![Page 1: RIGID SAFETY BARRIER 15C - tccs.act.gov.au · Method Statement Process description for the manufacture, supply and installation of any road safety ... Electrical conduits Location](https://reader034.vdocument.in/reader034/viewer/2022042211/5eb320d99457c50a382672a9/html5/thumbnails/1.jpg)
RIGID SAFETY BARRIER 15C
MUNICIPAL INFRASTRUCTURE TECHNICAL SPECIFICATION 15 - ROAD SIDE FURNITURE
Transport Canberra and City Services
JULY 2019
![Page 2: RIGID SAFETY BARRIER 15C - tccs.act.gov.au · Method Statement Process description for the manufacture, supply and installation of any road safety ... Electrical conduits Location](https://reader034.vdocument.in/reader034/viewer/2022042211/5eb320d99457c50a382672a9/html5/thumbnails/2.jpg)
ACT Government 2
Publication Number: MITS 15C Edition 1 Revision 0
Date of Effect: July 2019
Supersedes: Standard Specification for Urban Infrastructure Works Section 7
Edition 1 Revision 0 September 2002
Endorsed By: Karl Cloos Director, Infrastructure Planning
Approved By: Ken Marshall Executive Branch Manager, Roads ACT
Document Information
Document Key Information
Document Title MITS 15C Rigid Road Safety Barrier Systems
Next review date
Key words
AUS-SPEC Base Document
1163 Rigid road safety barrier systems
Revision Register
Edition/ Revision Number
Clause Number Description of Revision Authorised By Date
1/0
![Page 3: RIGID SAFETY BARRIER 15C - tccs.act.gov.au · Method Statement Process description for the manufacture, supply and installation of any road safety ... Electrical conduits Location](https://reader034.vdocument.in/reader034/viewer/2022042211/5eb320d99457c50a382672a9/html5/thumbnails/3.jpg)
ACT Government 3
CONTENTS
1 Rigid road safety barrier systems .............................................................. 4
1.1 General ........................................................................................................................ 4
1.1.1 Responsibilities ....................................................................................................................... 4
1.1.2 Cross references ..................................................................................................................... 4
1.1.3 Referenced documents .......................................................................................................... 4
1.1.4 Standard ................................................................................................................................. 5
1.1.5 Interpretation ......................................................................................................................... 5
1.1.6 Hold points and witness points .............................................................................................. 5
1.2 Materials ...................................................................................................................... 7
1.2.1 General ................................................................................................................................... 7
1.2.2 Concrete ................................................................................................................................. 7
1.2.3 Reinforcement ........................................................................................................................ 7
1.3 Execution ..................................................................................................................... 8
1.3.1 Provision for traffic ................................................................................................................. 8
1.3.2 Site establishment .................................................................................................................. 8
1.3.3 Traffic safety ........................................................................................................................... 8
1.3.4 Establishment ......................................................................................................................... 8
1.3.5 Manufacture of precast reinforced concrete ......................................................................... 9
1.3.6 Installation .............................................................................................................................. 9
1.3.7 Placing, compacting and finishing concrete ......................................................................... 10
1.3.8 Alignment and level.............................................................................................................. 11
1.3.9 Joints in concrete placed in-situ ........................................................................................... 11
1.3.10 Curing ................................................................................................................................... 12
1.3.11 Delineators ........................................................................................................................... 13
1.3.12 Signage and line marking at barrier ..................................................................................... 13
1.4 Completion ................................................................................................................ 13
1.4.1 Submissions .......................................................................................................................... 13
2 MEASUREMENT AND PAYMENT .............................................................. 14
2.1 Measurement ............................................................................................................ 14
2.2 Pay items ................................................................................................................... 14
LIST OF TABLES
Table 15C-1 Hold point table...................................................................................................................... 5
Table 15C-2 Witness point table ................................................................................................................ 6
Table 15C-3 Pay items table ..................................................................................................................... 14
![Page 4: RIGID SAFETY BARRIER 15C - tccs.act.gov.au · Method Statement Process description for the manufacture, supply and installation of any road safety ... Electrical conduits Location](https://reader034.vdocument.in/reader034/viewer/2022042211/5eb320d99457c50a382672a9/html5/thumbnails/4.jpg)
ACT Government 4
1 RIGID ROAD SAFETY BARRIER SYSTEMS
1.1 General
1.1.1 Responsibilities
1.1.1.1 General
Requirement: Provide concrete safety barriers from precast units, fixed forms or slip forming, as
documented or as directed. This Specification details the requirements for public domain, Type F and VCB
rigid road safety barrier systems. Proprietary systems shall be installed according to the manufacturer’s
specification.
1.1.1.2 Performance
Requirements: All new road safety barriers must be accepted by RMS for used on classified roads.
1.1.2 Cross references
1.1.2.1 Design Standards
General: The following Design Standards are related to this Specification:
MITS 00 Preliminaries
MITS 01 Traffic Management
MITS 10 Concrete works
MITS 11 Pavement marking
MITS 14 Road signs
1.1.3 Referenced documents
1.1.3.1 Standards
General: The following documents are incorporated into this Specification by reference:
Australian standards
AS 1289 Methods of testing soils for engineering purposes.
AS 1289.5.4.1 Soil compaction and density tests—Compaction control test—Dry density ratio, moisture variation and moisture ratio.
AS 1379 Specification and supply of concrete.
AS 1906 Retroreflective materials and devices for road traffic control purposes.
AS 1906.2 Retroreflective devices (non pavement application).
AS 3610 Formwork for concrete.
AS 3610.1 Documentation and surface finish
AS 3799 Liquid membrane-forming curing compounds for concrete.
AS/NZS 3845 Road safety barrier systems.
![Page 5: RIGID SAFETY BARRIER 15C - tccs.act.gov.au · Method Statement Process description for the manufacture, supply and installation of any road safety ... Electrical conduits Location](https://reader034.vdocument.in/reader034/viewer/2022042211/5eb320d99457c50a382672a9/html5/thumbnails/5.jpg)
ACT Government 5
1.1.4 Standard
1.1.4.1 General
Standard: To AS/NZS 3845.
Proprietary products: To TCCS Products previously considered for use list
1.1.5 Interpretation
1.1.5.1 Definitions
General: General: For the purpose of this Specification, the definitions of terms used to define the
components of the road reserve are in conformance with AS 1348, Glossary of Austroads Terms and
AGRD03, the definitions given below also apply:
Rigid road safety barrier system: A road safety barrier system where there is no observable dynamic
deflection. The deformation is contained in the impacting vehicle.
1.1.6 Hold points and witness points
1.1.6.1 Notice
General: Give written notice to the Authorised person so that the documented inspection and
submissions may be made to the Hold point table and the Witness point table.
Table 15C-1 Hold point table
Item Clause title Requirement Notice for inspection Release by
Materials
15C.1 General - Approved Products
Submit compliance certification
1 week prior to erection
Authorised Person
15C.2 Concrete – Properties Confirm concrete strength requirements for slip forming
5 working days before commencing works
Authorised Person
Execution
15C.3 Establishment – Method Statement
Process description for the manufacture, supply and installation of any road safety barrier system
7 working days before commencing works
Authorised Person
15C.4 Establishment – Location of barriers
Safety barrier set out approval 2 working days before construction
Authorised Person
15C.5 Manufacture of precast reinforced concrete –Procedures
Submit process details for the manufacture of precast safety barriers
5 days before commencing manufacture
Authorised Person
15C.6 Manufacture of precast reinforced concrete –Manufacturing records
Submit information on specific precast barriers
3 working days before use
Authorised Person
15C.7 Placing, compacting and finishing concrete – Slip forming
Submit proprietary extrusion machines for approval
5 working days prior to commencing works
Authorised Person
![Page 6: RIGID SAFETY BARRIER 15C - tccs.act.gov.au · Method Statement Process description for the manufacture, supply and installation of any road safety ... Electrical conduits Location](https://reader034.vdocument.in/reader034/viewer/2022042211/5eb320d99457c50a382672a9/html5/thumbnails/6.jpg)
ACT Government 6
Item Clause title Requirement Notice for inspection Release by
15C.8 Joints in concrete placed in-situ –Expansion joints
Jointing material for approval 3 working days before ordering
Authorised Person
15C.9 Curing – General Curing method and materials for approval
3 working days before placing concrete
Authorised Person
15C.10 Signage and line marking at barrier - Removal of temporary traffic control devices
Inspection of permanent works before removal of temporary works
24 hours before removal
Authorised Person
Table 15C-2 Witness point table
Item Clause title Requirement Notice for inspection
Execution
15C.1 Traffic safety – General Protect concrete barriers from impact by general traffic for a period of 7 days
Progressive
15C.2 Quality requirements – Concrete strength
Strength results to be submitted
Progressive
15C.3 Installation – Dowelled base fixings Provide dowels fixed in place for inspection
Prior to installing barriers
15C.4 Installation – Compaction of foundations
Provide the compacted base for inspection with relative compaction test results
Prior to installing barriers
15C.5 Installation – Electrical conduits Location of conduits subject to approval
24 hours before placing conduits
15C.6 Placing, compacting and finishing concrete – Fixed form construction
Immediately carry out any necessary repairs
Progressive
15C.7 Curing – Curing compound Certificate of compliance required
Prior to use
![Page 7: RIGID SAFETY BARRIER 15C - tccs.act.gov.au · Method Statement Process description for the manufacture, supply and installation of any road safety ... Electrical conduits Location](https://reader034.vdocument.in/reader034/viewer/2022042211/5eb320d99457c50a382672a9/html5/thumbnails/7.jpg)
ACT Government 7
1.2 Materials
1.2.1 General 1.2.1.1 Approved products
General: Transport Canberra require that all new safety barrier products must be accepted by Roads and
Maritime Services (RMS) NSW for use on classified roads within NSW prior to use in the ACT.
Certification: Submit compliance certification by the manufacturer that the barrier system meets all
specified criteria.
This is a HOLD POINT.
1.2.2 Concrete
1.2.2.1 Properties
Standard: To AS 1379.
Concrete: Supply and placement of concrete, steel reinforcement, formwork, tolerances, construction
joints and protection conform to MITS 10 Concrete works except as specified in this Specification.
Minimum concrete strength: 30MPa at 28 days for cast-in-situ formed concrete or precast concrete.
Slip form strength: Obtain approval for minimum strength for slip forming prior to commencing works.
This is a HOLD POINT.
Aggregate size: 20mm maximum nominal size.
Slump: Conform to the following specified slump at the point of placement:
Extrusion: 15mm.
Slip forming: 25mm.
Fixed forms: 75mm.
Ready mixed concrete: If ready-mixed concrete is used, mix and deliver the concrete to conform to AS
1379.
1.2.3 Reinforcement
1.2.3.1 General
Drawings: Reinforcing steel as shown on the drawings.
Cover: The minimum cover to the nearest concrete surface is 50mm unless documented otherwise on the
drawings.
Supports: Do not use wire, timber or coarse aggregate to support reinforcing steel. Use either concrete or
plastic.
![Page 8: RIGID SAFETY BARRIER 15C - tccs.act.gov.au · Method Statement Process description for the manufacture, supply and installation of any road safety ... Electrical conduits Location](https://reader034.vdocument.in/reader034/viewer/2022042211/5eb320d99457c50a382672a9/html5/thumbnails/8.jpg)
ACT Government 8
1.3 Execution
1.3.1 Provision for traffic
1.3.1.1 General
Requirement: Conform to MITS 01 Traffic Management.
1.3.2 Site establishment
1.3.2.1 Survey
Requirement: Confirm site surface and benchmarks. Conform to MITS 00 Preliminaries.
1.3.3 Traffic safety
1.3.3.1 General
Traffic control: To MITS 01 Traffic Management.
Material stacks: Locate any temporary stacks of new or surplus material associated with the works clear
of the traffic flow and behind the line of the safety barrier system being removed, under construction or
to be constructed.
Works program: Manage the sequence for construction to make sure that there are no traffic hazards or
safety issues for road users.
Protection from traffic: Protect constructed concrete barriers from impact by general traffic for a period
of 7 days.
This is a WITNESS POINT.
1.3.4 Establishment
1.3.4.1 Method Statement
Submit: Prior to the installation of any road safety barrier system, submit a process description for the
manufacture, supply and installation of road safety barrier systems for approval. Include the source of any
precast manufacturing or proprietary items.
This is a HOLD POINT.
1.3.4.2 Location of barriers
Set out: Set out the work so that all road safety barriers are located to conform to the drawings or as
directed. Peg or paint mark the start and finish points and line of safety barrier.
This is a HOLD POINT.
![Page 9: RIGID SAFETY BARRIER 15C - tccs.act.gov.au · Method Statement Process description for the manufacture, supply and installation of any road safety ... Electrical conduits Location](https://reader034.vdocument.in/reader034/viewer/2022042211/5eb320d99457c50a382672a9/html5/thumbnails/9.jpg)
ACT Government 9
1.3.5 Manufacture of precast reinforced concrete
1.3.5.1 Precast reinforced concrete
General: Conform to dimensions and details as shown on the drawings to conform to the requirements
for rigid road safety barrier systems in AS 3845.
Location of manufacturer: Precast concrete units may be supplied by an offsite manufacturer, or
manufactured onsite by the Contractor.
1.3.5.2 Procedures
Method statement for the precast units: Submit the proposed methods of manufacture, including
handling, transport, storage and erection, program of manufacture and delivery details.
This is a HOLD POINT.
1.3.5.3 Manufacturing records
Records: Submit the following information prior to erecting the precast concrete safety barriers:
Unit number or other identification mark.
Date and time of casting.
Concrete temperature and ambient temperature.
Date and time of lifting from the mould.
Quality and type of concrete materials.
Details of curing prior to lifting from mould.
Details of curing while stacked in the casting yard.
The date of transport to the site.
Any non-conformance or defect and any remedial works carried out.
This is a HOLD POINT.
1.3.6 Installation
1.3.6.1 General
Method: Unless otherwise stated on the drawings, the barrier may be precast, constructed in fixed forms
or slip-formed to the dimensions and details as shown on the drawings.
1.3.6.2 Connections to non-rigid barriers
Connections: If a non-rigid road safety barrier will be connected to a rigid road safety barrier, cast
anchorage assemblies into the road safety barrier to the dimensions and details shown on the drawings.
All other components for non-rigid road safety barriers are specified in MITS 15B Non-rigid safety barrier
systems.
1.3.6.3 Preparation of the base
Cleaning: Clean the base of all loose materials and dust before any works are commenced.
1.3.6.4 Dowelled base fixings
Location: Safety barriers constructed on new or existing pavements.
Cored holes: Provide 25mm diameter 200mm in length dowels in fine concrete or cement-mortar-filled
holes at regular staggered spacings to conform to AS 3845 and as shown on the drawings.
![Page 10: RIGID SAFETY BARRIER 15C - tccs.act.gov.au · Method Statement Process description for the manufacture, supply and installation of any road safety ... Electrical conduits Location](https://reader034.vdocument.in/reader034/viewer/2022042211/5eb320d99457c50a382672a9/html5/thumbnails/10.jpg)
ACT Government 10
Dowels: Dowel sizing and location as shown on the drawings.
This is a WITNESS POINT.
Precast spacings: If precast units are used, accurately align and space the cored holes.
1.3.6.5 Compaction of foundations
Firm base: Shape and compact the foundation material to form a firm base.
Relative compaction: Other than for barriers constructed on pavement courses, achieve relative
compaction of 95% to conform to AS 1289.5.4.1 for standard compactive effort. Submit test results.
This is a WITNESS POINT.
Pavement courses: If barriers placed on pavement courses, compact the foundation to the requirements
of the respective pavement course.
1.3.6.6 Electrical conduits
Cables location: For safety barriers containing street lighting standards, locate the conduit carrying
electrical cables in the base rather than in the barrier, as detailed on the drawings, unless otherwise
approved.
This is a WITNESS POINT.
Keyed conduit trench: Unless shown otherwise on the drawings, the conduit trench forms a key and no
dowels are required for slip-formed barriers.
1.3.6.7 Precast safety barrier segments
Mortar pad: After debonding the concrete surface, construct a (nominal) 10mm cement mortar pad
beneath the barrier full width and length.
1.3.7 Placing, compacting and finishing concrete
1.3.7.1 General
Continuous: Place concrete continuously between the ends of the concrete safety barrier systems or
between construction joints or within a precast safety barrier segment.
Placement: Except at properly formed construction joints, do not place fresh concrete against concrete
that has taken its initial set.
Compaction: Compact concrete thoroughly.
Formwork design: Conform to AS 3610 section 4.
Formwork construction: Conform to AS 3610.1.
Concrete finish: Finish surfaces uniform in appearance with a class 3 surface finish to AS 3610.1 unless
otherwise shown on drawings or directed.
Cracks: Construct/supply finished concrete barriers free of any cracks other than of movement joints no
wider than 0.05mm at any point on the surface at the completion of the curing period.
Rejected: Barriers with cracks wider then 0.05mm will be rejected.
![Page 11: RIGID SAFETY BARRIER 15C - tccs.act.gov.au · Method Statement Process description for the manufacture, supply and installation of any road safety ... Electrical conduits Location](https://reader034.vdocument.in/reader034/viewer/2022042211/5eb320d99457c50a382672a9/html5/thumbnails/11.jpg)
ACT Government 11
1.3.7.2 Fixed form construction
Tamping: Tamp unformed surfaces to bring a layer of fines to the surface and then screed to the
documented level.
High/low spots: Immediately following compaction and screeding, test unformed surfaces for high or low
spots and make any necessary corrections before the concrete hardens.
Repairs: Immediately after stripping the forms, use an approved method to perform any necessary repairs
to the formed surfaces.
This is a WITNESS POINT.
1.3.7.3 Hand finishing
Concrete finish: If hand finishing is required for slip form construction, provide a barrier of uniform
appearance.
1.3.7.4 Slip forming
Submit: Prior to extruding any concrete safety barrier, submit evidence that the proposed proprietary
machine can extrude the barrier shape to conform to the specification and drawings.
This is a HOLD POINT.
1.3.8 Alignment and level
1.3.8.1 Finish and appearance
Top and face of the barrier: True to line with the top surface of uniform width, free from humps, sags and
other irregularities.
1.3.8.2 Line and level tolerance
1.3.8.3 Surface tolerance
straightedge laid on top of or along any face of the
barrier except at grade changes or curves in which case the faces are to transition uniformly.
1.3.9 Joints in concrete placed in-situ
1.3.9.1 Contraction joints
Fixed or slip forms: Straight, square (± 5º) to the line of the barrier.
Depth: 50 (± 5) mm on all exposed surfaces at 4m spacing.
Method: Sawn or formed.
Sawing: Saw joints before uncontrolled cracking begins and within 12 hours after placing the concrete.
![Page 12: RIGID SAFETY BARRIER 15C - tccs.act.gov.au · Method Statement Process description for the manufacture, supply and installation of any road safety ... Electrical conduits Location](https://reader034.vdocument.in/reader034/viewer/2022042211/5eb320d99457c50a382672a9/html5/thumbnails/12.jpg)
ACT Government 12
1.3.9.2 Expansion joints
Type: Straight, square (± 5º) to the line of the barrier.
Width and spacing: As shown on the drawings.
Sealant: Fill with a preformed joint filler of bituminous fibreboard or an approved equivalent.
This is a HOLD POINT.
1.3.9.3 Pavement joints
Matching: If the barrier is cast on concrete pavement, continue the contraction, isolation, tied or
expansion joints in the pavement through the barrier to form a continuous joint through both structures.
1.3.9.4 Adjacent to pavement
Match: If the barrier is cast adjacent to a concrete pavement, form the contraction joints at 4m centres.
1.3.9.5 Precast units
Connections: Place precast units so that all connections are tight, secure and true in line and level.
1.3.10 Curing
1.3.10.1 General
Method: Cure concrete placed in safety barriers by either steam curing, moisture curing or by spraying an
approved curing compound on all exposed surfaces of the fresh concrete.
Submission: Submit the proposed method and materials for curing for approval prior to use.
This is a HOLD POINT.
Protection: Protect exposed surfaces from rain or other damage, until hard set has occurred.
Curing time: Maintain the curing membrane intact in a continuous and unbroken film for 7 days after
placing the concrete.
Damage: Make good any damage to the membrane by respraying the affected area as soon as the
damage occurs.
1.3.10.2 Curing compound
Slip-formed barriers: Provide wax emulsion, hydrocarbon resin or water borne curing compounds in
conformance with AS 3799 Class A Type 1, Class B Type 1-D or Class Z Type 1-D respectively.
Compliance: Provide a certificate of compliance for the curing compound from a laboratory with
appropriate NATA registration.
This is a WITNESS POINT.
Application rate: Apply the curing compound in a fine spray to provide even coverage at a rate of 0.2 l/m²
or the rate determined on the test certificate to achieve 95 % water retention, whichever is the greater.
Equipment on site: Keep equipment and materials for the curing operations on site at all times during slip-
forming of the barrier.
![Page 13: RIGID SAFETY BARRIER 15C - tccs.act.gov.au · Method Statement Process description for the manufacture, supply and installation of any road safety ... Electrical conduits Location](https://reader034.vdocument.in/reader034/viewer/2022042211/5eb320d99457c50a382672a9/html5/thumbnails/13.jpg)
ACT Government 13
1.3.11 Delineators
1.3.11.1 Fixing
Standards: Conform to AS 1906.2.
Method: Fix with brackets to the concrete safety barrier as shown on the drawings.
1.3.11.2 Arrangement and colour
Approaching colour: Arrange the delineators so that drivers approaching from either direction will see
only red reflectors on their left side and white reflectors on their right.
1.3.12 Signage and line marking at barrier
1.3.12.1 Permanent signage, and longitudinal line marking
Provide: Provide permanent signage, and longitudinal line marking adjacent to the concrete safety barrier
to conform to MITS 11 Pavement marking and MITS 14 Road signs.
1.3.12.2 Removal of temporary traffic control devices
Inspect: Do not remove temporary traffic control devices installed for the control of traffic before the
concrete safety barrier, permanent signing and longitudinal line marking have been inspected and
approved.
This is a HOLD POINT
1.4 Completion
1.4.1 Submissions Work as Executed Records: To MITS 00B Quality Requirements.
![Page 14: RIGID SAFETY BARRIER 15C - tccs.act.gov.au · Method Statement Process description for the manufacture, supply and installation of any road safety ... Electrical conduits Location](https://reader034.vdocument.in/reader034/viewer/2022042211/5eb320d99457c50a382672a9/html5/thumbnails/14.jpg)
ACT Government 14
2 MEASUREMENT AND PAYMENT
2.1 Measurement
2.1.1.1 General
Payments made to the Bill of Quantities: To MITS 00A General requirements, this Specification, the drawings and Pay items.
2.1.1.2 Methodology
The following methodology will be applied for measurement and payment:
Allow for all work, materials, testing and quality assurance requirements in each Pay Item.
Traffic control: To conform to MITS 01 Traffic Management.
Concrete safety barrier: To conform to this Specification and not MITS 10 Concrete works.
Linemarking and signage: To conform to MITS 11 Pavement marking and MITS 15A Guide posts.
Removal of road safety barriers: To MITS 15B Non-rigid safety barrier systems.
A concrete barrier transition shall be regarded as any change in shape from the standard section for the concrete safety barrier type.
2.2 Pay items
Table 15C-3 Pay items table
Item no
Pay items Unit of measurement Schedule of rates scope
15C.1 Road safety barrier
Linear metre of barrier constructed, measured along the centre line of the barrier, excluding terminal ends.
All activities associated with the supply and
installation of the barrier, including delineators.
Separate pay items shall be included for different
base conditions.
15C.2 Terminal ends
Each terminal section All activities associated with the supply and
installation of the terminals, including cast in
anchorage assemblies for the connection of non-
rigid road safety barriers.
A separate pay item shall be included in the
Contract for each terminal type.
![Page 15: RIGID SAFETY BARRIER 15C - tccs.act.gov.au · Method Statement Process description for the manufacture, supply and installation of any road safety ... Electrical conduits Location](https://reader034.vdocument.in/reader034/viewer/2022042211/5eb320d99457c50a382672a9/html5/thumbnails/15.jpg)
Transport Canberra and City Services
JULY 2019