RUN 11 RHIC MACHINE/EXPERIMENTS MEETING
7 Jun 2011
Agenda:
• √s = 200 GeV AuAu progress• 27 GeV Run (or other)
Run 11 Plan based on PAC recommendation/ALD Guidance and available funds 6/7/10 update
• 3 Jan, Begin cool-down to 4.5K • 8 Jan, Cool-down to 4.5K complete in both rings, preliminary setup begins• 24 Jan, 1 week Ramp-up with 8 hr/night beam to experiments• 11 Feb (machine and ~experiments), begin ~10 week physics run (√s = 500 GeV pp)• 7 Mar, cryo troubles, extended maintenance, 0900 hrs till 2000 hrs 14 Mar – lost 7.5 days• 17 Mar, power distribution problem, extended maintenance, 1930 hrs till 0315 hrs 20 Mar –
lost 2.3 days• 18 Apr, end 9.4 week physics run at √s = 500 GeV• 18 Apr jet target polarization measurement at injection (<5%) • 19 Apr, short maintenance followed by setup for √s = 18 GeV AuAu• 23 Apr, begin ~1 week physics run (√s = 19.6 AuAu)• 2 May 08:00, end 1.3 week physics run at √s = 19.6 GeV• 2 May, begin setup for √s = 200 AuAu• 5 May, begin 2 day Ramp-up with 8 hr/night beam to experiments• 6 May 11:37, begin ~8 week physics run at (√s = 200 GeV/n AuAu)
• 7 Jun- TODAY• 29 June, end 7.7 wk AuAu physics run at √s = 200 GeV/n , begin warm-up• 30 June, cryo warm-up ~ complete, end 25.4 weeks cryo operation
What’s missing :• Run into July?• 27 GeV AuAu; Uranium test/physics run• Low energy test run
PREP TIME REQ’D, NEED DECISION SOON!
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
5-M
ay
12
-Ma
y
19
-Ma
y
26
-Ma
y
2-J
un
9-J
un
16
-Ju
n
23
-Ju
n
Inte
gra
ted
Lu
min
os
ity
[m
b^
-1]
Run11 RHIC AuAu Integrated Luminosity for Physics(√s = 200 GeV/n)
STAR PHENIX Lmax Lmin PHENIX Run10
thru store 16022Tuesday 7 Jun
STAR Goal
PHENIX Goal
0
200
400
600
800
1000
1200
0
200
400
600
800
1000
1200
15750 15800 15850 15900 15950 16000 16050
Del
iver
ed lu
mi/
wee
k (m
b-1 )
lum
i/w
eek
for >
3 hr
stor
es a
nd 6
0% ti
me
at st
ore
(mb-1
)
Store Number
Run 11 100 x 100 GeV/n Au-Au (Phenix)60% time at store Integrated lumi Delivered Integrated Lumi/week (Physics)thru fill 16016
Goal
AnDY Revised 6/3/2011Singles Corrected (draft – another correction likely)
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
11-Feb 18-Feb 25-Feb 4-Mar 11-Mar 18-Mar 25-Mar 1-Apr 8-Apr 15-Apr
De
live
red
Lu
min
os
ity
(pb
-1)
Date
Run 11 250 x 250 GeV pp, Luminosity2.9 mb STAR, 2.7 mb PHENIX, 0.95 mb AnDY
STAR
PHENIX
ANDY(x10)
max
min
thru fill final 15472, 18 Apr
http://www.bnl.gov/cad/esfd
AGS-Booster-Tandem/Linac/EBIS Startup
RHIC Cryo Cooldown to 45 deg K
RHIC Cryo Cooldown/Warm-up
RHIC Cryo Operation
RHIC Cryo off
RHIC STAR & PHENIX
RHIC Research with s = 500 GeV pp
RHIC Research with s = 200 GeV /n AuAu
RHIC Research with s = 192 GeV /n UU
RHIC Research with s = 19.6 GeV /n AuAu
RHIC AnDY Drell-Yan Test (2:00 IR)
Low Energy Au test(?)
Extended Maintenance
NSRL (NASA Radiobiology)
BLIP (Isotopes)
BLIP (other)
Shutdown (RHIC)
C-A Operations-FY11
Program Element Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
FY 2011
31 May 11
setup with beams
Sep
concurrent with RHIC
ramp up luminosity
5 Oct
25.4 weeks
3Jan
24 Nov
setup as required
10 weeks physics
7.7 weeks
.4 weeks
as run/planned
11A 11B10C
31 Jun
10 Jun
15 Mar 20 May
9.4 weeks
1.3
30 Jun
Old information
√S = 200 GeV/n AuAu luminosity goals (24 May efficiencies)
STAR
2000 mb-1 sampled / 60% = 3300 mb-1 delivered
PHENIX
700 mb-1 sampled / 14% = 5000 mb-1 delivered
Estimate from PHENIX Beam Use Proposal – 15.8%• Live Time = 97%• Uptime = 65%• +/- 10 cm vertex = 25%
9.7 hour store comparing AnDY Lumi to STAR and PHENIX
Not singles corrected
LumiPHENIX = 5.88E9/2.7mb = 2.18 pb-1
STAR = 5.36E9/2.9 mb = 1.84 pb-1
AnDY = 0.52E9/0.95 mb = 0.55 pb-1
b*’sPHENIX ~0.7 mSTAR ~0.8 mAnDY ~ 3 m
9.7 hour store comparing AnDY Lumi to STAR and PHENIX
AnDY Lumi ~consistent with larger b* (x4 less Lumi)
Not singles corrected
PHENIX Lumi (singles corrected) for entire store = 3.09 pb-1
Store 15408 – AnDY projection• 2:00 b* = 3 meters
– AnDY fraction of store 15408 = 0.55/3.09 = 18%
• With 2:00 b* = 1.5 meters– AnDY fraction of store 15408 would have been 2x18%=36%
– using Fischer et.al. 11 May 2010 Table 7 lumi projections for Run12 Physics Weeks Max Lumi Min Lumi AnDY Est (1.5 m b*)
8 276 pb-1 98 pb-1 35-99 pb-1
10 388 pb-1 134 pb-1 48-140 pb-1
12 500 pb-1 170 pb-1 61-180 pb-1
100 pb-1 is not an unreasonable expectation for a 10-12 week run
0
20
40
60
80
100
120
0
200
400
600
800
1000
1200
15750 15800 15850 15900 15950 16000 16050
max
imum
lum
i (x
1026
cm-2
s-1)
lum
i/w
eek
for >
3 hr
stor
es a
nd 6
0% ti
me
at st
ore
(mb-1
)
Store Number
Run 11 100 x 100 GeV/n Au-Au (Phenix)60% time at store Integrated lumi Maximum Luminositythru fill 16016
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
0
10
20
30
40
50
60
15750 15800 15850 15900 15950 16000 16050
aver
age
bunc
h in
tens
ity a
t beg
inni
ng o
f sto
re(x
109 )
Max
imum
Lum
inos
ity
(x 1
026 cm
-2 s-1
)
Store Number
Run 11 100 x 100 GeV/n Au-Au (Phenix)Maximum Luminosity (>3 hr store) Blue/Yellow Average Bunch Intensitythru fill 16016
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
0
200
400
600
800
1000
1200
15750 15800 15850 15900 15950 16000 16050
aver
age
bunc
h in
tens
ity a
t beg
inni
ng o
f sto
re(x
109 )
lum
i/w
eek
for >
3 hr
stor
es a
nd 6
0% ti
me
at st
ore
(mb-1
)
Store Number
Run 11 100 x 100 GeV/n Au-Au (Phenix)60% time at store Integrated lumi Blue/Yellow Average Bunch Intensitythru fill 16016
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
0
10
20
30
40
50
60
15750 15800 15850 15900 15950 16000 16050
aver
age
bunc
h in
tens
ity a
t beg
inni
ng o
f sto
re(x
109 )
Max
imum
Lum
inos
ity
(x 1
026 cm
-2 s-1
)
Store Number
Run 11 100 x 100 GeV/n Au-Au (Phenix)Maximum Luminosity (>3 hr store) Blue/Yellow Average Bunch Intensitythru fill 16016
Fill 15974, not singles corrected
Fill 15974, with singles correction
26%
6%
Fill 15974
Goal 17-20
Goal 122
Peak Lumi goal 45 x 1026 cm-2s-1
Average Lumi goal 25 x 1026 cm-2s-1
Long emitt
x,y emitt
Blue/yellow ions
Store 15408 – AnDY projection• 2:00 b* = 3 meters
– AnDY fraction of store 15408 = 0.55/3.09 = 18%
• With 2:00 b* = 1.5 meters– AnDY fraction of store 15408 woulh have been 2x18%=36%
– using Fischer et.al. 11 May 2010 Table 7 lumi projections for Run12 Physics Weeks Max Lumi Min Lumi AnDY Est (1.5 m b*)
8 276 pb-1 98 pb-1 35-99 pb-1
10 388 pb-1 134 pb-1 48-140 pb-1
12 500 pb-1 170 pb-1 61-180 pb-1
100 pb-1 is not an unreasonable expectation for a 10-12 week run
i.e. there’s still an issue with singles corrections.
0.5000
0.7500
1.0000
1.2500
1.5000
1.7500
2.0000
0.0 20.0 40.0 60.0 80.0 100.0 120.0 140.0 160.0
Rati
o PH
ENIX
/STA
R ZD
C (s
ingl
es co
rrec
ted)
peak lumi (x 1026 cm-2s-1)
PHENIX/STAR Lumi Ratios, 250 GeV pp Run 11PHENIX/STAR Ratio NOT Singles Corrected
$(20)
$-
$20
$40
$60
$80
$100
$120 O
ct-0
0
Oct
-01
Oct
-02
Oct
-03
Oct
-04
Oct
-05
Oct
-06
Oct
-07
Oct
-08
Oct
-09
Oct
-10
Oct
-11
$/M
Wh
rBNL Energy Cost Billed Cost/MWhr
Without Balanced Billing
Balanced Billing Projection
RHIC ON
AGS SEB/FEB
NSRL
through Apr 2011
Through fill 15928 delivered 1474 mb-1
201 ub^-1 of 700 ub^-1 accumulated in 12cm vertex Efficiency = 201/1474 = 14%
Through 16 May 2011
0
5
10
15
20
25
30
35
40
45
501-
Jul-
081-
Aug
-08
1-S
ep-0
81-
Oct
-08
1-N
ov-0
81-
Dec
-08
1-Ja
n-09
1-F
eb-0
91-
Mar
-09
1-A
pr-0
91-
May
-09
1-Ju
n-09
1-Ju
l-09
1-A
ug-0
91-
Sep
-09
1-O
ct-0
91-
Nov
-09
1-D
ec-0
91-
Jan-
101-
Feb
-10
1-M
ar-1
01-
Apr
-10
1-M
ay-1
01-
Jun-
101-
Jul-
101-
Aug
-10
1-S
ep-1
01-
Oct
-10
1-N
ov-1
01-
Dec
-10
1-Ja
n-11
1-F
eb-1
11-
Mar
-11
1-A
pr-1
11-
May
-11
Dai
ly A
vera
ge
Po
wer
(M
W)
Date
BNL Energy Use FY 2009-11RHIC Cryo RHIC other
AGS-Exp Booster
AGS-Mach Tandem
CAD Bldg less SMD NSRL
Site Base BNL Peak-Av
Site total not recorded 30 Nov 09through Oct 2010
Through 16 May 2011
0.00
5.00
10.00
15.00
20.00
25.00
30.00
35.00
-30 -20 -10 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140
MW
Days since beginning of Run
RHIC Operations FY09-11CAD Power 09
CAD Power 10
CAD Power 11
4.00
4.50
5.00
5.50
6.00
6.50
7.00
7.50
8.00
-5 5 15 25 35 45 55 65 75 85 95 105 115 125 135
MW
Days since beginning of Run
RHIC Cryo Operations FY09-11RHIC Cryo 09
RHIC Cryo 10
RHIC Cryo 11
Through 16 May 2011
Possible oil contamination in one of the heat exchangers
Through 16 May 2011
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
-30 -20 -10 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140
MW
Days since beginning of Run
RHIC Cryo Operations FY09-11RHIC Cryo 09
RHIC Cryo 10
RHIC Cryo 11
0.50
0.75
1.00
1.25
1.50
1.75
2.00
15160 15210 15260 15310 15360 15410 15460
Rati
o PH
ENIX
/STA
R ZD
C (s
ingl
es co
rrec
ted)
fill number
Phenix/STAR Lumi Ratio, 250 GeV pp Run 11
Final Lumi should change as it appears there’s an issue with the singles correction
0
1
1
2
2
3
3
4
0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00
PHEN
IX p
b-1/
stor
e (s
ingl
es c
orre
cted
)
blue beam intensity at physics start (1E11/bunch)
Phenix Lumi vs beam intensity, 250 GeV pp Run 11
Run 11 Plan based on PAC recommendation/ALD Guidance and available funds 4/26/10 update (1/2)
• 3 Jan, Begin cool-down to 4.5K • 8 Jan, Cool-down to 4.5K complete in both rings, preliminary setup begins• ~11 Jan, 2 ⅟2 weeks beam setup for √s = 500 GeV pp in RHIC begins.• 15 Jan, power supply work/DX training complete• 17 Jan, first successful ramp• 19 Jan, 1st maint day• 24 Jan, 1 week Ramp-up with 8 hr/night beam to experiments• 11 Feb (machine and ~experiments), begin ~10 week physics run (√s = 500 GeV pp)• 16 Feb, AGS Jump Quads in routine operation for RHIC injection• 24 Feb, 9 MHz cavity in routine operation • 7 Mar, cryo troubles, extended maintenance, 0900 hrs till 2000 hrs 14 Mar – lost 7.5 days• 17 Mar, power distribution problem, extended maintenance, 1930 hrs till 0315 hrs 20 Mar – lost 2.3 days• 28 March – 1 April, PAC 2011• 15 April Continuing Resolution Ends, guidance to follow• 18 Apr, end 9.4 week pp physics run at √s = 500 GeV • 18 Apr jet target polarization measurement at injection (<5%) • 19 Apr, short maintenance followed by setup for √s = 18 GeV AuAu• 23 Apr, begin ~1 week physics run (√s = 19.6 AuAu)
• 2 May, end 1.3 week physics run at √s = 19.6 GeV
30.00
35.00
40.00
45.00
50.00
55.00
60.00
65.00
0 50 100 150 200 250 300
Pola
riza
tion
(%
)
energy (GeV)
Up down ramp, Blue Beampolarization with current analyzing powers
Up
Down
+11.0 %
-28.5 %
+6.8%
0.30
0.40
0.50
0.60
0.70
0.80
0.90
0 50 100 150 200 250 300
Asy
mm
etry
(x10
2 )
energy (GeV)
Up down ramp, Blue BeamAsymmetry
Up
Down
-15.0%
-11.3%
-5.0%
7 April Up-Down Ramp measurementBlue Beam
Current CNI average analyzing powers are:Energy AN
24 0.0144100 0.0122250 0.0147
30.00
35.00
40.00
45.00
50.00
55.00
60.00
65.00
0 50 100 150 200 250 300
Pola
riza
tion
(%
)
energy (GeV)
Up down ramp, Yellow Beampolarization (#1 only) with current analyzing powers
Up
Down
+24.4 % -23.1 %
-0.4 %
0.30
0.40
0.50
0.60
0.70
0.80
0.90
0 50 100 150 200 250 300
Asy
mm
etry
(X10
2 )
energy (GeV)
Up down ramp, Yellow Beamasymmetry (CNI #1 only)
Up
Down
-13.3%
-15.9%
-1.9%
7 April Up-Down Ramp measurementYellow Beam (only Yellow 1 was used as Yellow 2 was acting up)
Current CNI average analyzing powers are:Energy AN
24 0.0144100 0.0122250 0.0147
A good store with 9 MHzSat 2/26
Run 11, First overnight store, Mon Jan 24 00:12Fill number 14919,, s=500 GeV21 days since start of cool-down
20K
20 x 1011
• 28 x 27 bunches• b*=0.65 meters
For peak store lumi = 170 x 1030 cm-2s-1 (projected MAXIMUM)ZDC Rate ~ 400K (assuming 2.4 mb n-pair xsection)
Run 9, First overnight store at s=500 GeV22 days after start of cool-down
• 56 x 56 bunches• b*=0.7 meters
40K
40 x 1011
AGS pp log, 23 Feb 09, 00:26
PHENIX Goal (50% pol)
STAR Goal (50% pol)
Goals to be updated/corrected
Run-11 Au-Au luminosity projections 100 GeV/nucleon
Wolfram Fischer 38
Assume 6 weeks to ramp-up for min, and 8 weeks for max (stoch. cooling re-commissioning).Expect Lavg up to 25x1026cm-2s-1 (+25%).
[from Run-10 to max: b* = 0.75 0.65 m, Nb = 1.1 1.1x109, more cooling]
PHENIX Goal (0.7 recorded)
?? (complicated)
STAR Goal (TBD)
Goals to be updated/corrected