGING DEPARTMENT

RIGGING & EQPTEDI TRIANTO

DESGN ENGINEER RIGGING ENGINEER RIGGING SUPERVI. SCAFOLDER SUPERV.HAGUN GUNAWAN SARPAN KARTONO

Foreman, Scafolder, Helper Foreman, Scafolder, Helper

Page 4: PT. GAKA KARYA ENGINEERING

START

DATA MATERIAL1. DIMENSION2. WEIGHT

REFERENCE1. RIGGING BOOK 2. EQUIP. MANUAL

3. B30.24-2003 Safety Standard4. B30.21-2005 manually lever operated hoist

5. Australian Standard, AS 3569--1989, Wire ropes6. Australian Standard, AS 2759--1985, Wire ropes

7. NAVFAC P-307, Juni 20038. Construction Industry Crane Safety Summit, 2009

NEED DUO

CRANE

TAILING DESIGNMONO CRANE

A

No

Yes

B

Page 5: PT. GAKA KARYA ENGINEERING

A

JSA

BRisk

Safe

RIGGING PLAN

STOP

CONTROL

REPORT

ACTION

Page 6: PT. GAKA KARYA ENGINEERING

STEP-11.TAHAP PERTAMA, OBJECT YANG AKAN DI ANGKAT ADALAH GENERATOR UNIT 2 (BARAT)2.INSTALL RAIL WAY FOR SLINDING.3.MENURUNKAN GENARATOR DARI ATAS "GOLDEFER"4.TAKE IT ON RAIL WAY.5.READY TO SLIDING.6.MOVE IT UNTIL 30.000MM OVER THAN BEFORE ON ELEVATION +500.

Page 7: PT. GAKA KARYA ENGINEERING

STEP-21.TAHAP KEDUA, OBJECT YANG AKAN DI ANGKAT ADALAH GENERATOR UNIT 1 (TIMUR)2.MENURUNKAN GENARATOR DARI ATAS "GOLDEFER"3.TAKE IT ON RAIL WAY.4.READY TO SLIDING.5.MOVE IT UNTIL TO CENTERLINE OF GENERATOR ON ELEVATION +500.

Page 8: PT. GAKA KARYA ENGINEERING

STEP-31.INSTALL RAIL WAY SEJAJAR DENGAN SUMBU GENERATOR.

2.MOVE IT UNTIL 7000MM OVER THAN BEFORE.

Page 9: PT. GAKA KARYA ENGINEERING

STEP-41.INSTALL GANTRY CRANE FOR LIFTING GENERATOR UNIT 1 (TIMUR)

Page 10: PT. GAKA KARYA ENGINEERING

STEP-51.CONNECTED ALL CONNECTOR,

2.LIFT OBJECT UNTIL ELEVATION 10.000 UP TO GROUND FLOOR,3.MOVE OBJECT BY CRANE UNTIL POSITION (FROM BARAT TO TIMUR)

Page 11: PT. GAKA KARYA ENGINEERING

STEP-61.INSTAL SKIDDING UNIT KETGA DAN KEEMPAT DI KAKI TENGAH.

2.LEPASKAN KAKI PANJANG.

Page 12: PT. GAKA KARYA ENGINEERING

STEP-71.GESER OBJECT KE POSISI TARGET.

Page 13: PT. GAKA KARYA ENGINEERING

STEP-81.TURUNKAN OBJECT KE POSISI TARGET.

Page 14: PT. GAKA KARYA ENGINEERING

STEP-91.SLIDING GENERATOR UNIT 2 (BARAT) TO CENTER LINE ON GROUND FLOOR.

Page 15: PT. GAKA KARYA ENGINEERING

STEP-101.PREPARATION ACTIVITIES FOR GENERATOR UNIT 2 (BARAT)

Page 16: PT. GAKA KARYA ENGINEERING

STEP-111.CONNECTED ALL CONNECTOR,

2.LIFT OBJECT UNTIL ELEVATION 10.000 UP TO GROUND FLOOR,3.MOVE OBJECT BY CRANE UNTIL POSITION (FROM TIMUR TO BARAT)

Page 17: PT. GAKA KARYA ENGINEERING

STEP-121.INSTAL SKIDDING UNIT KETGA DAN KEEMPAT DI KAKI TENGAH.2.LEPASKAN KAKI PANJANG.

Page 18: PT. GAKA KARYA ENGINEERING

STEP-131.GESER OBJECT KE POSISI TARGET.

Page 19: PT. GAKA KARYA ENGINEERING

STEP-141.TURUNKAN OBJECT KE POSISI TARGET.

Page 20: PT. GAKA KARYA ENGINEERING

RIGGING DEPARTMENT LOGOLIFT

SWINGMOVEDOWN

In safety corridor

THINK SAFEDO SAFELY

SAFETY FIRST