S Flores Street Improvement Project4th Community Briefing
Art Reinhardt PE CFM Assistant DirectorArt Reinhardt, PE, CFM, Assistant DirectorTransportation & Capital Improvements (TCI)
1
May 19, 2014
Agenda
• Project Background• Project Background• April 2014 Meeting• Preferred Alternate Route• Next Steps• Next Steps• Questions
2Main & Soledad – Concept PlanSource: Downtown Transportation Study – 2012
Project Background
• Bike Master Plan id tifi d 5 3 ilidentified 5.3 mile segment of bicycle facilitiesalong S Flores corridor
• Three phasesPhase I completed in 2012, Cevallos/
N lit t Mit h ll (1 1 il )Nogalitos to Mitchell (1.1 miles), ~$425,000
Phase II completed in 2013, Mitchell $to SE Military (2.8 miles), ~$995,000
Phase III planned in 2017, SE Military to Ashley (1.4 miles), ~$240,000Existing width can support bike
lanes
3
April 2014 Meeting
Alt t R t• Alternate RoutesSayers Route ($478,000)1.3 miles of bike lanes removed
Hart Route ($623,320)1.6 miles of bike lanes removed
Th /M l R ($ 00 400)Theo/Malone Route ($700,400)2.3 miles of bike lanes removed
Alamo/Probandt Route ($509,000)Alamo/Probandt Route ($509,000)3.9 miles of bike lanes removed1.4 miles of bike lanes addedTxDOT roads
4
Preferred Alternate Route• Theo/Malone RouteTheo/MaloneTheo/MaloneUtilize existing bike lanes
Probandt Utilize existing shared use path
Mission Rd (Theo to Hart)Utilize existing bike lanesUtilize existing bike lanes
Mission Rd (Hart to E White)Existing road and bike lanes need to be
rehabilitatedE White & VFW Blvd Existing road needs to be rehabilitatedExisting road needs to be rehabilitated
and bike lanes addedBexar County project will include bike
lanes
5
lanesPadre DrUtilize existing bike lanes
Next Steps
• Present Preferred Alternate Route (Theo/Malone) to City( ) yCouncil on May 29, 2014 (http://www.sanantonio.gov/councilto view agenda)
• Timeline to implement Alternate Route along S FloresDevelop bid package and specifications ~ 1 monthp p g pAdvertise project to solicit bids ~ 1 monthReview bids and award contract ~ 2 monthsImplement modifications to S Flores ~ 2 monthsTotal ~ 6 months
• Timeline to implement Alternate Route along Mission Rd and E WhiteFY 2015 Budget adoption on October 1 2014
6
FY 2015 Budget adoption on October 1, 2014Implement rehabilitation on Mission Rd and E White ~ 2 months