Download - saipem australia - EIANZ
saipem australiap
Strategic thinking on a daily basis: integration Strategic thinking on a daily basis: integration of environmental management, regulatory
approvals, cultural heritage, land liaison and approvals, cultural heritage, land liaison and construction.
Sue Korecki – Compliance Manager
15th October 2013
AIM FOR CONSTRUCTION – Utilising an example
Access into the Gladstone State Development Area (GSDA) from the Bruce Highway (KP 383.1)
saipem australiap
2
Background: GSDA Gladstone State Development Area
‐ Declared in 1993.‐ Located 15 kms NW of Gladstone Located 15 kms NW of Gladstone. ‐ Land uses considered suitable for the Gladstone
SDA include: SDA include: port-related activities and industries necessary
t t j i d t i l d l t to support major industrial development; materials transportation infrastructure and utility
and service infrastructure; gas transportation infrastructure and other
saipem australia
compatible infrastructure.
p
3
saipem australiap
4
Infrastructure User Definition
means a person whom a Landowner has authorisedto use part of the GSDA for the purposes of construction, operation, maintenance, alteration, repair and replacement of Infrastructure but excludes for the avoidance of doubt a Grazierexcludes, for the avoidance of doubt, a Grazier.
saipem australiap
5
Flow chartEnvironment ˃
Ecological Survey Incl. Weed Survey: Complete 1 year prior ˃ Build Washdown Facility: 1- 2 weeks
˃ Weed Treatment: 10-14 days
˃ Fauna Survey: 7 days
Regulatory Approvals ˃TMR Application for Road Corridor P it 20 b i dg y pp Permit: 20 business days
˃ GSDA ˃ 5 days notification - to enter the area
˃ 1 day notification - for preliminary works
˃ 15 days notification - major construction works
Cultural Heritage ˃Cultural Heritage Survey and Sign-Off ˃ Survey for ROW: prior to Construction (Company)
Survey for EWSs and ATs off ROW: 10 business ˃
Survey for EWSs and ATs off ROW: 10 business days' notice
Land Liaison ˃Landholder and Leaseholder Approvals ˃ Amendment to GSDA Licence (C-G): 4-6 weeks
saipem australia
˃Access, Conduct and Compensation Agreements (Leaseholder): 1 day - weeks
˃ Temporar Use Notice (C G) 1 2 eeksp
6
˃ Temporary Use Notice (C-G): 1-2 weeks
Regulatory Approvals
Land Use Protocol for Gladstone State Development Area – Materials Transportation and Services pCorridor Precinct –Notifications to Leaseholders
saipem australiap
7
Gladstone State Development Area (GSDA)
The Infrastructure User must:( ) i l 5 B i D ' i (a) give at least 5 Business Days' written notice to the Landowner and the relevant GSDA Users that the Infrastructure User GSDA Users that the Infrastructure User proposes to enter onto the Licensed Area, including details of the manner in which the gGSDA;(b) provide a list of activities, including the location, the proposed work program and the timing, proposed to be carried out on the Licensed Area
saipem australia
Licensed Area.
p
8
GSDA
Next, the Infrastructure User must provide notice to the Landowner and all GSDA Users notice to the Landowner and all GSDA Users who occupy the relevant part of the GSDA as follows before entering onto its Licensed Area:follows before entering onto its Licensed Area: (a) provide 24 hours' notice to the Landowner and all relevant GSDA Users prior pto preliminary works, such as surveying activities; (b) 15 Business Days' notice for major construction activities.
saipem australiap
9
Designated Access Point (DAP) – KP 383. 1 (Bruce Highway).
- TMR – Road Corridor Permit Approval required for access off the Bruce Highway directly onto Saipem’s g y y pROW. Lots of negotiations and a potential standstill to Construction commencing in the GSDA.
Photo: No approval yet to access from the Bruce Highway –g ytemporary signage
saipem australiap
10
DAP – KP 383. 1
Potential Delays: look for alternatives – utilizing the MCJV DAP onto their ROW and then utilize an AT to Saipem’s ROW.
Photo: No approval yet to access from ythe Bruce Highway – vehicles parked on the side of the road.
saipem australiap
11
DAP – KP 383. 1
Map: The different gasdifferent gas pipeline corridors and the proposedthe proposed access from MCJV ROW.
saipem australiap
12
DAP – KP 383. 1
Cultural Heritage potentially an issue, so utilized an existing farm track (with leaseholder’s consent)
Photo: Existing farmPhoto: Existing farm track – no works required. Therefore, no CH approvalno CH approval required.
saipem australiap
13
DAP – KP 383. 1
Gained consent from TMR
saipem australiap
14
Environmental
Ecological Survey(a) conduct a baseline
survey of its Licensed Area;
(b) prepare a Condition Report; and
( ) i f th (c) give a copy of the survey and Condition Report to the C-G Report to the C G, prior to commencing the works.
saipem australiap
15
Environmental
Fauna Survey – 7 days prior to y pthe works commencing
saipem australia
Sugar Gliderp
16
Environmental
Weed survey: as a part of the Condition Report
Map: GSDA, GRT v Clean area, washarea, wash downs
* Weed Treatment
ll 10normally 10-14 days prior. Different for
saipem australia
GRT
p
17
Environmental
Machinery and Vehicle washdown requirements; (a) Must be washed on entry into the GSDA and out (a) Must be washed on entry into the GSDA and out
from the GSDA (need a washdown at the DAP at Bruce Highway).
(b) However, machinery and vehicles coming straight from the CICSDA did not need another washdown.
Had to build a washdown on the ROW as the Temporary Use Notice (TUN) for EWS 194 from the C G was taking time
saipem australia
C-G was taking time.
p
18
Environmental
Photos: Building and use of Wash Down Facility at KP 383
saipem australiap
19
Cultural Heritage
pre-construction PCCC CH survey of the ROWFor EWSs (off the ROW) – 10 business days’ notice, ( ) y ,must submit a Request for Cultural Heritage ClearanceEWS must be pegged prior to initial CH survey.
Photo: NO GO ZONE for Cultural HeritageCultural Heritage
saipem australiap
20
Land Liaison
Notification to the leaseholders/ Graziers, as per the GSDA Land Use Protocol.Extra Work Spaces:
(a) EWSs inside the GSDA corridor - Temporary Use Notices from the C-G
(b) EWSs outside the GSDA corridor –A d t t th GSDA li f th CAmendment to the GSDA licence from the C-G
(c) EWSs outside the GSDA corridor Access (c) EWSs outside the GSDA corridor – Access Conduct and Compensation Agreements with the leaseholders
saipem australia
the leaseholders
p
21
Environmental
saipem australiap
22
GO NO-GO
When Signed off and received from Company
construction – construction is clear to proceed.proceed.
saipem australiap
23
AIM Complete
saipem australiap
24Photos: Construction of the GLNG Gas Transmission Pipeline